SEA BREEZE GENERAL CONSTRUCTION INC | State University Construction Fund | T006467 |
$1,647,944.00
|
$1,647,944.00 |
12/11/2018 | 12/11/2020 | SUCF291015 Roof Replacement C | Contracts Not Subject to OSC Pre-Audit | 12/28/2018 |
VMJR COMPANIES LLC | State University Construction Fund | T006466 |
$2,337,852.00
|
$2,337,852.00 |
12/05/2018 | 12/05/2020 | SUCF401002 Renovate 3 Union A | Contracts Not Subject to OSC Pre-Audit | 12/06/2018 |
DOW ELECTRIC INC | State University Construction Fund | T006415 |
$1,000,000.00
|
$26,853.00 |
04/27/2018 | 04/27/2019 | SUCF80X700 Job Order Contract | Contracts Not Subject to OSC Pre-Audit | 11/21/2018 |
RODEMS CONSTRUCTION CO INC | State University Construction Fund | T006463 |
$12,413,713.00
|
$12,413,713.00 |
11/02/2018 | 10/22/2021 | SUCF30XB05 Rehabilitate Exter | Contracts Not Subject to OSC Pre-Audit | 11/08/2018 |
NELCORP ELECTRICAL CONTRACTING CORP | State University Construction Fund | T006460 |
$912,337.00
|
$912,337.00 |
10/25/2018 | 04/15/2021 | SUCF251015 Upgrade Building F | Contracts Not Subject to OSC Pre-Audit | 10/31/2018 |
RSI ROOFING INC | State University Construction Fund | T006433 |
$685,725.00
|
$685,725.00 |
10/19/2018 | 07/01/2020 | SUCF091017 Rehab Roofs Variou | Contracts Not Subject to OSC Pre-Audit | 10/29/2018 |
WENDEL WD ARCHITECTURE ENGINEERING SURVEYING & LANDSCAPE ARCHITECTURE PC | State University Construction Fund | T006441 |
$2,000,000.00
|
$452,919.24 |
10/24/2018 | 07/26/2029 | SUCF 80800 Commissioning Serv | Contracts Not Subject to OSC Pre-Audit | 10/26/2018 |
WILKINS MECHANICAL INC | State University Construction Fund | T006461 |
$1,226,338.00
|
$1,226,338.00 |
10/23/2018 | 09/16/2020 | SUCF251018 Replace Boilers & | Contracts Not Subject to OSC Pre-Audit | 10/24/2018 |
GUTH DECONZO CONSULTING ENGINEERS PC | State University Construction Fund | T006439 |
$2,000,000.00
|
$404,303.62 |
10/16/2018 | 05/04/2027 | SUCF 80800 Commissioning Serv | Contracts Not Subject to OSC Pre-Audit | 10/18/2018 |
ANDREW BERMAN ARCHITECT PLLC | State University Construction Fund | T006457 |
$2,508,000.00
|
$1,998,696.71 |
10/12/2018 | 04/12/2025 | SUCF281007 Renovate Crosby Ha | Contracts Not Subject to OSC Pre-Audit | 10/15/2018 |
HORIZON ENGINEERING ASSOCIATES LLP | State University Construction Fund | T006440 |
$2,000,000.00
|
$278,464.57 |
10/04/2018 | 12/12/2028 | SUCF 80800 Commissioning Serv | Contracts Not Subject to OSC Pre-Audit | 10/12/2018 |
GENESYS ENGINEERING PC | State University Construction Fund | T006438 |
$2,000,000.00
|
$604,168.35 |
10/04/2018 | 10/20/2027 | SUCF 80800 Commissioning Serv | Contracts Not Subject to OSC Pre-Audit | 10/12/2018 |
CJ BROWN ENERGY & ENGINEERING PC | State University Construction Fund | T006437 |
$2,000,000.00
|
$174,536.51 |
10/04/2018 | 10/25/2027 | SUCF 80800 Commissioning Serv | Contracts Not Subject to OSC Pre-Audit | 10/12/2018 |
NELCORP ELECTRICAL CONTRACTING CORP | State University Construction Fund | T006456 |
$2,490,970.00
|
$2,490,970.00 |
09/24/2018 | 04/01/2021 | SUCF071016 Site Utility Upgra | Contracts Not Subject to OSC Pre-Audit | 10/10/2018 |
RODEMS CONSTRUCTION CO INC | State University Construction Fund | T006459 |
$15,946,078.00
|
$15,946,078.00 |
10/04/2018 | 12/03/2020 | SUCF031008 Selective Renovati | Contracts Not Subject to OSC Pre-Audit | 10/05/2018 |
JOHN G WAITE ASSOCIATES ARCHITECT PLLC | State University Construction Fund | T006455 |
$1,352,000.00
|
$887,725.18 |
09/24/2018 | 03/31/2025 | SUCF101025 Replace/Reconstruc | Contracts Not Subject to OSC Pre-Audit | 10/01/2018 |
CHIANG OBRIEN ARCHITECTS DPC | State University Construction Fund | T006446 |
$3,941,669.03
