Vendor Name: CRESCENT CONTRACTING CORP
Agency Name: General Services, Office of
Department/Facility Name: Office of General Services - Design & Construction
Contract Number: D44049P
Current Contract Amount: $530,388.00
Spending to Date: $530,293.00
Contract Type: Construction - Building
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date | |
---|---|---|---|---|---|---|
Original Contract data not available for this contract record. |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $5,339.00 |
REHAB KINGSBORO ADDICTION CENTER CN | 06/15/2012 | |
Amendment | $5,085.00 |
REHAB KINGSBORO ADDICTION CENTER CN 64053 | 06/15/2012 | |
Amendment | $5,829.00 |
REHAB KINGSBORO ADDICTION CTR CN 65305 CO #3 | 02/12/2013 | |
Amendment | $1,745.00 |
REHAB KINGSBORO ADDICTION CTR CO65474 | 02/20/2013 | |
Amendment | $20,000.00 |
Control# 65731 INCREASE THE FIELD ORDER CONTI | 03/28/2013 | |
Amendment | $4,900.00 |
REHAB KINGSBORO ADDICTION CTR - KINGSBORO ATC CN65413 Remove/Replace Deteriorted pipe insulation | 03/11/2013 | |
Amendment | $10,178.00 |
REHAB KINGSBORO ADDICTION CTR CO65738 | 04/12/2013 | |
Amendment | $8,449.00 |
Control# 65835 REPLACE VARIOUS PLUMBING accessories in Phase 1B bathrooms | 05/01/2013 | |
Amendment | $543.00 |
Control# 65857 Relocate exist sprinkler head & related piping in 1st Fl Multipurpose Rm | 05/01/2013 | |
Amendment | $20,051.00 |
Control# 66001 PHASE 2B - PROVIDE TWENTY (20) new wall mounted toilets & faucets | 06/18/2013 | |
Amendment | $12,369.00 |
CO# 12 Control# 66343 ROOF #5 - PROVIDE 4" Roof drain(6th Fl Roof-East side) | 07/31/2013 | |
Amendment | $4,443.00 |
CO# 13 Control# 66498 PHASE 2B - Prov, replace & reinstall plumbing trim in various loc's | 09/20/2013 | |
Amendment | $5,950.00 |
CO# 14 Control# 66684 PHASE 2B - REPLACE & RAISE 4 SPRINKLER HD & 4 LAUNDRY SINKS;HI PRIORITY | 10/16/2013 | |
Amendment | $16,024.00 |
CO#15 Control#64175A Reimburse contractor for a credit taken that should have been an add | 12/19/2013 | |
Amendment | $6,860.00 |
06/27/2016 | CO# 16 #66951 TE & Phase 2A Toilet & Faucet replacemt Kingsboro ATC | 01/31/2014 |
Amendment | $5,870.00 |
06/30/2016 | CO# 17 #66850 TE & $ Domestic Water pressure tank Kingsboro ATC | 02/03/2014 |
Amendment | $6,579.00 |
06/30/2016 | CO# 21 67405 Relocate Sprinkler Main outside the Janitor Closet Kingsboro ATC | 05/23/2014 |
Amendment | $17,593.00 |
06/30/2016 | CO# 23 67472 Provide new 3" waste line Kingsboro ATC | 06/02/2014 |
Amendment | ($250.00) |
06/30/2016 | CO# 22 67356 Demo & provide hote&cold water lines @ new knee wall Kingsboro ATC | 06/03/2014 |
Amendment | $664.00 |
CO# 19 67054 Resubmittal: Repair shower mixing valve in bathroom 622 Kingsboro ATC | 05/28/2014 | |
Amendment | $1,112.00 |
CO# 20 67243 Resubmittal Provide Pressure Reducing Valve Kingsboro ATC | 05/29/2014 | |
Amendment | $1,345.00 |
CO# 18 67259 Resubmittal Prov credit for not plugging floor drain Rm210 &add automatic sprinklerhead | 05/29/2014 | |
Amendment | $3,353.00 |
CO# 24 67681 Replace 16 lf of existing 3" gase line w/ new 2" line Rehab Kingsboro ATC | 07/21/2014 | |
Amendment | $10,374.00 |
CO#25 67854 Prov & install 7 faucets & 6 grinders @ existing kitchen sinks Rehab Kingsboro ATC | 10/29/2014 | |
Amendment | $4,867.00 |
CO# 26 68135 Resubmittal Remove & replace existing 3" waste pipe Kingsboro ATC | 12/29/2014 | |
Amendment | $2,081.00 |
CO# 27 68096 Relocate sprinkler head @2nd Fl corridor-reconnect combi oven@new kitchen | 12/31/2014 | |
Amendment | $12,364.00 |
CO# 29 68465 Replace Trim at Shower Rms Phase 2A & Remove Lines @ Temp Kitchen Kingsboro ATC | 04/20/2015 | |
Amendment | ($6,467.00) |
CO# 28 68587 Provide Credit for Cast Iron & Gas Tight Cleanout &Sanitary/storm Caps Kingsboro ATC | 05/15/2015 | |
Amendment | ($457.00) |
06/30/2016 | CO # 30 69514 TE & Credit for work not completed(done under other contract),Kingsboro ATC | 02/05/2016 |
Amendment | ($4,900.00) |
06/30/2016 | CO#70132 Credit for CO65413(remv/replc deteriorated pipe insulation) Rehab Kingsboro Addiction Ctr | 06/16/2016 |