Department/Facility | Contract Number | Current Contract Amount | Spending to Date | Contract Start Date | Contract End Date | Contract Description | Contract Type | Original Contract Approved/Filed Date |
---|---|---|---|---|---|---|---|---|
Office of General Services - Design & Construction | DED377V |
$300,000.00
|
$62,655.00 |
12/13/2016 | 08/31/2017 | Restore Electrical Feeder 7X98 Blg 40 Bronx PC Bronx County | Construction - Building | 01/10/2017 |
Office of General Services - Design & Construction | DEE361V |
$1,200,000.00
|
$1,169,367.00 |
06/10/2020 | 01/31/2021 | Restore power at Creedmoor PC Bldg 71 Queens Village Nassau County | Construction - Building | 08/07/2020 |
Office of General Services - Design & Construction | DEC734V |
$300,000.00
|
$189,113.00 |
09/12/2014 | 12/31/2016 | CORRECT FAILED POWER FEEDERS BUILDING 122 MANHATTAN PC NY COUNTY | Construction - Building | 10/07/2014 |
Office of General Services - Design & Construction | DEB323V |
$75,000.00
|
$6,205.00 |
09/20/2010 | 05/18/2011 | REPAIR FAILED EMERGENCY GENERATOR ANNEX BLDG LAKEVIEW CF | Construction - Building | 10/14/2010 |
Office of General Services - Design & Construction | DEE104V |
$600,000.00
|
$447,960.00 |
05/17/2019 | 03/31/2020 | Restore Power Attica CF Wyoming County | Construction - Building | 07/26/2019 |
Office of General Services - Design & Construction | DEE063V |
$100,000.00
|
$65,777.00 |
03/25/2019 | 11/08/2019 | Restore Power to Bldgs 5 14 Work Control & Heat Plant Altona CF Clinton County | Construction - Building | 05/30/2019 |
Office of General Services - Design & Construction | DED652V |
$100,000.00
|
$17,556.00 |
11/16/2017 | 03/16/2018 | Investigate & Repair High Voltage Switch, Bldg 140, Groveland CF | Construction - Building | 12/20/2017 |
Office of General Services - Design & Construction | DEC475V |
$300,000.00
|
$11,192.00 |
10/25/2013 | 02/22/2014 | INVESTIGATE AND CORRECT GFI FAULT WILLARD DRUG TREATMENT CENTER | Construction - Building | 12/06/2013 |
Office of General Services - Design & Construction | DEC684V |
$300,000.00
|
$89,249.00 |
07/02/2014 | 10/30/2014 | RESTORE FAULTY FEEDER 1 & PROVIDE TEMPORARY GENERATORS BUILDING 11 12 & 13 BRONX PC BRONX COUNTY | Construction - Building | 08/06/2014 |
Office of General Services - Design & Construction | DEC633V |
$100,000.00
|
$36,298.00 |
05/13/2014 | 11/19/2014 | REPAIR FAILED POWER FEED KIRBY FORSENIC BLDG MANHATTAN PC | Construction - Building | 06/05/2014 |
Office of General Services - Design & Construction | DEC408V |
$300,000.00
|
$249,468.00 |
07/30/2013 | 11/27/2013 | CLEAN & REPAIR HIGH VOLTAGE SWITCHGEAR CAMP SMITH | Construction - Building | 08/30/2013 |
Office of General Services - Design & Construction | DEC223V |
$200,000.00
|
$25,991.00 |
02/01/2013 | 07/19/2013 | RESTORE FAILED ATS CONTROLS FOR ELECTRICAL POWER IN BUILDING 82 AT PILGRIM PC | Construction - Building | 03/08/2013 |
Office of General Services - Design & Construction | DEE674V |
$300,000.00
|
$251,237.68 |
10/08/2021 | 08/04/2022 | Repair generator Riverview Correctional Facility St. Lawrence County | Construction - Building | 11/22/2021 |
Office of General Services - Design & Construction | DED494V |
$200,000.00
|
$47,830.00 |
05/19/2017 | 11/15/2017 | Restore Electrical Power Bldg 6 South Beach PC Richmond County | Construction - Building | 06/14/2017 |