|
$3,699,425.75 |
09/19/2018 | 01/31/2025 | SUCF201018 Renovate Marshall | Contracts Not Subject to OSC Pre-Audit | 09/27/2018 |
TURNER CONSTRUCTION COMPANY | State University Construction Fund | T006409 |
$5,000,000.00
|
$45,554.27 |
04/17/2018 | 04/17/2021 | SUCF 80804 Construction Manag | Contracts Not Subject to OSC Pre-Audit | 09/27/2018 |
BAST HATFIELD CONSTRUCTION LLC | State University Construction Fund | T006458 |
$981,703.00
|
$981,703.00 |
09/24/2018 | 09/24/2020 | SUCF401010 Interior Rehab & L | Contracts Not Subject to OSC Pre-Audit | 09/25/2018 |
SCHULER-HAAS ELECTRIC CORP | State University Construction Fund | T006452 |
$3,154,841.00
|
$3,154,841.00 |
09/11/2018 | 01/11/2021 | SUCF021012 Replace Emergency | Contracts Not Subject to OSC Pre-Audit | 09/13/2018 |
BUFFALO CONSTRUCTION CONSULTANTS INC | State University Construction Fund | T006447 |
$2,494,539.00
|
$1,775,996.57 |
07/27/2018 | 07/27/2023 | SUCF031009 Reconstruct Centra | Contracts Not Subject to OSC Pre-Audit | 09/04/2018 |
NUA CONSTRUCTION CORP | State University Construction Fund | T006427 |
$688,318.00
|
$688,318.00 |
08/30/2018 | 02/26/2020 | SUCF081013 Exterior Rehab Var | Contracts Not Subject to OSC Pre-Audit | 08/30/2018 |
THE WHITING-TURNER CONTRACTING COMPANY INC | State University Construction Fund | T006429 |
$5,273,867.72
|
$5,118,470.16 |
05/23/2018 | 06/30/2024 | SUCF151036 CM - Construct He | Contracts Not Subject to OSC Pre-Audit | 08/27/2018 |
ICON CONTRACTING GROUP INC | State University Construction Fund | T006450 |
$1,936,696.00
|
$1,716,696.00 |
08/23/2018 | 01/20/2021 | SUCF311009 Replace Roofs, Nat | Contracts Not Subject to OSC Pre-Audit | 08/27/2018 |
C & S ENGINEERS INC | State University Construction Fund | T006451 |
$3,840,520.13
|
$2,493,435.36 |
08/24/2018 | 06/14/2028 | SUCF021025 Infrastructure Imp | Contracts Not Subject to OSC Pre-Audit | 08/27/2018 |
CANNON DESIGN ARCHITECTURE AND ENGINEERING PC | State University Construction Fund | T006435 |
$6,570,156.67
|
$5,170,730.76 |
08/09/2018 | 09/30/2026 | SUCF101027 Renovate Hewitt Ha | Contracts Not Subject to OSC Pre-Audit | 08/10/2018 |
KIRCHER CONSTRUCTION INC | State University Construction Fund | T006414 |
$12,000,000.00
|
$211,087.00 |
04/27/2018 | 04/25/2022 | SUCF80X700 Job Order Contract | Contracts Not Subject to OSC Pre-Audit | 08/08/2018 |
WAINSCHAF ASSOCIATES INC | State University Construction Fund | T006448 |
$1,601,511.00
|
$1,601,511.00 |
07/30/2018 | 08/14/2020 | SUCF011008 Rehab Toilet Rooms | Contracts Not Subject to OSC Pre-Audit | 08/08/2018 |
KIDENEY ARCHITECTS PC | State University Construction Fund | T006449 |
$1,546,529.00
|
$1,309,332.81 |
07/27/2018 | 06/01/2025 | SUCF351003 Renovate McMahon f | Contracts Not Subject to OSC Pre-Audit | 07/27/2018 |
GANEM CONTRACTING CORPORATION | State University Construction Fund | T006445 |
$2,174,219.00
|
$2,174,219.00 |
07/19/2018 | 08/15/2020 | SUCF091016 Repair Masonry - H | Contracts Not Subject to OSC Pre-Audit | 07/20/2018 |
MID-STATE INDUSTRIES LTD | State University Construction Fund | T006444 |
$662,663.00
|
$662,663.00 |
07/11/2018 | 08/21/2019 | SUCF251020 Replace Roofs- Var | Contracts Not Subject to OSC Pre-Audit | 07/16/2018 |
TITAN ROOFING INC | State University Construction Fund | T006443 |
$3,163,694.00
|
$3,163,694.00 |
07/10/2018 | 05/06/2020 | SUCF111016 Replace Roof Sible | Contracts Not Subject to OSC Pre-Audit | 07/11/2018 |
GENERAL ROOFING CONTRACTORS LLC | State University Construction Fund | T006430 |
$2,806,397.00
|
$2,806,397.00 |
07/06/2018 | 11/10/2020 | SUCF061013 Replace Roofs - Va | Contracts Not Subject to OSC Pre-Audit | 07/06/2018 |
