Department/Facility | Contract Number | Current Contract Amount | Spending to Date | Contract Start Date | Contract End Date | Contract Description | Contract Type | Original Contract Approved/Filed Date |
---|---|---|---|---|---|---|---|---|
Franklin Correctional Facility | C530112 |
$112,830.00
|
$105,080.00 |
08/28/2017 | 12/31/2018 | DINING HALL WINDOW REPLACEMENT FRANKLIN CORRECTIONAL FACILITY | Service - Refurbishing/Restoration Services | 11/08/2017 |
Franklin Correctional Facility | C530114 |
$61,610.00
|
$52,860.00 |
02/01/2019 | 01/31/2020 | PURCHASE AND INSTALL REPLACEMENT WINDOWS FRANKLIN CORRECTIONAL FACILITY | Service - Building Services | 03/13/2019 |
State University Construction Fund | D006608 |
$793,752.00
|
$785,352.00 |
04/09/2021 | 04/09/2023 | Replace switchgear and electrical panels Wicks and McArthur Halls Canton St Lawrence County | Construction - Building | 04/07/2021 |
Department of Environmental Conservation | D007933 |
$98,925.00
|
$98,925.00 |
10/14/2010 | 07/22/2011 | LIMEKILN LAKE CAMPGROUND ELECTRIC FEED LINE REHAB | Construction - Miscellaneous | 09/23/2011 |
Department of Environmental Conservation | D012830 |
$2,000,000.00
|
$313,191.83 |
07/10/2023 | 07/10/2024 | JOC various counties in Region 8 | Construction - Building | 07/10/2023 |
College at Potsdam | D0Q0497 |
$650,000.00
|
$559,515.37 |
09/13/2010 | 09/23/2011 | EMERGENCY GENERATOR SUNY POTSDAM - PROJECT 12284 | Construction - Building | 09/13/2010 |
Department of Transportation | D261666 |
$860,448.00
|
$860,448.00 |
04/25/2011 | 01/18/2013 | SIGNAL IMPROVEMENTS AT VARIOUS LOCATIONS FRANKLIN, JEFFERSON AND ST LAWRENCE COUNTIES | Construction - Highway | 04/25/2011 |
Department of Transportation | D262206 |
$796,790.81
|
$796,790.81 |
03/18/2013 | 07/11/2014 | ADA SIDEWALK IMPROVEMENTS CARTHAGE SARANAC LAKE AND WEST CARTHAGE FRANKLIN AND JEFFERSON COUNTIES | Construction - Highway | 03/18/2013 |
Department of Transportation | D262305 |
$786,906.82
|
$786,906.82 |
05/30/2013 | 10/31/2015 | INSTALL TRAFFIC SIGNALS DUTCHESS ULSTER WESTCHESTER COUNTIES | Construction - Highway | 05/30/2013 |
Department of Transportation | D262321 |
$426,357.00
|
$426,357.00 |
05/16/2013 | 06/30/2014 | TRAFFIC SIGNAL UPGRADES ORANGE ROCKLAND COUNTIES | Construction - Highway | 05/16/2013 |
Department of Transportation | D262336 |
$1,017,115.67
|
$1,017,115.67 |
06/10/2013 | 03/31/2015 | TRAFFIC SIGNAL IMPROVEMENTS SPECIFIED INTERSECTIONS CLINTION JEFFERSON AND ST LAWRENCE COUNTIES | Construction - Highway | 06/10/2013 |
Department of Transportation | D262751 |
$178,106.44
|
$178,106.44 |
02/04/2015 | 07/31/2016 | Traffic signal install, Rt 9 & ferry rd., town of Stuyvesant, Columbia Cnty. | Construction - Highway | 02/04/2015 |
Department of Transportation | D262958 |
$829,284.37
|
$829,284.37 |
08/12/2015 | 01/30/2017 | SIGNAL IMPROVEMENT PROJECT 8 SITES, TOWN OF WATERTOWN AND VILLAGE OF POTSDAM | Construction - Highway | 08/12/2015 |
Department of Transportation | D263447 |
$1,113,007.38
|
$1,113,007.38 |
05/25/2017 | 04/30/2019 | Signal Improvement Project, Part 19, Region 7 Counties | Construction - Building | 05/25/2017 |
Department of Transportation | D263700 |
$520,384.44
|
$520,384.44 |
03/29/2018 | 05/31/2019 | ADA Accessibility Improvement Project Region 7 | Construction - Highway | 03/29/2018 |
Department of Transportation | D263928 |
$801,284.70
|
$801,284.70 |
05/22/2019 | 11/30/2019 | ADA Accessibility Improve Sidewalks Ramps Pedestrian Poles Pushbuttons & Warning Devices R7 Counties | Construction - Highway | 05/22/2019 |
Department of Transportation | D263967 |
$1,422,367.41
|
$1,422,367.41 |