Office of General Services - Design & Construction | DEE620V |
$150,000.00
|
$38,714.36 |
07/27/2021 | 11/24/2021 | Restoration of power at Bare Hills CF Franklin County | Construction - Building | 09/10/2021 |
Office of General Services - Design & Construction | D44750E |
$2,827,951.00
|
$2,827,731.00 |
11/15/2017 | 12/10/2021 | Replace Switchgear, Altona Correctional Facility, Clinton County | Construction - Building | 11/15/2017 |
Office of General Services - Design & Construction | DM3025E |
$1,809,794.00
|
$1,807,178.00 |
11/20/2013 | 02/15/2017 | REPLACE 115KV SUBSTATION & SWITCHGEAR GREAT MEADOW CF | Construction - Building | 11/20/2013 |
Office of General Services - Design & Construction | DEE236V |
$100,000.00
|
$19,153.00 |
12/03/2019 | 04/01/2020 | Restore Power Mohawk CF Oneida County | Construction - Building | 12/27/2019 |
Office of General Services - Design & Construction | D41999E |
$1,582,826.00
|
$1,579,104.00 |
06/30/2004 | 12/31/2011 | ARTHURKILL CF, REPLACE FACILITY SWITCHGEAR | Construction - Building | 11/16/2011 |
Office of General Services - Design & Construction | DEB565V |
$300,000.00
|
$190,970.00 |
06/15/2011 | 05/09/2012 | REPLACE EMERGENCY GENERATOR BINGHAMTON SOB | Construction - Building | 01/20/2012 |
Office of General Services - Design & Construction | DEB569V |
$150,000.00
|
$67,385.00 |
06/18/2011 | 10/16/2011 | REPAIR SWITCH GEAR TO RESTORE POWER ALTONA CF | Construction - Building | 07/26/2011 |
Office of General Services - Design & Construction | DEB837V |
$190,923.00
|
$190,844.00 |
02/07/2012 | 09/19/2013 | REPAIR VOLTAGE IRREGULARITIES TO BACK UP GENERATOR RIVERVIEW CF | Construction - Building | 02/28/2012 |
Office of General Services - Design & Construction | DEE052V |
$600,000.00
|
$63,268.00 |
02/27/2019 | 08/26/2019 | Restore Power to Facility Wallkill CF Ulster County | Construction - Building | 03/26/2019 |
Office of General Services - Design & Construction | DEE321V |
$1,100,000.00
|
$1,067,542.00 |
04/01/2020 | 05/06/2021 | Restore Power Generator Function Mohawk CF Oneida County | Construction - Building | 07/15/2020 |
Office of General Services - Design & Construction | DED297V |
$600,000.00
|
$582,953.00 |
09/14/2016 | 10/13/2017 | REPAIR ELECTRICAL FEEDER #3, BUILDING 103, MANHATTAN PC | Construction - Building | 10/05/2016 |
Office of General Services - Design & Construction | DEC982V |
$150,000.00
|
$3,731.00 |
07/23/2015 | 12/20/2015 | Investigate/Restore Power, Switchgear Room, Building 47, Rockland PC | Construction - Building | 08/27/2015 |
Office of General Services - Design & Construction | D45210E |
$3,484,285.00
|
$3,474,145.00 |
03/15/2019 | 11/07/2021 | Replace Generator & Switchgear Building 20 & 43 Franklin CF Franklin County E | Construction - Building | 03/15/2019 |
Office of General Services - Design & Construction | DEE854V |
$300,000.00
|
$299,934.76 |
07/28/2022 | 01/24/2023 | Repair generator Wende CF Erie County | Construction - Building | 08/11/2022 |
Office of General Services - Design & Construction | DEF011V |
$300,000.00
|
$134,820.64 |
06/18/2023 | 10/16/2023 | Repair Feeder Washington Correctional Facility Washington County | Construction - Building | 08/09/2023 |
Office of General Services - Design & Construction | DEF140V |