DOW ELECTRIC INC | State University Construction Fund | T006434 |
$2,000,000.00
|
$61,442.00 |
06/27/2018 | 06/27/2019 | SUCF80X700 JOCS - 80700-07- A | Contracts Not Subject to OSC Pre-Audit | 07/05/2018 |
FERGUSON ELECTRIC INC | State University Construction Fund | T006442 |
$3,256,942.00
|
$3,256,942.00 |
07/03/2018 | 04/29/2020 | SUCF30XA95 Replace Fire Alarm | Contracts Not Subject to OSC Pre-Audit | 07/05/2018 |
STANTEC ARCHITECTURE INC | State University Construction Fund | T006406 |
$9,454,985.18
|
$9,076,409.98 |
06/18/2018 | 11/13/2025 | SUCF151036 Construct Health | Contracts Not Subject to OSC Pre-Audit | 06/28/2018 |
MARIC MECHANICAL INC | State University Construction Fund | T006432 |
$3,472,447.00
|
$3,472,447.00 |
06/25/2018 | 08/29/2020 | SUCF291014 Rehab HTHW System | Contracts Not Subject to OSC Pre-Audit | 06/28/2018 |
ENVISION ARCHITECTS DPC | State University Construction Fund | T006422 |
$3,282,000.00
|
$2,694,437.81 |
05/29/2018 | 12/10/2025 | SUCF251026 Renovate Farnswort | Contracts Not Subject to OSC Pre-Audit | 06/27/2018 |
CENTRAL PAVING INC | State University Construction Fund | T006431 |
$770,400.00
|
$770,400.00 |
06/19/2018 | 09/27/2019 | SUCF391010 Reconstruct Variou | Contracts Not Subject to OSC Pre-Audit | 06/25/2018 |
SAVARINO COMPANIES LLC | State University Construction Fund | T006426 |
$7,058,440.00
|
$7,058,440.00 |
06/19/2018 | 06/08/2021 | SUCF021011 Renovate Exterior | Contracts Not Subject to OSC Pre-Audit | 06/20/2018 |
M & J ELECTRICAL CONTRACTORS CORP | State University Construction Fund | T006424 |
$2,579,780.00
|
$2,579,780.00 |
06/11/2018 | 05/27/2020 | SUCF411004 Renovate Lower Lob | Contracts Not Subject to OSC Pre-Audit | 06/11/2018 |
STEVEN E FULLER EXCAVATING INC | State University Construction Fund | T006428 |
$560,139.00
|
$560,139.00 |
06/01/2018 | 09/09/2019 | SUCF111024 Replace HTHW Lines | Contracts Not Subject to OSC Pre-Audit | 06/05/2018 |
ENVISION ARCHITECTS DPC | State University Construction Fund | T006425 |
$1,807,479.09
|
$1,807,479.09 |
05/29/2018 | 05/29/2023 | SUCF011011 Renovate Building | Contracts Not Subject to OSC Pre-Audit | 05/29/2018 |
JACOBS PROJECT MANAGEMENT CO | State University Construction Fund | T006411 |
$5,000,000.00
|
$1,061,302.55 |
04/17/2018 | 06/06/2024 | SUCF 80805 Construction Manag | Contracts Not Subject to OSC Pre-Audit | 05/25/2018 |
LIRO PROGRAM & CONSTRUCTION MANAGEMENT PE PC | State University Construction Fund | T006412 |
$5,000,000.00
|
$2,920,580.55 |
04/17/2018 | 04/03/2025 | SUCF 80805 Construction Manag | Contracts Not Subject to OSC Pre-Audit | 05/24/2018 |
FERGUSON ELECTRIC INC | State University Construction Fund | T006423 |
$3,839,477.00
|
$3,839,477.00 |
05/23/2018 | 08/02/2020 | SUCF301014 Replace Electrical | Contracts Not Subject to OSC Pre-Audit | 05/24/2018 |
ELLANA INC | State University Construction Fund | T006410 |
$5,000,000.00
|
$1,325,081.00 |
04/18/2018 | 11/01/2024 | SUCF 80805 Construction Manag | Contracts Not Subject to OSC Pre-Audit | 05/24/2018 |
GILBANE BUILDING COMPANY | State University Construction Fund | T006408 |
$5,000,000.00
|
$1,912,741.71 |
04/17/2018 | 02/23/2028 | SUCF 80804 Construction Manag | Contracts Not Subject to OSC Pre-Audit | 05/23/2018 |
WELLIVER MCGUIRE INC | State University Construction Fund | T006417 |
$11,532,723.00
|
$11,532,723.00 |
05/14/2018 | 05/19/2021 | SUCF041002 Renovate Park Cent | Contracts Not Subject to OSC Pre-Audit | 05/16/2018 |
PTL CONTRACTING CORP | State University Construction Fund | T006392 |
$590,701.00
|
$590,701.00 |
05/09/2018 | 08/17/2019 | SUCF12X369 Renovate Timerman | Contracts Not Subject to OSC Pre-Audit | 05/14/2018 |