Vendor Name | Department/Facility | Contract Number | Current Contract Amount | Spending to Date | Contract Start Date | Contract End Date | Contract Description | Contract Type | Original Contract Approved/Filed Date |
---|---|---|---|---|---|---|---|---|---|
DIDONATO ASSOCIATES ENGINEERING & ARCHITECTURE PC | SUNY at Buffalo | T000312 |
$223,834.37
|
$223,834.37 |
01/22/2010 | 05/30/2013 | DESIGN CONSULTING SERVICES - PROJECT 2008-181 ALUMNI ARENA MODIFICATIONS | Contracts Not Subject to OSC Pre-Audit | 01/25/2010 |
HUNT ENGINEERS ARCHITECTS LAND SURVEYORS & LANDSCAPE ARCHITECT DPC | SUNY at Buffalo | T000320 |
$68,543.13
|
$68,543.00 |
02/01/2010 | 06/30/2011 | DESIGN CONSULTING SVCS - PROJECT 2010-091 SOUTH CAMPUS STAGING AREA | Contracts Not Subject to OSC Pre-Audit | 01/10/2011 |
BUFFALO ENGINEERING PC | SUNY at Buffalo | T000326 |
$49,869.00
|
$49,869.00 |
02/04/2010 | 12/31/2011 | DESIGN CONSULTING SERVICES - PROJECT 2010-090 FIRE ALARM SYSTEM | Contracts Not Subject to OSC Pre-Audit | 01/10/2011 |
HAMILTON HOUSTON LOWNIE ARCHITECTS LLC | SUNY at Buffalo | T000325 |
$249,264.00
|
$249,264.00 |
03/01/2010 | 09/30/2012 | DESIGN CONSULTING SVCS - PROJECT 2005-243 WENDE HALL EXTERIOR RESTORATION | Contracts Not Subject to OSC Pre-Audit | 05/05/2011 |
STANLEY STEEMER WESTERN NY | SUNY at Buffalo | T000329 |
$250,000.00
|
$10,000.00 |
03/01/2010 | 02/28/2015 | EMERGENCY BASEMENT CLEANUP | Contracts Not Subject to OSC Pre-Audit | 03/29/2010 |
CUBRC INC | SUNY at Buffalo | X001155 |
$44,852.00
|
$0.00 |
03/08/2010 | 03/07/2030 | REVENUE FOR FIBER OPTIC ACCESS AND MAINTENANCE | Revenue Generating - Other | 06/30/2010 |
ALLIED WASTE SERVICES OF NORTH AMERICA LLC | SUNY at Buffalo | T000344 |
$250,000.00
|
$244,654.15 |
03/17/2010 | 05/16/2013 | WASTE REMOVAL - ROLL-OFFS AND COMPACTOR | Contracts Not Subject to OSC Pre-Audit | 06/08/2010 |
MOLLENBERG-BETZ INC | SUNY at Buffalo | T500014 |
$181,934.57
|
$181,934.57 |
03/29/2010 | 07/31/2012 | PROJECT 2008-155(C) NORTH CAMPUS UTILITY INFRASTRUCTURE BUILD-OUT (WAS D0C1156) | Contracts Not Subject to OSC Pre-Audit | 02/29/2012 |
BERGMANN ASSOCIATES ARCHITECTS ENGINEERS LANDSCAPE ARCHITECTS SURVEYORS DPC | SUNY at Buffalo | T000331 |
$49,693.00
|
$48,699.14 |
03/30/2010 | 08/30/2011 | DESIGN CONSULTING SERVICES-FARBER PENTHOUSE ROOF REPLACEMENT | Contracts Not Subject to OSC Pre-Audit | 03/31/2010 |
PATRICK DEVELOPMENT INC | SUNY at Buffalo | T500019 |
$3,087,757.27
|
$2,602,397.82 |
03/31/2010 | 05/15/2012 | PROJECT 2008-127 FARBER CONSTRUCTION 3RD & 4TH FLOORS | Contracts Not Subject to OSC Pre-Audit | 11/30/2011 |
CORR DISTRIBUTORS INC | SUNY at Buffalo | T000333 |
$335,000.00
|
$334,937.97 |
