Vendor Name: TIOGA CONSTRUCTION COMPANY INC
Agency Name: Transportation, Department of
Department/Facility Name: Department of Transportation
Contract Number: D262108
Current Contract Amount: $1,074,890.78
Spending to Date: $1,074,890.78
Contract Type: Construction - Highway
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $1,157,430.40 |
11/02/2012 | 10/30/2013 | BRIDGE REHAB-SUPERSTRUCTURE REPLACEMENT RTE5 OVER SCONONDOA CREEK VILLAGE OF VERNON ONEIDA COUNTY | 11/02/2012 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $10,223.85 |
REVISED CONTRACT PLAN SHEETS CO 01 | 09/03/2013 | |
Amendment | $0.00 |
11/23/2013 | TIME EXTENSION | 11/04/2013 |
Amendment | ($94,292.47) |
CO4 Reg 2 FINAL settling up items | 01/24/2014 | |
Amendment | $1,583.24 |
CO 6 extra rebar cost resolution resolved | 03/25/2014 | |
Amendment | ($54.24) |
CO 7 FUEL PRICE ADJUSTMENT Village of Vern Oneida Co | 04/21/2014 |