Vendor Name: SEALAND CONTRACTORS CORP
Agency Name: Transportation, Department of
Department/Facility Name: Department of Transportation
Contract Number: D262281
Current Contract Amount: $18,731,119.46
Spending to Date: $18,731,119.46
Contract Type: Construction - Highway
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $18,959,993.30 |
04/16/2013 | 10/31/2014 | PAVEMENT & BRIDGE REHABILITION INTERSTATE 690 | 04/16/2013 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $18,805.00 |
CO# 2 - MAJOR DESIGN REVISION | 10/24/2013 | |
Amendment | $7,072.23 |
CO #4 - FAW for Bridge Rail Installation - Pavement & Bridge Rehabilitation Interstate 690 | 11/22/2013 | |
Amendment | $0.03 |
CO# 8- design revisions - Pavement & Bridge Rehab, Interstate 690 | 12/13/2013 | |
Amendment | $4,799.90 |
CO#9 Milling down joint repairs Pavement & Bridge Rehabilitation Interstate 690 | 05/01/2014 | |
Amendment | $12,465.68 |
CO#10 Add'l joint repairs Pavement & Bridge Rehabilitation I-690 | 05/13/2014 | |
Amendment | $8,550.66 |
CO# 11 Utility conflict - Prev Engagemt w/ Onondaga West | 05/22/2014 | |
Amendment | $5,951.19 |
CO# 12 Temp Access Rd construction to access wksite due to chgs in WZTC plan Pavemt/Brid Rehab I-690 | 06/02/2014 | |
Amendment | $65,805.66 |
CO# 13 Add'l night work ordered to accomodate the NYS Fair - Lighting | 06/23/2014 | |
Amendment | $931.52 |
CO# 15 Add'l Radius Curb FAW - Var Locations Pavemt & Bridge Rehab I690 | 07/03/2014 | |
Amendment | $3,959.12 |
CO# 14 Pave under guiderail approaches Rte 690 over Rte 370 | 07/15/2014 | |
Amendment | $4,305.00 |
CO# 17 Agreed prices for delineators Pavemt & Brid Rehab Interstate 690 | 10/07/2014 | |
Amendment | $484,752.84 |
CO# 6 Crossover Construction Pavemt & Brid Rehab I 690 | 11/04/2014 | |
Amendment | $44,585.10 |
CO# 16 FAW Night Work Dispensation conflicts in main line peak hr I 690 Pavemt & Brid Rehab Project | 11/19/2014 | |
Amendment | $0.00 |
12/31/2014 | CO# 19 NCTE due to added wk/new drawings/winter postponed work I 690 Pavemt & Brid Rehab Proj | 12/01/2014 |
Amendment | $300,000.00 |
CO# 20 FAW Mid November 2014 Buffalo Snow Event - Filed 112 Exempt | 12/24/2014 | |
Amendment | $32,321.43 |
CO# 21 Increase for bar lock couplers item I 690 Pavemt & Brid Rehab Proj | 01/15/2015 | |
Amendment | $9,000.62 |
CO# 18 Additional Curb Pavemt & Bridge Rehab I-690 | 02/19/2015 | |
Amendment | $11,628.39 |
CO# 24 Emergency Work FA - Mid November Lake Effect Snow Event Exec Order 137 | 03/02/2015 | |
Amendment | ($1,133,013.65) |
CO#22 Cleanup CO Pavement & Bridge Rehab I-690 | 04/30/2015 | |
Amendment | $0.00 |
07/31/2015 | CO#26 NCTE Pavement & Bridge Rehab I-690 | 05/07/2015 |
Amendment | $30,579.69 |
CO#23 Add'l bridge railing posts & box beam guide railing Pavement & Bridge Rehab I-690 | 05/12/2015 | |
Amendment | $45,292.17 |
CO#25 Pavement & Bridge Rehab I-690 | 06/17/2015 | |
Amendment | $257,015.31 |
CO#27 Pavement & Bridge Rehab I-690 | 06/25/2015 | |
Amendment | ($412,076.06) |
07/31/2015 | CO#28 Cleanup Pavement & Bridge Rehab I-690 | 08/08/2016 |
Amendment | $0.00 |
07/31/2016 | CO#29 NCTE Pavement & Bridge Rehab I-690 | 08/19/2016 |
Amendment | $15,216.77 |
07/31/2016 | CO#030 PAVEMENT & BRIDGE REHABILITION INTERSTATE 690 | 02/16/2017 |
Amendment | ($29,822.52) |
07/31/2016 | CO#031, CLEAN UP, PAVEMENT & BRIDGE REHABILITION INTERSTATE 690 | 04/14/2017 |
Amendment | ($16,999.92) |
CO#32 Adjust LD and Contractor Charges I 690Pavement/Bridge Rehab project Region 3 | 01/10/2018 |