04/01/2010 | 03/31/2014 | CUSTODIAL EQUIPMENT - MAINTENANCE AND REPAIRS | Contracts Not Subject to OSC Pre-Audit | 05/21/2010 |
UNITED MEMORIAL FUNERAL HOME INC | SUNY at Buffalo | T000330 |
$160,000.00
|
$6,666.00 |
04/04/2010 | 04/03/2014 | CADAVER TRANSPORTATION SERVICES | Contracts Not Subject to OSC Pre-Audit | 03/17/2010 |
OCONNELL ELECTRIC COMPANY INC | SUNY at Buffalo | T000340 |
$250,000.00
|
$127,120.58 |
05/01/2010 | 04/30/2011 | ELECTRICAL SWITCH GEAR TESTING | Contracts Not Subject to OSC Pre-Audit | 05/19/2010 |
TITAN DEVELOPMENT INC | SUNY at Buffalo | T000334 |
$197,495.00
|
$197,495.00 |
05/10/2010 | 05/31/2011 | FUND PROJECT #2010-056 CHILD CARE CTR UG UTILITIES | Contracts Not Subject to OSC Pre-Audit | 12/21/2010 |
AUDIO-VIDEO CORPORATION | SUNY at Buffalo | T000349 |
$17,235.00
|
$17,235.00 |
05/17/2010 | 05/10/2011 | NYS CONTRACT CMT552A FOR LCD MONITOR/AVC SYSTEM | Contracts Not Subject to OSC Pre-Audit | 05/18/2010 |
CROWN PARTNERS LLC | SUNY at Buffalo | T000347 |
$100,470.00
|
$100,383.50 |
05/17/2010 | 12/31/2010 | CQ5 ARCHITECT-DEVELOPER | Contracts Not Subject to OSC Pre-Audit | 02/01/2011 |
WORKING KNOWLEDGE LLC | SUNY at Buffalo | T000350 |
$47,845.00
|
$0.00 |
05/20/2010 | 05/20/2011 | RECORDING & OBSERVATION SYSTEM NYS CONTRACT# PT64309 | Contracts Not Subject to OSC Pre-Audit | 05/21/2010 |
HUNT ENGINEERS ARCHITECTS LAND SURVEYORS & LANDSCAPE ARCHITECT DPC | SUNY at Buffalo | T000338 |
$143,074.00
|
$143,074.00 |
05/24/2010 | 12/31/2011 | DESIGN CONSULTING SVCS - PROJECT 2010-017 S. CAMPUS INTERIOR STORM & SANITARY SEPARATION STUDY | Contracts Not Subject to OSC Pre-Audit | 01/10/2011 |
M E ENGINEERING PC | SUNY at Buffalo | T000337 |
$59,320.00
|
$59,320.00 |
05/25/2010 | 06/30/2013 | KIMBALL SPRINKLER SYSTEM PROJECT 2008-180 | Contracts Not Subject to OSC Pre-Audit | 12/16/2011 |
EPIC CONTRACTING OF ORCHARD PARK INC | SUNY at Buffalo | T000360 |
$250,000.00
|
$111,900.00 |
06/01/2010 | 05/31/2011 | ASBESTOS ABATEMENT SERVICES | Contracts Not Subject to OSC Pre-Audit | 07/20/2010 |
NICHOLS LONG & MOORE CONSTRUCTION CORP | SUNY at Buffalo | T000341 |
$250,000.00
|
$31,851.76 |
06/01/2010 | 05/31/2011 | EMERGENCY WATER & SEWER REPAIR SERVICE | Contracts Not Subject to OSC Pre-Audit | 06/03/2010 |
URS CORPORATION-NY | SUNY at Buffalo | T500007 |
$1.00
|
$0.00 |
06/09/2010 | 05/08/2014 | CONSULTANT TERM AGREEMENT-ARCHITECTURAL & ENGINEERING SERVICES. | Contracts Not Subject to OSC Pre-Audit | 06/22/2011 |
OCONNELL ELECTRIC COMPANY INC | SUNY at Buffalo | T000363 |
$250,000.00
|
$242,619.77 |
06/15/2010 | 06/14/2011 | ELECTRICAL SYSTEM SERVICES | Contracts Not Subject to OSC Pre-Audit | 07/20/2010 |
LEDGE CREEK DEVELOPMENT INC | SUNY at Buffalo | T000351 |
$201,804.45
|
$201,804.45 |
