Department/Facility | Contract Number | Current Contract Amount | Spending to Date | Contract Start Date | Contract End Date | Contract Description | Contract Type | Original Contract Approved/Filed Date |
---|---|---|---|---|---|---|---|---|
Department of Transportation | D262108 |
$1,074,890.78
|
$1,074,890.78 |
11/02/2012 | 11/23/2013 | BRIDGE REHAB-SUPERSTRUCTURE REPLACEMENT RTE5 OVER SCONONDOA CREEK VILLAGE OF VERNON ONEIDA COUNTY | Construction - Highway | 11/02/2012 |
Department of Transportation | D264383 |
$2,666,866.31
|
$2,579,836.79 |
02/16/2021 | 09/30/2022 | Bridge superstructure replacement Route 5 over Kayaderosseras Creek Montgomery county | Construction - Highway | 02/16/2021 |
Department of Transportation | D264291 |
$18,176,507.91
|
$18,176,507.91 |
10/22/2020 | 07/31/2022 | Bridge replacement project Rte 34B over Salmon Creek Town of Lansing Tompkins County | Construction - Highway | 10/22/2020 |
Department of Transportation | D264031 |
$14,874,161.15
|
$14,084,771.73 |
09/13/2019 | 05/31/2023 | Rehabilitate Seven Bridges Amsterdam Montgomery County | Construction - Highway | 09/13/2019 |
Department of Transportation | D264320 |
$1,673,967.57
|
$1,673,967.57 |
12/17/2020 | 12/31/2021 | Bridge rehabilitation project Route 357 over Susquehanna River Unadilla Otsego county | Construction - Highway | 12/17/2020 |
Department of Transportation | D264795 |
$1,297,426.58
|
$1,297,426.58 |
06/23/2022 | 07/30/2023 | Placement of concrete box tunnel Empire State Trail under CSX bridge Rotterdam Schenectady County | Construction - Highway | 06/23/2022 |
Department of Transportation | D264842 |
$26,154,846.34
|
$17,314,072.59 |
09/28/2022 | 07/30/2025 | Bridge replacement NYS Route 12E over Chaumont River Chaumont Jefferson County | Construction - Highway | 09/28/2022 |
Department of Transportation | D265048 |
$2,269,415.10
|
$124,975.00 |
08/21/2023 | 11/30/2024 | Bridge replacement BIN 1027580 Route 58 over Chippewa Creek in Town of Morristown St Lawrence County | Construction - Highway | 08/21/2023 |
Department of Transportation | D264619 |
$2,771,047.10
|
$2,638,999.69 |
01/11/2022 | 11/30/2022 | Bridge rehab project Route 8 over Oneida Street Region 2 Oneida County | Construction - Highway | 01/11/2022 |
Department of Transportation | D264600 |
$2,505,566.96
|
$2,505,566.96 |
12/22/2021 | 01/13/2023 | Repair/replace 7 culverts various locations Region 2 counties | Construction - Highway | 12/22/2021 |
Department of Transportation | D263785 |
$5,160,059.62
|
$5,160,059.61 |
01/04/2019 | 11/30/2019 | Replace Rte 67 Bridge & Repair Route 2 Slope Washington & Rensselaer Counties | Construction - Highway | 01/04/2019 |
Office of General Services - Design & Construction | D45369C |
$1,371,000.00
|
$1,326,809.00 |
07/26/2017 | 09/15/2018 | Dam Modifications, Lower Pool Perch River Wildlife Refuge Jefferson County | Construction - Building | 07/26/2017 |
Office of General Services - Design & Construction | D45540C |
$2,056,083.00
|
$2,055,345.00 |
06/04/2018 | 09/13/2020 | Reconstruct Dam & Water Control Devices Perch River WMA Upper Pool & Stone Mills Jefferson County | Construction - Building | 06/04/2018 |
New York State Thruway Authority | D213980 |
$8,113,710.88
|
$0.00 |
10/07/2010 | 05/16/2013 | BRIDGE REHABS OVER BARGE CANAL @ ROUTE 5S & OVER MOHAWK RIVER, HERKIMER AND ONEIDA COUNTIES | Construction - Highway | 10/07/2010 |
New York State Thruway Authority | D214479 |
$18,449,443.86
|
$0.00 |
12/27/2016 | 11/01/2019 | BRIDGE REPLACEMENTS AT I90 OVER CSX RAILROAD AND VINE STREET, ONONDAGA COUNTY | Construction - Highway | 12/28/2016 |
New York State Thruway Authority | D214166 |
$884,447.61
|
$0.00 |
04/26/2013 | 09/27/2013 | Final | Construction - Miscellaneous | 08/17/2021 |
New York State Thruway Authority | D213401 |
$5,631,606.24
|
$0.00 |
11/05/2007 | 02/28/2010 | BRIDGE REPLACEMENT BUCKLEY RD OVER THUWAY MP 283.4 SYRACUSE DIVISION | Construction - Highway | 01/22/2009 |