$300,000.00
|
$25,680.03 |
01/25/2024 | 07/23/2024 | Repair Generator Lakeview Correctional Facility Chautauqua County | Construction - Building | 02/21/2024 |
Office of General Services - Design & Construction | DEE898V |
$200,000.00
|
$195,507.01 |
11/04/2022 | 03/04/2023 | Restore Power Cayuga CF Cayuga County | Construction - Building | 11/28/2022 |
Office of General Services - Design & Construction | D45390E |
$7,816,229.00
|
$0.00 |
03/22/2024 | 06/20/2026 | Upgrade generator & switchgear at Mohawk Correctional Facility in Oneida County | Construction - Building | 03/22/2024 |
Office of General Services - Design & Construction | DM3140E |
$136,929.00
|
$126,729.00 |
01/20/2022 | 01/16/2023 | Repair/replace switchgear heating plant Sing Sing CF Ossining Westchester County | Construction - Building | 01/20/2022 |
Office of General Services - Design & Construction | DEE600V |
$225,000.00
|
$177,537.00 |
07/08/2021 | 03/31/2022 | Repair switch gear & generator EdgeCombe CF New York County Region 2 | Construction - Building | 08/20/2021 |
Office of General Services - Design & Construction | DEF074V |
$300,000.00
|
$8,445.47 |
10/12/2023 | 04/09/2024 | Repair electrical feeder at Albion CF in Orleans County | Construction - Building | 11/10/2023 |
Office of General Services - Design & Construction | DEF071V |
$600,000.00
|
$135,662.32 |
10/06/2023 | 04/03/2024 | Replace Transformer Building 22 Wende Correctional Facility Alden Erie County | Construction - Building | 11/21/2023 |
Office of General Services - Design & Construction | DEE902V |
$300,000.00
|
$43,383.60 |
11/15/2022 | 05/14/2023 | Generator repair at NC Welcome Center Alexandria Bay NY Jefferson County | Construction - Building | 01/06/2023 |
Office of General Services - Design & Construction | DEF169V |
$300,000.00
|
$0.00 |
03/25/2024 | 03/20/2025 | Repair generator on Industry Campus in Rush NY Monroe County | Construction - Building | 04/15/2024 |
Office of General Services - Design & Construction | DEF040V |
$150,000.00
|
$43,616.28 |
08/03/2023 | 12/01/2023 | Repair arc flash in main transformer at Five Points Correctional Facility in Seneca County | Construction - Building | 08/23/2023 |
State University Construction Fund | T005625 |
$52,680.00
|
$52,680.00 |
01/29/2010 | 02/15/2012 | UTILITY UPGRADES DUCTBANKS TRANSFORMER SUCF 07A23 SUNY BINGHAMTON | Contracts Not Subject to OSC Pre-Audit | 05/04/2011 |
State University Construction Fund | T005690 |
$3,385,998.00
|
$3,385,998.00 |
07/09/2010 | 04/30/2015 | SUCF 23201 REPLACE ELECTRIC SUBSTATION SUNY CANTON | Contracts Not Subject to OSC Pre-Audit | 02/02/2012 |
State University Construction Fund | T006318 |
$1,942,656.00
|
$1,942,656.00 |
04/10/2017 | 06/11/2019 | SUCF 24007 Upgrade Switchgear | Contracts Not Subject to OSC Pre-Audit | 04/12/2017 |
State University Construction Fund | T005923 |
$3,321,217.00
|
$3,321,217.00 |
02/28/2012 | 01/16/2014 | SUCF 04354 CAMPUSWIDE ELECTRICAL DISTRIBUTION UPGRADE PHASE 1 - SUC CORTLAND | Contracts Not Subject to OSC Pre-Audit | 02/29/2012 |
State University Construction Fund | D006780 |
$1,798,729.00
|
$1,247,478.00 |
11/23/2022 | 05/06/2025 | Upgrade electrical substation for McMahon Hall at the College of Ceramics at Alfred University | Construction - Building | 11/18/2022 |