06/21/2010 | 07/01/2011 | PROJECT 2005-243 WENDE HALL LOADING DOCK | Contracts Not Subject to OSC Pre-Audit | 09/22/2011 |
CJS ARCHITECTS LLP | SUNY at Buffalo | T500013 |
$280,915.60
|
$280,915.60 |
06/24/2010 | 12/31/2019 | DESIGN PRJ 2009-156 MFAC TUNNEL-UTILITY SERVICES RENEWAL; FORMERLY D0C1171 | Contracts Not Subject to OSC Pre-Audit | 06/20/2011 |
APPLIED BUSINESS SYSTEMS INC | SUNY at Buffalo | T000372 |
$136,117.50
|
$94,494.00 |
07/01/2010 | 06/30/2015 | DOMESTIC MAILINGS AND LITERATURE FULFILLMENT | Contracts Not Subject to OSC Pre-Audit | 08/26/2010 |
U&S SERVICES LLC | SUNY at Buffalo | C001185 |
$173,270.00
|
$135,658.30 |
07/01/2010 | 06/30/2013 | ANDOVER CONTROLS-NORTH/SOUTH/DOWNTOWN CAMPUS | Equipment - Other | 04/20/2011 |
SIEMENS INDUSTRY INC | SUNY at Buffalo | T000375 |
$150,000.00
|
$0.00 |
07/01/2010 | 06/30/2013 | CHILLER MAINTENANCE | Contracts Not Subject to OSC Pre-Audit | 08/27/2010 |
SIEMENS INDUSTRY INC | SUNY at Buffalo | C001184 |
$255,134.00
|
$214,941.96 |
07/01/2010 | 06/30/2013 | EMS SERVICES - NORTH/SOUTH/DOWNTOWN | Equipment - Other | 05/19/2011 |
WASHER SOLUTIONS INCORPORATED | SUNY at Buffalo | T000366 |
$19,900.00
|
$19,900.00 |
07/01/2010 | 06/30/2011 | FUND CONTRACT FOR 10-11 FY | Contracts Not Subject to OSC Pre-Audit | 07/30/2010 |
WASHER SOLUTIONS INCORPORATED | SUNY at Buffalo | T000364 |
$122,400.00
|
$122,400.00 |
07/01/2010 | 06/30/2015 | FUND 10-11 CONTRACT | Contracts Not Subject to OSC Pre-Audit | 08/02/2011 |
U&S SERVICES LLC | SUNY at Buffalo | T000376 |
$125,000.00
|
$0.00 |
07/01/2010 | 06/30/2013 | CHILLER MAINTENANCE | Contracts Not Subject to OSC Pre-Audit | 08/27/2010 |
SIEMENS INDUSTRY INC | SUNY at Buffalo | T000374 |
$125,000.00
|
$0.00 |
07/01/2010 | 06/30/2013 | CHILLER MAINTENANCE | Contracts Not Subject to OSC Pre-Audit | 08/27/2010 |
U&S SERVICES LLC | SUNY at Buffalo | T000377 |
$125,000.00
|
$0.00 |
07/01/2010 | 06/30/2013 | CHILLER MAINTENANCE | Contracts Not Subject to OSC Pre-Audit | 08/27/2010 |
JOHNSON CONTROLS INC | SUNY at Buffalo | T000378 |
$125,000.00
|
$86,712.23 |
07/01/2010 | 06/30/2013 | CHILLER MAINTENANCE (EMS) SERVICE | Contracts Not Subject to OSC Pre-Audit | 08/26/2010 |
NANCY J PARISI | SUNY at Buffalo | T000369 |
$12,000.00
|
$4,852.50 |
07/01/2010 | 06/30/2011 | PHOTOGRAPHY SERVICES | Contracts Not Subject to OSC Pre-Audit | 08/18/2010 |
U&S SERVICES LLC | SUNY at Buffalo | T000367 |
$89,900.00
|
$89,900.00 |
07/06/2010 | 11/30/2010 | SECURITY SYSTEM & BUILDING CONTROLS/NYS CONTRACT PT63600/77201 | Contracts Not Subject to OSC Pre-Audit | 08/13/2010 |
ALLGAIER CONSTRUCTION CORP | SUNY at Buffalo | T500024 |
$57,616.50
|
$57,616.50 |
07/14/2010 | 10/31/2011 | PROJECT 2010-162 O'BRIAN HALL-RENOVATE SE VESTIBULE; FORMERLY D0C1168 | Contracts Not Subject to OSC Pre-Audit | 12/13/2011 |
