Department/Facility | Contract Number | Current Contract Amount | Spending to Date | Contract Start Date | Contract End Date | Contract Description | Contract Type | Original Contract Approved/Filed Date |
---|---|---|---|---|---|---|---|---|
College of Technology at Farmingdale | T000456 |
$4,608,671.24
|
$4,608,490.84 |
05/22/2017 | 09/30/2020 | FSC PROJECT #2017-03 GREENLEY | Contracts Not Subject to OSC Pre-Audit | 06/02/2017 |
State University Construction Fund | D006636 |
$32,086,253.00
|
$12,413,688.00 |
09/04/2021 | 09/03/2025 | Electrical system upgrade at SUNY Downstate | Construction - Miscellaneous | 07/23/2021 |
Dormitory Authority of the State of New York | D192559 |
$4,686,493.00
|
$0.00 |
05/03/2016 | 08/11/2017 | PA Filed Contract-SUNY Purchase Ph.4 Bld45 Dorm-Big Haus Bathrm Rehab&Asbestos&Hazardous Mat.Abate. | Contracts Not Subject to OSC Pre-Audit | 05/10/2016 |
Dormitory Authority of the State of New York | D206767 |
$5,277,500.00
|
$0.00 |
12/06/2018 | 12/31/2020 | PA Filed Contract NYC College of Technology Namm Hall Entrance Replacement&Associated Asbestos Abate | Contracts Not Subject to OSC Pre-Audit | 12/20/2018 |
Dormitory Authority of the State of New York | D210506 |
$6,042,173.00
|
$0.00 |
09/30/2019 | 12/30/2021 | PA Filed Contract Restrooms Upgrade & Asbestos Abatement Haaren Hall John Jay College | Contracts Not Subject to OSC Pre-Audit | 10/21/2019 |
Dormitory Authority of the State of New York | D214798 |
$1,098,864.00
|
$0.00 |
01/19/2021 | 10/22/2021 | PA Filed Contract Catholic Charities Community Services NY standby generators and asbestos abatement | Contracts Not Subject to OSC Pre-Audit | 04/12/2021 |
Dormitory Authority of the State of New York | D215035 |
$1,311,973.00
|
$0.00 |
01/28/2021 | 08/25/2021 | PA filed contract storm hardening & hazardous materials abatement Kneseth Isreal Queens County | Contracts Not Subject to OSC Pre-Audit | 05/24/2021 |
Dormitory Authority of the State of New York | D210500 |
$1,625,403.89
|
$0.00 |
10/22/2019 | 11/05/2020 | PA Filed Contract - Abron Arts Center New Gas Generators and Asbestos Abatement | Contracts Not Subject to OSC Pre-Audit | 11/01/2019 |
Dormitory Authority of the State of New York | D212365 |
$6,979,500.00
|
$0.00 |
09/24/2020 | 09/22/2022 | PA Filed Contract Haaren Hall Athletic Dept upgrades and asbestos abatement | Contracts Not Subject to OSC Pre-Audit | 01/08/2021 |
Dormitory Authority of the State of New York | D220515 |
$3,136,587.00
|
$0.00 |
12/28/2022 | 05/01/2024 | PA filed contract switchgear replacement & asbestos abatement John Jay College New York County | Contracts Not Subject to OSC Pre-Audit | 01/03/2023 |
Dormitory Authority of the State of New York | D215761 |
$1,646,488.00
|
$0.00 |
08/03/2021 | 08/31/2022 | PA Filed Contract John Jay College Haaren Hall Gymnasium lighting upgrade | Contracts Not Subject to OSC Pre-Audit | 08/17/2021 |
Office of General Services - Design & Construction | D45082C |
$2,000,000.00
|
$625,541.75 |
02/19/2015 | 08/19/2016 | Job Order Contracting (JOC) Area 2 Construction | Construction - Building | 02/19/2015 |
Office of General Services - Design & Construction | D45122E |
$2,647,971.00
|
$2,627,283.00 |
07/22/2016 | 06/26/2019 | Provide Emergency Generator St. Albans Veterans Home 178-50 Linden Blvd Jamaica Queens County | Construction - Building | 07/22/2016 |
State University Construction Fund | T005402 |
$1,833,093.00
|
$1,833,093.00 |
07/22/2008 | 01/21/2014 | JOB ORDER CONTRACT - NYC REGION SUCF 80709 | Contracts Not Subject to OSC Pre-Audit | 05/24/2011 |
Dormitory Authority of the State of New York | D198167 |
$1,447,960.00
|
$0.00 |
05/25/2017 | 08/04/2017 | PA Filed Contract-SUNY College@Purchase Bld#5 Dormitory Big Haus Bathroom Rehab incl. Asbestos Abate | Contracts Not Subject to OSC Pre-Audit | 06/05/2017 |