Department/Facility | Contract Number | Current Contract Amount | Spending to Date | Contract Start Date | Contract End Date | Contract Description | Contract Type | Original Contract Approved/Filed Date |
---|---|---|---|---|---|---|---|---|
Office of General Services - Design & Construction | DQ1794H |
$483,483.00
|
$451,683.00 |
03/13/2020 | 09/19/2020 | Replace Cooling Tower Holland Ave Office Building Albany County | Construction - Building | 03/13/2020 |
Office of General Services - Design & Construction | D45259H |
$1,338,632.00
|
$1,301,032.00 |
05/08/2019 | 11/13/2020 | Replace Windows Boilers & HVAC Renovations Units 1 Through 4 & Medical Wing Brookwood SC Columbia Co | Construction - Building | 05/08/2019 |
Office of General Services - Design & Construction | D45509H |
$1,638,638.00
|
$1,530,679.00 |
05/07/2019 | 02/20/2020 | Replace Boilers Brookwood Secure Center Columbia County | Construction - Building | 05/07/2019 |
Office of General Services - Design & Construction | DEE625H |
$600,000.00
|
$544,302.41 |
08/11/2021 | 11/14/2022 | Repair Steam Leaks, repair cracked manhole cover, bldg 20 & 83, Midstate CF, Oneida Co | Construction - Building | 09/23/2021 |
Office of General Services - Design & Construction | DED676P |
$100,000.00
|
$88,501.00 |
12/13/2017 | 04/12/2018 | Repair Steam Leaks, Bldg. 39 Central NY PC, New York County | Construction - Building | 01/23/2018 |
Office of General Services - Design & Construction | DED874H |
$300,000.00
|
$121,100.00 |
07/25/2018 | 11/28/2018 | Investigate & Repair Chiller #1 Provide Temp Chiller Coxsackie CF Greene County | Construction - Building | 09/13/2018 |
Office of General Services - Design & Construction | DEE084H |
$650,000.00
|
$640,322.00 |
04/24/2019 | 12/01/2019 | Repair Steam Leaks Washington CF Washington County | Construction - Building | 05/30/2019 |
Office of General Services - Design & Construction | D45460H |
$1,251,251.00
|
$1,185,609.00 |
08/29/2018 | 01/31/2020 | Repair & Replace HVAC System Brookwood Secure Center Columbia County H | Construction - Building | 08/29/2018 |
Office of General Services - Design & Construction | D43262H |
$5,877,971.00
|
$5,693,693.21 |
12/09/2011 | 08/03/2018 | LONG TERM CARE ADDITION & RENOVATION WALSH RMU MOHAWK CF | Construction - Building | 12/09/2011 |
Office of General Services - Design & Construction | D44808H |
$10,237,268.00
|
$9,985,579.50 |
02/27/2014 | 09/20/2015 | Renovate Building 5 @ Harriman State Office Campus, Albany | Construction - Building | 02/27/2014 |
Office of General Services - Design & Construction | D44808P |
$2,391,075.00
|
$2,302,009.00 |
02/27/2014 | 09/20/2015 | Renovate Building 5 @ Harriman State Office Campus, Albany | Construction - Building | 02/27/2014 |
Office of General Services - Design & Construction | D47436H |
$1,388,382.00
|
$901,276.26 |
07/25/2023 | 01/30/2025 | Provide HVAC & energy efficiency improvements at NYS Museum & Veterans Research Ctr in Saratoga Co | Construction - Building | 07/25/2023 |
Office of General Services - Design & Construction | D46254P |
$500,000.00
|
$0.00 |
09/14/2020 | 09/13/2021 | Job Order Contracting JOC Area 4 | Construction - Highway | 09/14/2020 |
Office of General Services - Design & Construction | D44981H |
$682,682.00
|
$4,841.00 |
10/04/2019 | 01/30/2021 | Rehabilitate Tunnel & Connection Points NYS Capitol to AE Smith Building Albany County | Construction - Building | 10/04/2019 |
Office of General Services - Design & Construction | D45723H |
$525,755.00
|
$524,995.00 |
03/18/2022 | 03/30/2024 | Replace roof at the center courtyard main floor at the NYS Capitol in Albany County | Construction - Building | 03/18/2022 |
Office of General Services - Design & Construction | D47042H |
$733,000.00
|
$631,298.63 |
01/17/2023 | 06/02/2024 | Modify boiler controls Sheridan Avenue steam plant Albany County | Construction - Building | 01/17/2023 |
Office of General Services - Design & Construction | DQ1844H |
$142,000.00
|
$12,777.50 |
08/12/2024 | 10/12/2025 | HVAC work for computer forensic laboratory expansion at State Office Campus in Albany Co. | Construction - Building | 08/12/2024 |
Office of General Services - Design & Construction | D45818P |
$7,739,085.00
|
$5,796,856.64 |
09/21/2021 | 08/09/2026 | Replace toilets & flushometers bldgs 3 & 4 & upgrade wiring bldg 3 Eastern CF Ulster County | Construction - Building | 09/21/2021 |
Office of General Services - Design & Construction | D46010H |
$3,515,204.00
|
$3,513,518.00 |
01/27/2021 | 02/27/2024 | Replace heat exchangers housing units 8 9 10 11 & 12 bldgs 1 4 & 13 Upstate CF Malone NY Franklin Co | Construction - Building | 01/27/2021 |
Office of General Services - Design & Construction | DM3186P |
$1,281,000.00
|
$431,671.64 |
03/27/2024 | 11/29/2025 | Mitigate water infiltration and repair building 22, Mohawk Correctional Facility, Oneida County | Construction - Building | 03/27/2024 |
