Vendor Name: JEMCO ELECTRICAL CONTRACTORS
Agency Name: State University Construction Fund
Department/Facility Name: State University Construction Fund
Contract Number: D006636
Current Contract Amount: $32,212,940.00
Spending to Date: $12,908,068.00
Contract Type: Construction - Miscellaneous
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $31,661,288.00 |
06/30/2021 | 06/29/2025 | Electrical system upgrade at SUNY Downstate | 07/23/2021 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $643,500.00 |
Change order #1 insurance requirements | 09/01/2021 | |
Amendment | $0.00 |
09/03/2025 | Term correction | 09/09/2021 |
Amendment | $56,753.00 |
Change orders #2-4 for added containers, power source modifications and equipment layout revisions | 04/27/2022 | |
Amendment | $58,075.00 |
Change order #5 for Motor Control Center electrical upgrades | 04/29/2022 | |
Amendment | $4,860.00 |
Change order #6 for scan floor slab to determine feasibility of below grade conduit installation | 08/26/2022 | |
Amendment | $20,647.00 |
Change order #7 is for door hardware changes | 03/13/2023 | |
Amendment | ($1,000,000.00) |
Change order #8 is to reduce contract field order allowance | 06/14/2023 | |
Amendment | $242,572.00 |
Change orders 9 and 10 are to increase diameter of water pipe and install additional conduit | 09/05/2023 | |
Amendment | $57,302.00 |
Change order 12 for additional asbestos abatement and insulation removal | 10/18/2023 | |
Amendment | $43,584.00 |
Change order 11 is for additional abatement | 11/01/2023 | |
Amendment | $26,749.00 |
Change order 14 to increase the diameter of domestic water pipe | 12/08/2023 | |
Amendment | $54,654.00 |
Change order 13 for demolition and abatement of piping and associated materials | 12/18/2023 | |
Amendment | $216,269.00 |
Change order 15 is for additional asbestos abatement | 04/08/2024 | |
Amendment | $126,687.00 |
Change order 16 is for increase of required insurance limits | 05/15/2024 |