Department of Transportation | D263928 |
$801,284.70
|
$801,284.70 |
05/22/2019 | 11/30/2019 | ADA Accessibility Improve Sidewalks Ramps Pedestrian Poles Pushbuttons & Warning Devices R7 Counties | Construction - Highway | 05/22/2019 |
Department of Transportation | D262751 |
$178,106.44
|
$178,106.44 |
02/04/2015 | 07/31/2016 | Traffic signal install, Rt 9 & ferry rd., town of Stuyvesant, Columbia Cnty. | Construction - Highway | 02/04/2015 |
Department of Transportation | D263447 |
$1,113,007.38
|
$1,113,007.38 |
05/25/2017 | 04/30/2019 | Signal Improvement Project, Part 19, Region 7 Counties | Construction - Building | 05/25/2017 |
Department of Transportation | D263700 |
$520,384.44
|
$520,384.44 |
03/29/2018 | 05/31/2019 | ADA Accessibility Improvement Project Region 7 | Construction - Highway | 03/29/2018 |
Department of Transportation | D262305 |
$786,906.82
|
$786,906.82 |
05/30/2013 | 10/31/2015 | INSTALL TRAFFIC SIGNALS DUTCHESS ULSTER WESTCHESTER COUNTIES | Construction - Highway | 05/30/2013 |
Department of Transportation | D262958 |
$829,284.37
|
$829,284.37 |
08/12/2015 | 01/30/2017 | SIGNAL IMPROVEMENT PROJECT 8 SITES, TOWN OF WATERTOWN AND VILLAGE OF POTSDAM | Construction - Highway | 08/12/2015 |
Department of Transportation | D262321 |
$426,357.00
|
$426,357.00 |
05/16/2013 | 06/30/2014 | TRAFFIC SIGNAL UPGRADES ORANGE ROCKLAND COUNTIES | Construction - Highway | 05/16/2013 |
Department of Transportation | D262206 |
$796,790.81
|
$796,790.81 |
03/18/2013 | 07/11/2014 | ADA SIDEWALK IMPROVEMENTS CARTHAGE SARANAC LAKE AND WEST CARTHAGE FRANKLIN AND JEFFERSON COUNTIES | Construction - Highway | 03/18/2013 |
Department of Transportation | D263967 |
$1,422,367.41
|
$1,422,367.41 |
06/10/2019 | 10/31/2020 | Signal Improvements Project Region 7 | Construction - Highway | 06/10/2019 |
Department of Transportation | D262336 |
$1,017,115.67
|
$1,017,115.67 |
06/10/2013 | 03/31/2015 | TRAFFIC SIGNAL IMPROVEMENTS SPECIFIED INTERSECTIONS CLINTION JEFFERSON AND ST LAWRENCE COUNTIES | Construction - Highway | 06/10/2013 |
Department of Transportation | D264515 |
$1,315,909.32
|
$1,315,909.32 |
06/25/2021 | 12/31/2022 | Traffic signal upgrades with curb improvements various locations Region 7 counties | Construction - Miscellaneous | 06/25/2021 |
Department of Transportation | D261666 |
$860,448.00
|
$860,448.00 |
04/25/2011 | 01/18/2013 | SIGNAL IMPROVEMENTS AT VARIOUS LOCATIONS FRANKLIN, JEFFERSON AND ST LAWRENCE COUNTIES | Construction - Highway | 04/25/2011 |
Department of Transportation | D264974 |
$798,345.54
|
$597,293.50 |
03/29/2023 | 05/31/2024 | Sidewalk ADA accessibility improvements Jefferson & St Lawrence Counties | Construction - Highway | 03/29/2023 |
SUNY at Binghamton | T300108 |
$67,125.00
|
$65,281.00 |
08/03/2011 | 02/10/2012 | REMOVE SIDEWALKS & PARKING LOT PAVEMENT & SITE LIGHTING | Contracts Not Subject to OSC Pre-Audit | 02/16/2012 |
College at Potsdam | T000550 |
$101,709.63
|
$101,709.63 |
09/13/2010 | 06/30/2012 | EMERGENCY GENERATOR (FORMERLY D0Q0497 | Contracts Not Subject to OSC Pre-Audit | 01/10/2012 |
College at Potsdam | D0Q0497 |
$650,000.00
|
$559,515.37 |
09/13/2010 | 09/23/2011 | EMERGENCY GENERATOR SUNY POTSDAM - PROJECT 12284 | Construction - Building | 09/13/2010 |
College at Potsdam | T000812 |
$49,948.43
|
$49,948.43 |
06/05/2023 | 08/16/2023 | BARRINGTON STUDENT UNION CONCR | Contracts Not Subject to OSC Pre-Audit | 08/01/2023 |
College at Potsdam | T000532 |
$78,750.00
|
$78,750.00 |
08/11/2011 | 06/30/2012 | MAXCY HALL LIGHTING | Contracts Not Subject to OSC Pre-Audit | 08/12/2011 |