New York State Thruway Authority | D214102 |
$404,201.47
|
$0.00 |
08/31/2011 | 09/28/2012 | STEEL REPAIRS TO THREE IMPACT DAMAGED BRIDGES VARIOUS LOCATIONS, SYRACUSE DIVISION | Construction - Highway | 08/31/2011 |
New York State Thruway Authority | D214166 |
$982,200.00
|
$0.00 |
04/26/2013 | 09/27/2013 | DREDGING ERIE CANAL LOCK E-12 MILEPOST E 197 MONTGOMERY COUNTY | Construction - Miscellaneous | 04/26/2013 |
New York State Thruway Authority | D214005 |
$284,554.80
|
$0.00 |
01/19/2011 | 03/30/2012 | STEEL REPAIR TO FOUR BRIDGES ALBANY DIVISION | Construction - Highway | 01/19/2011 |
New York State Thruway Authority | D214905 |
$4,658,542.00
|
$0.00 |
12/23/2022 | 11/17/2023 | Replacement of the North Main Street Bridge over I-90 at milepost 262-01 Madison county | Construction - Highway | 12/23/2022 |
New York State Thruway Authority | D214860 |
$4,843,934.80
|
$0.00 |
03/25/2022 | 07/01/2023 | Replace Judd Road Bridge over Thruway Whitestown Oneida county | Construction - Highway | 03/25/2022 |
New York State Canal Corporation | D214100 |
$673,534.37
|
$0.00 |
11/15/2012 | 11/15/2013 | RAILING INSTALLATIONS LOCK E14 AND ROCKY RIFT MOVABLE DAM SYRACUSE DIVISION | Construction - Miscellaneous | 11/15/2012 |
New York State Canal Corporation | D214136 |
$1,176,431.92
|
$0.00 |
01/26/2012 | 06/29/2012 | EMERGENCY REPAIRS TO UPRIGHT & LIGHTING AT MOVABLE DAMS 4 & 5 | Construction - Highway | 01/26/2012 |
New York State Canal Corporation | D214212 |
$1,335,263.92
|
$0.00 |
10/28/2013 | 10/10/2014 | DREDGING & UPLAND DISPOSAL SITE CONSTRUCTION LOCK E-6 SARATOGA COUNTY | Construction - Miscellaneous | 10/28/2013 |
New York State Canal Corporation | D214370 |
$1,651,034.00
|
$0.00 |
12/26/2014 | 12/31/2017 | STATEWIDE ON DEMAND INFASTRUCTURE REPAIRS TO CANAL FACILITIES & MARINE VESSEL RECOVERY | Construction - Highway | 12/26/2014 |
New York State Canal Corporation | D213874 |
$32,129,560.76
|
$0.00 |
10/07/2010 | 06/20/2014 | REHAB MOVABLE DAM 9 AT ERIE CANAL MP 207.48 MONTGOMERY COUNTY | Construction - Miscellaneous | 10/07/2010 |
New York State Canal Corporation | D213982 |
$252,720.20
|
$0.00 |
11/09/2010 | 06/21/2013 | STATE-WIDE MARINE VESSEL WHERE & WHEN RECOVERY CONTRACT | Construction - Miscellaneous | 11/09/2010 |
New York State Canal Corporation | D213616 |
$17,204,894.65
|
$0.00 |
04/24/2007 | 06/15/2010 | REHAB MOVABLE DAM 10 AT LOCK E-14 MONTGOMERY COUNTY | Construction - Highway | 10/29/2009 |
New York State Canal Corporation | D213758 |
$10,217,170.15
|
$0.00 |
11/21/2008 | 01/13/2011 | REHABILITATION OF LOCKS 0-5 & 0-8 OSWEGO CANAL, SYRACUSE DIVISION | Construction - Miscellaneous | 11/21/2008 |
New York State Canal Corporation | D214004 |
$1,391,684.84
|
$0.00 |
01/03/2010 | 12/29/2012 | LOWER MITER GATE REPLACEMENT LOCK CS-2 MPCS364.35 CAYUGA-SENECA CANAL, SENECA COUNTY | Construction - Miscellaneous | 01/03/2011 |
New York State Canal Corporation | D214046 |
$824,049.89
|
$0.00 |
07/15/2011 | 01/27/2013 | REPAIR TO SOUTHWEST APPROACH WALL AT LOCK 0-1 OSWEGO CANAL | Construction - Building | 07/15/2011 |
New York State Canal Corporation | D214068 |
$9,080,397.98
|
$0.00 |
01/11/2013 | 08/26/2016 | REHAB UTICA TAINTOR GATE AND DAM ONEIDA COUNTY | Construction - Highway | 01/11/2013 |
New York State Canal Corporation | D214161 |
$1,674,560.00
|
$0.00 |
01/14/2013 | 12/31/2014 | ON DEMAND REPAIRS CANAL FACILITIES AND MARINE VESSEL RECOVERY ALBANY TO BUFFALO DIVISIONS | Construction - Standby Contracts | 01/14/2013 |
New York State Canal Corporation | D214319 |
$2,719,653.57
|
$0.00 |
04/16/2015 | 12/31/2015 | Replacement of the Brewerton Terminal Pier (North) at MP E-305.00 on the Erie Canal Syracuse Div. | Construction - Highway | 04/16/2015 |
Office of Parks Recreation & Historic Preservation | D004531 |
$319,000.00
|
$319,000.00 |
07/28/2014 | 04/24/2015 | Otsquago Creek Bridge Rehab, Erie Canalway Trail - Village of Fort Plain. Project SA-HMT-2013-01 | Construction - Building | 07/28/2014 |