Vendor Name: EL SOL CONTRACTING & CONST CORP
Agency Name: Transportation, Department of
Department/Facility Name: Department of Transportation
Contract Number: D900015
Current Contract Amount: $12,881,637.50
Spending to Date: $12,881,637.50
Contract Type: Construction - Miscellaneous
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $12,826,000.00 |
06/18/2014 | 11/12/2015 | Carll's Straight Path Bridge Over I-495 Design Build | 06/19/2014 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $0.00 |
01/31/2016 | CO#009 NCTE, Carll's Straight Path Bridge Over I-495 Design Build | 02/01/2016 |
Amendment | $0.00 |
03/31/2016 | CO#011 Extension of Time Carll's Straight Path Bridge Over I-495 Design Build | 02/25/2016 |
Amendment | $58,249.30 |
03/31/2016 | CO#12 New Item FAW-Relocating, Furnishing&installing hwy lighting, D/B Carll's Straight Path Brid | 05/02/2016 |
Amendment | $0.00 |
04/30/2016 | CO#013, NCTE Carll's Straight Path Bridge Over I-495 Design Build | 05/13/2016 |
Amendment | $0.00 |
05/31/2016 | CO#014 Time extension, Carll's Straight Path Bridge Over I-495 Design Build | 06/15/2016 |
Amendment | ($2,611.80) |
05/31/2016 | CO#16 Item Decrease Carll's Straight Path Bridge Over I-495 Design Build | 10/04/2016 |
Amendment | $0.00 |
05/31/2016 | Closeout Carll's Straight Path Bridge Over I-495 Design Build | 02/16/2017 |