College of Technology at Canton | T860270 |
$162,000.00
|
$162,000.00 |
12/12/2019 | 07/01/2020 | L23135 SOUTH WING SMITH HALL E | Contracts Not Subject to OSC Pre-Audit | 01/31/2020 |
Office of General Services - Design & Construction | D45214E |
$76,800.00
|
$69,100.00 |
05/05/2017 | 07/24/2018 | Roof repair Bldg. 4-7, Ogdensburg CF, St. Lawrence County, (E), | Construction - Building | 05/05/2017 |
Office of General Services - Design & Construction | D45762E |
$400,302.00
|
$383,470.00 |
01/05/2018 | 12/29/2018 | Rehab Bldgs. 1, 2, and 20. Adirondack CF, Essex County | Construction - Building | 01/05/2018 |
Office of General Services - Design & Construction | DEC265C |
$150,000.00
|
$99,403.00 |
02/26/2013 | 06/28/2013 | REPLACE FALLEN CEILING IN THE DISH WASH ROOM CLINTON CF | Construction - Building | 04/17/2013 |
Office of General Services - Design & Construction | D45670E |
$38,200.00
|
$38,195.00 |
05/31/2018 | 01/30/2019 | Provide Salt Storage Building Warren County (E) | Construction - Building | 05/30/2018 |
Office of General Services - Design & Construction | D44306E |
$2,739,877.00
|
$2,739,836.00 |
09/25/2013 | 05/09/2017 | REPLACE EMERGENCY GENERATORS & SWITCHGEAR POWER HOUSE BUILDING 17 MID STATE CF | Construction - Building | 09/25/2013 |
Office of General Services - Design & Construction | D45440E |
$81,731.00
|
$81,719.00 |
10/06/2016 | 09/13/2017 | REHAB LOWER SARANAC LOCKS, OSEETAH LAKE DAM, FRANKLIN COUNTY (DEC ID 183-0642) | Construction - Miscellaneous | 10/06/2016 |
Office of General Services - Design & Construction | D45636E |
$1,268,711.00
|
$1,267,981.00 |
12/19/2019 | 10/20/2021 | Rehabilitate Auditorium Dulles SOB Jefferson County | Construction - Building | 12/19/2019 |
Office of General Services - Design & Construction | DEB440G |
$75,000.00
|
$760.00 |
12/28/2010 | 04/27/2011 | REPAIR WATER TOWER PIPING LEAK MID STATE CF | Construction - Building | 02/09/2011 |
Office of General Services - Design & Construction | D44090E |
$10,900.00
|
$10,200.00 |
03/31/2011 | 01/26/2012 | REPLACE WINDOWS & EXTERIOR WALLS, 300 WING ST REGIS MOHAWK SCHOOL | Construction - Building | 03/31/2011 |
Office of General Services - Design & Construction | DEC706E |
$300,000.00
|
$144,356.00 |
07/31/2014 | 06/30/2016 | DECOMMISSION ELECTRICAL SYSTEM FACILITY CLOSURE MT MCGREGOR CF SARATOGA COUNTY | Construction - Building | 08/27/2014 |
Office of General Services - Design & Construction | D44313E |
$1,244,453.00
|
$84,153.00 |
06/10/2013 | 09/26/2015 | REPLACE ELECTRIC PANELS AND RELATED WORK MT MCGREGOR CORRECTIONAL FACILITY VARIOUS BLDGS WILTON NY | Construction - Building | 06/10/2013 |
Office of General Services - Design & Construction | DEC367V |
$35,000.00
|
$2,983.00 |
07/02/2013 | 10/30/2013 | REMOVE ROTTED UTILITY POLE & COVER HIGH VOLTAGE ELECTRIC VAULTS ADIRONDACK PC CLINTON COUNTY | Construction - Building | 08/29/2013 |
Office of General Services - Design & Construction | DM2916E |
$162,327.00
|
$159,920.00 |
02/14/2011 | 03/31/2012 | REPLACE ELECTRICAL DISTRIBUTION SYSTEM PANELS & LIGHTING PARKING GARAGE BLDG #3 CDPC | Construction - Building | 01/23/2012 |
Office of General Services - Design & Construction | D45121E |
$62,788.00
|
$61,686.00 |
07/15/2016 | 10/11/2018 | Replace Roof E; NYS Police Ray Brook, Essex County | Construction - Building | 07/15/2016 |
Office of General Services - Design & Construction | D44563E |
$550,107.00
|
$550,034.00 |