06/10/2019 | 10/31/2020 | Signal Improvements Project Region 7 | Construction - Highway | 06/10/2019 |
Department of Transportation | D264515 |
$1,315,909.32
|
$1,315,909.32 |
06/25/2021 | 12/31/2022 | Traffic signal upgrades with curb improvements various locations Region 7 counties | Construction - Miscellaneous | 06/25/2021 |
Department of Transportation | D264974 |
$798,345.54
|
$597,293.50 |
03/29/2023 | 05/31/2024 | Sidewalk ADA accessibility improvements Jefferson & St Lawrence Counties | Construction - Highway | 03/29/2023 |
Office of General Services - Design & Construction | D43387E |
$2,628,459.00
|
$2,606,041.00 |
05/11/2011 | 08/18/2013 | CONSTRUCT EMERGENCY GENERATOR BLDG 982 GREAT MEADOW CF | Construction - Building | 05/11/2011 |
Office of General Services - Design & Construction | D43554E |
$1,000,000.00
|
$194,474.00 |
01/31/2008 | 01/30/2011 | JOC CONTRACTING-AREA 4 VARIOUS LOCATIONS | Construction - Building | 10/07/2010 |
Office of General Services - Design & Construction | D43556C |
$2,000,000.00
|
$862,129.00 |
01/31/2008 | 01/30/2011 | JOC CONTRACT - AREA 6 - UPSTATE VARIOUS FACILITIES | Construction - Building | 10/07/2010 |
Office of General Services - Design & Construction | D43658E |
$42,144.00
|
$38,944.00 |
09/08/2011 | 12/31/2012 | RELOCATE FACILITY LAUNDRY, BLDG 31 MID-STATE CF | Construction - Building | 09/08/2011 |
Office of General Services - Design & Construction | D44090E |
$10,900.00
|
$10,200.00 |
03/31/2011 | 01/26/2012 | REPLACE WINDOWS & EXTERIOR WALLS, 300 WING ST REGIS MOHAWK SCHOOL | Construction - Building | 03/31/2011 |
Office of General Services - Design & Construction | D44169E |
$98,484.00
|
$96,949.00 |
01/30/2012 | 07/30/2013 | PROVIDE FIRE ALARM SYSTEM IN OPTIC BUILDING WALLKILL CF | Construction - Building | 01/30/2012 |
Office of General Services - Design & Construction | D44214C |
$2,500,000.00
|
$1,025,060.00 |
09/06/2011 | 09/05/2014 | JOB ORDER CONTRACTING - AREA 4 UPSTATE GENERAL CONSTRUCTION - VARIOUS DAC FACILITIES | Construction - Building | 09/06/2011 |
Office of General Services - Design & Construction | D44214E |
$500,000.00
|
$46,227.00 |
08/31/2011 | 08/30/2014 | JOB ORDER CONTRACTING - AREA 4 VARIOUS DAC FACILITIES | Construction - Building | 08/31/2011 |
Office of General Services - Design & Construction | D44216C |
$1,000,000.00
|
$254,798.00 |
08/30/2011 | 08/29/2014 | JOB ORDER CONTRACTING - AREA 6 | Construction - Building | 08/30/2011 |
Office of General Services - Design & Construction | D44216E |
$500,000.00
|
$0.00 |
08/31/2011 | 08/30/2014 | JOB ORDER CONTRACTING - AREA 6 | Construction - Building | 08/31/2011 |
Office of General Services - Design & Construction | D44247E |
$230,302.00
|
$230,281.00 |
12/17/2014 | 08/31/2016 | Provide Classroom Expansion, 200 Wing, St Regis Mohawk School, Akwesasne Mohawk Territory | Construction - Building | 12/17/2014 |
Office of General Services - Design & Construction | D44259E |
$101,825.00
|
$95,316.00 |
05/21/2012 | 09/09/2014 | REHABILITATE SHOWER AREAS BUILDINGS 13 - 19 AT MAIN BARE HILL CF | Construction - Building | 05/21/2012 |
Office of General Services - Design & Construction | D44306E |
$2,739,877.00
|
$2,739,836.00 |
09/25/2013 | 05/09/2017 | REPLACE EMERGENCY GENERATORS & SWITCHGEAR POWER HOUSE BUILDING 17 MID STATE CF | Construction - Building | 09/25/2013 |
Office of General Services - Design & Construction | D44313E |
$1,244,453.00
|
$84,153.00 |
06/10/2013 | 09/26/2015 | REPLACE ELECTRIC PANELS AND RELATED WORK MT MCGREGOR CORRECTIONAL FACILITY VARIOUS BLDGS WILTON NY | Construction - Building | 06/10/2013 |
Office of General Services - Design & Construction | D44513E |
$325,203.00