PARISE MECHANICAL INC | SUNY at Buffalo | T500030 |
$86,679.50
|
$86,679.50 |
07/15/2010 | 04/30/2012 | PROJECT 2007-015 KIMBALL-REPLACE AHU'S/ASBESTOS ABATEMENT; FORMERLY D0C1158 | Contracts Not Subject to OSC Pre-Audit | 10/17/2011 |
PARISE MECHANICAL INC | SUNY at Buffalo | D0C1158 |
$465,737.50
|
$465,737.50 |
07/15/2010 | 10/01/2011 | FUND KIMBALL AIR HANDLER REPLACEMENT & ASBESTOS ABATEMENT | Construction - Building | 11/04/2011 |
MLP PLUMBING & MECHANICAL INC | SUNY at Buffalo | T500020 |
$108,454.68
|
$108,454.68 |
07/15/2010 | 01/01/2013 | PROJECT 2010-058 FRONCZAK-REPLACE AHU COOLING COILS & MER; FORMERLY D0C1162 | Contracts Not Subject to OSC Pre-Audit | 02/08/2012 |
GROVE ROOFING SERVICES INC | SUNY at Buffalo | T500010 |
$136,599.50
|
$136,599.50 |
07/15/2010 | 02/28/2012 | PROJECT 2010-132 FARBER - 4TH FLOOR & PENTHOUSE ROOF REPLACEMENTS | Contracts Not Subject to OSC Pre-Audit | 09/12/2011 |
M E ENGINEERING PC | SUNY at Buffalo | T000365 |
$136,882.00
|
$136,882.00 |
07/21/2010 | 03/15/2011 | DESIGN SERVICES - PROJECT 2010-145 BAKER CHILLED WATER PLANT - CHILLED WATER LOOP - FLOW ANALYSIS | Contracts Not Subject to OSC Pre-Audit | 09/21/2010 |
OCONNELL ELECTRIC COMPANY INC | SUNY at Buffalo | T500028 |
$343,074.71
|
$343,074.71 |
07/29/2010 | 02/28/2013 | PROJECT 2008-168B ELECTRICAL SUBSTATION; FORMERLY D0C1172 | Contracts Not Subject to OSC Pre-Audit | 08/18/2011 |
TRAVEL TEAM INCORPORATED | SUNY at Buffalo | T000354 |
$17,842.00
|
$17,573.00 |
08/01/2010 | 06/30/2011 | FUND 10/11 CONTRACT FOR FALL BUSSING | Contracts Not Subject to OSC Pre-Audit | 08/11/2010 |
D&F TRAVEL INCORPORATED | SUNY at Buffalo | T000358 |
$32,450.00
|
$32,450.00 |
08/01/2010 | 06/30/2011 | ATHLETIC BUS SERVICE - MEN'S FOOTBALL TEAM, 2010/2011 | Contracts Not Subject to OSC Pre-Audit | 08/10/2010 |
D&F TRAVEL INCORPORATED | SUNY at Buffalo | T000357 |
$21,675.00
|
$16,380.00 |
08/01/2010 | 06/30/2011 | ATHLETIC BUS SERVICE - WOMEN'S SOCCER TEAM, 2010/2011 | Contracts Not Subject to OSC Pre-Audit | 08/10/2010 |
D&F TRAVEL INCORPORATED | SUNY at Buffalo | T000359 |
$7,441.25
|
$7,441.25 |
08/01/2010 | 06/30/2011 | ATHLETIC BUS SERVICE - WOMEN'S ROWING TEAM, 2010/2011 | Contracts Not Subject to OSC Pre-Audit | 08/10/2010 |
GOLDEN TRIANGLE ASSOCIATES LLC | SUNY at Buffalo | T000386 |
$82,044.00
|
$36,585.61 |
08/01/2010 | 05/01/2012 | UNIVERSITY AT BUFFALO FOOTBALL RECRUITING WEEKENDS | Contracts Not Subject to OSC Pre-Audit | 09/07/2011 |
ALLPRO PARKING LLC | SUNY at Buffalo | T000348 |
$7,740.00
|
$7,740.00 |
08/01/2010 | 07/31/2011 | PARKING SERVICES FOR UB HOME FOOTBALL GAMES | Contracts Not Subject to OSC Pre-Audit | 07/29/2010 |