03/01/2013 | 09/26/2014 | SECURITY SYSTEM UPGRADES AT COLUMBIA SECURE CENTER FOR GIRLS CLAVERACK NY | Construction - Building | 03/01/2013 |
Office of General Services - Design & Construction | DQ1559C |
$771,000.00
|
$754,452.00 |
06/02/2014 | 02/27/2015 | REHAB PARKING AREA CONSTRUCTION WORK BINGHAMTON ARMORY BROOME COUNTY | Construction - Building | 06/02/2014 |
Office of General Services - Design & Construction | D45575E |
$1,000,000.00
|
$829,323.00 |
06/15/2017 | 01/26/2021 | Job Order Contracting (JOC) Area 5 (E) | Construction - Building | 06/15/2017 |
Office of General Services - Design & Construction | DEB669E |
$300,000.00
|
$2,150.00 |
09/12/2011 | 01/10/2012 | RESTORE FAILED ELECTRICAL SERVICE COBLESKILL ATC | Construction - Building | 10/06/2011 |
Office of General Services - Design & Construction | DM2943E |
$186,100.00
|
$184,027.00 |
03/25/2011 | 10/25/2011 | REPLACE TRANSFORMER & SWITCH IN PUMP STATION CLINTON CF | Construction - Building | 12/27/2011 |
Office of General Services - Design & Construction | DQ1479E |
$477,855.00
|
$462,434.00 |
11/23/2011 | 01/16/2013 | UPGRADE ELECTRICAL & PROVIDE WALLS & CEILINGS BLDG 23 CLINTON CF | Construction - Building | 11/23/2011 |
Office of General Services - Design & Construction | DEC209V |
$75,000.00
|
$3,532.00 |
01/22/2013 | 05/22/2013 | RESTORE CAMP GABRIELS ELECTRIC SERVICE 737 STATE ROUTE 86 GABRIELS NEW YORK | Construction - Building | 03/04/2013 |
Office of General Services - Design & Construction | DM3138E |
$71,300.00
|
$69,251.00 |
11/19/2021 | 11/22/2022 | Repair elevator Building 14 Clinton CF Clinton County | Construction - Building | 11/19/2021 |
Office of General Services - Design & Construction | DQ1559E |
$58,800.00
|
$58,735.00 |
06/02/2014 | 07/31/2015 | REHABI PARKING AREA ELECTRICAL WORK BINGHAMTON ARMORY BROOME COUNTY | Construction - Building | 06/02/2014 |
Office of General Services - Design & Construction | D44513E |
$325,203.00
|
$325,151.00 |
07/16/2013 | 07/19/2015 | PROVIDE EMERGENCY RESPONSE BUILDING ELECTRICAL WORK GOUVERNEUR CF ST LAWRENCE COUNTY | Construction - Building | 07/16/2013 |
Office of General Services - Design & Construction | D45576C |
$1,500,000.00
|
$910,062.00 |
05/30/2017 | 06/30/2021 | Job Order Contracting - Area 6 Construction | Construction - Building | 05/30/2017 |
Office of General Services - Design & Construction | D44247E |
$230,302.00
|
$230,281.00 |
12/17/2014 | 08/31/2016 | Provide Classroom Expansion, 200 Wing, St Regis Mohawk School, Akwesasne Mohawk Territory | Construction - Building | 12/17/2014 |
Office of General Services - Design & Construction | D44169E |
$98,484.00
|
$96,949.00 |
01/30/2012 | 07/30/2013 | PROVIDE FIRE ALARM SYSTEM IN OPTIC BUILDING WALLKILL CF | Construction - Building | 01/30/2012 |
Office of General Services - Design & Construction | D44214C |
$2,500,000.00
|
$1,025,060.00 |
09/06/2011 | 09/05/2014 | JOB ORDER CONTRACTING - AREA 4 UPSTATE GENERAL CONSTRUCTION - VARIOUS DAC FACILITIES | Construction - Building | 09/06/2011 |
Office of General Services - Design & Construction | D44214E |
$500,000.00
|
$46,227.00 |
08/31/2011 | 08/30/2014 | JOB ORDER CONTRACTING - AREA 4 VARIOUS DAC FACILITIES | Construction - Building | 08/31/2011 |
Office of General Services - Design & Construction | D44216C |
$1,000,000.00
|
$254,798.00 |
08/30/2011 | 08/29/2014 | JOB ORDER CONTRACTING - AREA 6 | Construction - Building | 08/30/2011 |
Office of General Services - Design & Construction | D44216E |
$500,000.00
|
$0.00 |
08/31/2011 | 08/30/2014 | JOB ORDER CONTRACTING - AREA 6 | Construction - Building | 08/31/2011 |