Vendor Name: DIGESARE MECHANICAL INC
Agency Name: General Services, Office of
Department/Facility Name: Office of General Services - Design & Construction
Contract Number: D46010H
Current Contract Amount: $3,515,204.00
Spending to Date: $3,513,518.00
Contract Type: Construction - Building
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $2,822,222.00 |
01/27/2021 | 12/29/2021 | Replace heat exchangers housing units 8 9 10 11 & 12 bldgs 1 4 & 13 Upstate CF Malone NY Franklin Co | 01/27/2021 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $177,476.00 |
CO#1 76370 Additional piping valves & materials | 10/25/2021 | |
Amendment | $0.00 |
10/26/2022 | CO# 2 76370A No cost time extension | 11/26/2021 |
Amendment | $63,608.00 |
CO#3 76558 Replace hot water heater in Building 9 | 03/01/2022 | |
Amendment | $14,606.00 |
CO#4 76881 Building 10 booster pump | 03/16/2022 | |
Amendment | $38,276.00 |
CO#6 76885 Restore hot water supply | 03/24/2022 | |
Amendment | $79,496.00 |
CO #5 76877 Removal and installation of new heaters | 04/14/2022 | |
Amendment | $5,839.00 |
C0#7 76877A Building 8 tank charging pump operation | 07/05/2022 | |
Amendment | $21,150.00 |
CO#8 76380B pipe insulation and painting | 08/08/2022 | |
Amendment | $0.00 |
09/28/2023 | CO #9 77604 no cost time extension | 08/10/2022 |
Amendment | $200,634.00 |
CO #10 77491 Provide modifications to pumps | 11/04/2022 | |
Amendment | $58,563.00 |
CO#11 77492 Provide bypass and pressure transmitters | 11/22/2022 | |
Amendment | $14,612.00 |
CO#12 78195 remove & replace balancing valves in return piping | 02/23/2023 | |
Amendment | $9,478.00 |
CO 13 77492A Perform hot taps to install instrument root | 03/08/2023 | |
Amendment | $12,772.00 |
CO#14 77491A Pump replacement | 03/23/2023 | |
Amendment | $17,896.00 |
CO#15 78404 mechanical and controls support for hot water system preliminary balancing | 05/05/2023 | |
Amendment | ($63,608.00) |
CO#16 76558A Amend value of CO#3 with Control# 76558 to $0 | 08/03/2023 | |
Amendment | ($9,521.00) |
CO#17 76881A omit booster pump work in building 10 Upstate CF | 08/21/2023 | |
Amendment | $0.00 |
02/09/2024 | CO#18 79188 No cost time extension | 10/12/2023 |
Amendment | ($11,032.00) |
CO#19 78910 Credit for omitted domestic hot water heater work | 12/21/2023 | |
Amendment | $62,737.00 |
CO#20 80060 Delay claim | 07/10/2024 | |
Amendment | $0.00 |
02/27/2024 | CO#21 81267 No cost time extension | 08/12/2024 |