Vendor Name: DIGESARE MECHANICAL INC
Agency Name: General Services, Office of
Department/Facility Name: Office of General Services - Design & Construction
Contract Number: D43262H
Current Contract Amount: $5,877,971.00
Spending to Date: $5,693,693.21
Contract Type: Construction - Building
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date | |
---|---|---|---|---|---|---|
Original Contract data not available for this contract record. |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | ($7,500.00) |
PER RFI 22, PROVIDE A SUITABLE 64650 | 09/12/2012 | |
Amendment | $959.00 |
PER RFI 132, PROVIDE METER BYP 65049 | 11/21/2012 | |
Amendment | ($3,943.00) |
PER IB 36, DELETE INSTALLATION 65056 | 01/22/2013 | |
Amendment | $49,267.00 |
64731 per IB 37, provide drainage, drain lines & mechanical joints restraints | 02/15/2013 | |
Amendment | ($27,538.00) |
65593 | 07/12/2013 | |
Amendment | ($623.00) |
DELETE 6" GATE VALVE ON LPS SU | 08/08/2013 | |
Amendment | $18,659.00 |
PROVIDE A 2ND PRV-1 STATION IN ROOB G 01 66661 | 01/10/2014 | |
Amendment | ($6,987.00) |
PROVIDE A SUITABLE CREDIT FOR | 02/20/2014 | |
Amendment | $4,351.00 |
67027 remove exsisting heater unit in receiving room, replace with new one | 03/28/2014 | |
Amendment | $5,165.00 |
67159 .3/4' copper pipe on 2 fl to basement | 03/28/2014 | |
Amendment | $2,640.00 |
67162 additional labor investigate underground manhole system seq 11 | 04/21/2014 | |
Amendment | $4,628.00 |
67158 connect 2 " vent pipes | 05/07/2014 | |
Amendment | $4,690.00 |
PER RFI451: DUCT MOUNTED TEMPE | 05/07/2014 | |
Amendment | $1,890.00 |
67610 provide switch ends switches on 3 actuators in basement ductwork CO 14 | 07/14/2014 | |
Amendment | $4,191.00 |
67542 new exhaust fan Mohawk CF | 08/11/2014 | |
Amendment | $59,876.00 |
CO 67366 remove exsisting air handling units, to make room for new units Mohawk CF | 08/19/2014 | |
Amendment | $2,665.00 |
67669 remove fin tube radiation componets at the tie in G-wing Mohawk CF | 08/26/2014 | |
Amendment | $3,307.00 |
RFI499-TYPE A1 MOTOR CONTROLLE | 08/25/2014 | |
Amendment | $1,831.00 |
68075 Seq 19 PROVIDE 3/4" CIRCUIT SETTERS | 10/20/2014 | |
Amendment | $6,571.00 |
67972 provide exhaust fan, ductwork, motorized damper Seq 20 Mohawk CF | 10/24/2014 | |
Amendment | $5,850.00 |
68012 impeller in hot water pumps seq 21 Mohawk CF | 10/24/2014 | |
Amendment | $589.00 |
68062 drip pan mounted North mech room basement G wing, Mohawk CF seq 22 | 11/06/2014 | |
Amendment | $487.00 |
68278 rovide 2 wall plates Mohawk CF Seq 23 | 01/29/2015 | |
Amendment | $4,928.00 |
B-WING DUCTWORK/GRD REVISIONS | 01/29/2015 | |
Amendment | $133,333.00 |
C.O. 68251- INCREASE THE CONTINGENCY ALLOWANCE | 01/22/2015 | |
Amendment | $10,725.00 |
68501 additional demo E wing tunnel, condensate pipe G wing Mohawk CF | 03/06/2015 | |
Amendment | $46,388.00 |
CO#69023 - Add'l labor for installation of Underdeck Insulation, Long Term Care Addition, Mohawk CF | 07/08/2015 | |
Amendment | ($500.00) |
08/03/2018 | CO 29 70592 Provide a credit to delete the closeout Project Manual Mohawk CF | 10/14/2016 |
Amendment | ($3,483.00) |
08/03/2018 | CO 30 70768 credit for not providing recommended chemical treatment chillers Mohawk CF | 12/12/2016 |