Vendor Name: MOHAWK VALLEY UTILITY CONSTRUCTION CORP
Agency Name: General Services, Office of
Department/Facility Name: Office of General Services - Design & Construction
Contract Number: D44750E
Current Contract Amount: $2,827,951.00
Spending to Date: $2,827,731.00
Contract Type: Construction - Building
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $2,482,667.00 |
11/15/2017 | 06/10/2019 | Replace Switchgear, Altona Correctional Facility, Clinton County | 11/15/2017 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $0.00 |
08/15/2019 | CO#4 NCTE | 06/27/2019 |
Amendment | $0.00 |
12/30/2019 | CO#7 73781 NCTE Switchgear Altona Correctional Facility Clinton County | 07/10/2019 |
Amendment | $11,129.00 |
CO#8 73738 Replace Switchgear Altona Correctional Facility Clinton County | 07/18/2019 | |
Amendment | $4,433.00 |
CO#5 73744 Additional Work Altona CF Replace Switchgear | 07/25/2019 | |
Amendment | $30,640.00 |
CO#6 73667 Provide alarm board and general alarm. | 08/06/2019 | |
Amendment | $10,036.00 |
CO#3 73599 Provide Analog Phase Rotation Meter | 08/20/2019 | |
Amendment | $11,113.00 |
CO#2 73596 Provide Key Operated Rotary Switch | 09/05/2019 | |
Amendment | $14,819.00 |
CO#09 73918 Provide replacement dampers. | 09/27/2019 | |
Amendment | $5,087.00 |
CO#10 73922 Provide metal panels. | 10/22/2019 | |
Amendment | $0.00 |
01/09/2020 | CO#11 73922A NCTE | 03/11/2020 |
Amendment | $7,344.00 |
07/20/2020 | CO#14 74586 TE & Replace Switchgear | 07/16/2020 |
Amendment | $246,991.00 |
10/07/2021 | CO #15 74706 TE & Change selector switch | 01/08/2021 |
Amendment | $0.00 |
12/10/2021 | CO#16 No cost time extension | 12/08/2021 |
Amendment | $3,692.00 |
CO#17 77111 Additional Insurance costs | 04/19/2022 |