Office of General Services - Design & Construction | D47142P |
$276,000.00
|
$30,366.74 |
03/22/2024 | 01/14/2026 | Renovate Unadilla & East Worcester rest areas in DOT Region 9 Otsego & Delaware Counties | Construction - Building | 03/22/2024 |
Office of General Services - Design & Construction | D47142H |
$199,000.00
|
$140,432.80 |
03/22/2024 | 01/14/2026 | Renovate Unadilla & East Worcester rest areas in DOT Region 9 Otsego & Delaware Counties | Construction - Building | 03/22/2024 |
Office of General Services - Design & Construction | DEE921H |
$150,000.00
|
$33,777.15 |
12/19/2022 | 04/18/2023 | Repair steam leak Sheridan Ave Power Plant Albany County | Construction - Building | 01/05/2023 |
Office of General Services - Design & Construction | D44186H |
$803,574.00
|
$779,313.00 |
09/20/2013 | 12/17/2015 | Provide ventilation, Main School Bldgs Green & Washington CF @ Various DCS Facilities | Construction - Building | 09/20/2013 |
Office of General Services - Design & Construction | DM3137H |
$453,453.00
|
$429,953.00 |
09/24/2021 | 02/10/2023 | Replace air handlers/HVAC system bldg 12 Marcy CF Oneida County | Construction - Building | 09/24/2021 |
Office of General Services - Design & Construction | D45980H |
$500,000.00
|
$31,941.00 |
11/06/2019 | 12/20/2022 | Provide Concrete Repairs Empire State Plaza Albany County | Construction - Building | 11/06/2019 |
Office of General Services - Design & Construction | D47126H |
$2,000,000.00
|
$0.00 |
03/29/2022 | 06/26/2025 | Repair underground direct bury system condensate & chilled water piping Various OG Facilities Albany | Construction - Building | 03/29/2022 |
Office of General Services - Design & Construction | D47098H |
$587,031.00
|
$566,029.00 |
07/26/2022 | 12/18/2023 | Upgrade heating and cooling systems region 2 Rome Oneida County | Construction - Building | 07/26/2022 |
Office of General Services - Design & Construction | D45858H |
$5,967,069.00
|
$5,473,889.03 |
12/17/2021 | 12/17/2025 | Rehabilitate cell blocks C & D Building 2 Great Meadow Correctional Facility Washington County | Construction - Building | 12/17/2021 |
Office of General Services - Design & Construction | DEE949H |
$100,000.00
|
$37,550.65 |
02/03/2023 | 08/02/2023 | Repair hot water Coxsackie CF Greene County | Construction - Building | 03/10/2023 |
Office of General Services - Design & Construction | D45583H |
$249,249.00
|
$170,178.67 |
05/20/2022 | 08/02/2025 | Replace Switchgear Empire State Plaza Albany County | Construction - Building | 05/20/2022 |
Office of General Services - Design & Construction | D47209P |
$541,000.00
|
$150,102.37 |
03/26/2024 | 04/30/2026 | Provide concrete repairs Empire State Plaza in Albany County | Construction - Building | 03/26/2024 |
Office of General Services - Design & Construction | D46095P |
$2,699,000.00
|
$1,374,031.55 |
06/20/2023 | 10/29/2025 | Provide structural repairs at the Sheridan Hollow Parking Facility Albany County | Construction - Building | 06/20/2023 |
Office of General Services - Design & Construction | DED487H |
$600,000.00
|
$542,170.00 |
05/10/2017 | 12/31/2017 | Re-Tube Boiler #2 due to leaking, Great Meadow CF, Washington County | Construction - Building | 06/14/2017 |
New York State Thruway Authority | D214793 |
$1,494,074.60
|
$0.00 |
12/31/2021 | 06/30/2022 | Computer room renovations administrative headquarters Albany division Albany county | Construction - Building | 06/04/2021 |
State University Construction Fund | T005426 |
$48,179.00
|
$48,179.00 |
11/04/2008 | 12/15/2010 | MECHANICAL SYSTEM UPGRADES SUCF 36083 SYSTEM ADMINISTRATION ALBANY | Contracts Not Subject to OSC Pre-Audit | 05/05/2011 |
State University Construction Fund | T006319 |
$389,063.00
|
$389,063.00 |
05/18/2017 | 10/31/2018 | SUCF 09003 Replace Humidifica | Contracts Not Subject to OSC Pre-Audit | 05/23/2017 |
State University Construction Fund | T006510 |
$10,245,492.00
|
$10,245,492.00 |
08/27/2019 | 09/01/2023 | SUCF011006 Upgrade Central Pl | Contracts Not Subject to OSC Pre-Audit | 08/27/2019 |
State University Construction Fund | T006205 |
$820,910.00
|
$820,910.00 |
02/18/2016 | 09/05/2017 | SUCF 36128 Mechanical Systems | Contracts Not Subject to OSC Pre-Audit | 02/22/2016 |
State University Construction Fund | T006206 |
$1,250,617.00
|
$1,250,617.00 |
02/18/2016 | 08/12/2017 | SUCF 09403 Rehabilitate HVAC | Contracts Not Subject to OSC Pre-Audit | 02/22/2016 |
Office of Parks Recreation & Historic Preservation | D006204 |
$456,800.00
|
$13,205.00 |
04/29/2024 | 04/29/2025 | PC Site improvements & construction of maintenance bldg at Olana State Historic Site in Columbia Co | Construction - Building | 04/29/2024 |
Office of Parks Recreation & Historic Preservation | D004076 |
$199,500.00
|
$199,500.00 |
05/05/2011 | 04/01/2012 | THOMPSON'S LAKE SP-COMFORT STATION REPL (SC) | Construction - Building | 05/05/2011 |