|
$325,151.00 |
07/16/2013 | 07/19/2015 | PROVIDE EMERGENCY RESPONSE BUILDING ELECTRICAL WORK GOUVERNEUR CF ST LAWRENCE COUNTY | Construction - Building | 07/16/2013 |
Office of General Services - Design & Construction | D44516E |
$7,779.00
|
$7,741.00 |
04/12/2013 | 08/17/2015 | REPLACE BOILER BUILDING 14 ALTONA CF ELECTRICAL | Construction - Building | 04/12/2013 |
Office of General Services - Design & Construction | D44549E |
$108,817.00
|
$108,411.00 |
08/29/2013 | 07/16/2015 | Provide Freezer & Cooler, Bldg. 3, Dining Room 1 | Construction - Building | 08/29/2013 |
Office of General Services - Design & Construction | D44560E |
$150,365.00
|
$150,365.00 |
02/06/2014 | 12/23/2015 | Waste Water Treatment Plant Improvements Electric, Finger Lakes RC | Construction - Building | 02/06/2014 |
Office of General Services - Design & Construction | D44563E |
$550,107.00
|
$550,034.00 |
03/01/2013 | 09/26/2014 | SECURITY SYSTEM UPGRADES AT COLUMBIA SECURE CENTER FOR GIRLS CLAVERACK NY | Construction - Building | 03/01/2013 |
Office of General Services - Design & Construction | D44605E |
$237,988.00
|
$225,807.00 |
09/04/2013 | 08/30/2014 | Provide safety and security upgrades, Bldg #76 @ Industry Limited Secure Center | Construction - Building | 09/04/2013 |
Office of General Services - Design & Construction | D44884C |
$1,500,000.00
|
$875,346.00 |
05/29/2014 | 05/28/2017 | JOB ORDER CONTRACTING (JOC) - AREA 4 Construction | Construction - Building | 05/29/2014 |
Office of General Services - Design & Construction | D44884E |
$1,000,000.00
|
$493,313.00 |
05/29/2014 | 05/28/2017 | JOB ORDER CONTRACTING - AREA 4 | Construction - Building | 05/29/2014 |
Office of General Services - Design & Construction | D44886E |
$500,000.00
|
$20,726.00 |
05/29/2014 | 01/22/2018 | JOB ORDER CONTRACTING (JOC) - AREA 6 Electrical | Construction - Building | 05/29/2014 |
Office of General Services - Design & Construction | D44922C |
$2,097,864.00
|
$2,082,437.00 |
03/28/2019 | 11/08/2022 | Construction Upgrade Plumbing & Fixtures Rehab Cell Backs Blocks A & B Clinton CF Clinton County | Construction - Building | 03/28/2019 |
Office of General Services - Design & Construction | D44946E |
$54,013.00
|
$52,289.00 |
05/01/2015 | 12/31/2016 | REPLACE AIR CONDITIONING UNITS, ADMIN BLDG 103, WATERTOWN CF | Construction - Building | 05/01/2015 |
Office of General Services - Design & Construction | D45006C |
$129,795.00
|
$116,299.00 |
11/09/2015 | 11/28/2016 | Replace Windows, Truck Trap Tower A-60, Clinton CF | Construction - Building | 11/09/2015 |
Office of General Services - Design & Construction | D45121E |
$62,788.00
|
$61,686.00 |
07/15/2016 | 10/11/2018 | Replace Roof E; NYS Police Ray Brook, Essex County | Construction - Building | 07/15/2016 |
Office of General Services - Design & Construction | D45214E |
$76,800.00
|
$69,100.00 |
05/05/2017 | 07/24/2018 | Roof repair Bldg. 4-7, Ogdensburg CF, St. Lawrence County, (E), | Construction - Building | 05/05/2017 |
Office of General Services - Design & Construction | D45215E |
$58,171.00
|
$56,171.00 |
07/05/2017 | 03/05/2019 | Electrical Work, Replace Steam Piping and Domestic Water Heaters, Jeferson County | Construction - Building | 07/05/2017 |
Office of General Services - Design & Construction | D45440E |
$81,731.00
|
$81,719.00 |
10/06/2016 | 09/13/2017 | REHAB LOWER SARANAC LOCKS, OSEETAH LAKE DAM, FRANKLIN COUNTY (DEC ID 183-0642) | Construction - Miscellaneous | 10/06/2016 |
Office of General Services - Design & Construction | D45574C |
$1,000,000.00
|
$571,053.00 |
06/07/2017 | 06/30/2021 | Job Order Contracting - Area 4 (GC) | Construction - Building | 06/07/2017 |