Vendor Name: RESTANI CONSTRUCTION CORP
Agency Name: Transportation, Department of
Department/Facility Name: Department of Transportation
Contract Number: D262162
Current Contract Amount: $14,366,168.92
Spending to Date: $14,366,168.92
Contract Type: Construction - Highway
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $12,233,135.20 |
05/24/2013 | 03/31/2014 | MILL & RESURFACE ASPHALT ON CROSS BRONX EXPWY - BRONX COUNTY | 05/24/2013 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $477,817.06 |
CO #1-Increase for catch basin frame/grate - MILL & RESURFACE ASPHALT ON CROSS BRONX EXPWY-Bronx Co. | 10/30/2013 | |
Amendment | ($1.00) |
CO#2-add new/decrease-MILL & RESURFACE ASPHALT ON CROSS BRONX EXPWY - BRONX COUNTY | 11/08/2013 | |
Amendment | $910,000.00 |
seq 3, CO #4 add 402.018902 & 604.07240010- Asphalt on Cross Bronx Expy-Bronx Co | 02/18/2014 | |
Amendment | $0.00 |
11/14/2014 | CO #5 - NCTE - Mill & resurface Asphalt on Cross Bronx Expy-Bronx Co | 02/26/2014 |
Amendment | ($1.00) |
CO#6-add 655.00050011,655.00060011- MIll & resurface asphalt on Cross Bronx Expwy-Bronx Co. | 03/14/2014 | |
Amendment | $1,871,253.25 |
CO#7 - Increase for Full Depth PCC, Pressure Relief Joints, Removal of Slab for Catch Basin | 05/28/2014 | |
Amendment | ($1.00) |
OOC 7 Incidental construction | 07/30/2014 | |
Amendment | ($1.00) |
CO 8 increase and decreases in items, new items Region 11 | 10/09/2014 | |
Amendment | $0.00 |
06/30/2015 | CO 10 No cost time extension region 11 | 12/24/2014 |
Amendment | ($1.25) |
CO#11 - Increases/Decreases, MILL & RESURFACE ASPHALT ON CROSS BRONX EXPWY - BRONX COUNTY | 03/03/2015 | |
Amendment | ($1.98) |
CO 9 NB Cross Bronx Expressway under Jerome Avenue and Grand Concourse Region 11 | 05/26/2015 | |
Amendment | ($1.25) |
06/30/2015 | CO 10 Resurface Cross Bronx Expy Region 11 settling up items | 12/04/2015 |
Amendment | ($1,126,028.11) |
06/30/2015 | CO 16 State of Good Repair Cross Bronx Final close out Region 11 | 02/26/2016 |
Amendment | $0.00 |
06/30/2015 | CO 19 Cross Bronx An error was made in prior Change Order #017/OOC#016 subtracting 5187.Expressway | 06/08/2016 |
Amendment | ($8,000.00) |
06/30/2015 | CO 18 Clean up & Liquidated damages Cross Bronx Expressway Region 11 | 08/24/2016 |
Amendment | $8,000.00 |
06/30/2015 | CO 23 State of Good Repair 111 Cross Bronx correct Engineering charges Region 11 | 09/21/2016 |
Amendment | $0.00 |
06/30/2015 | Final Agreement Mill and Resurface Asphalt on Cross Bronx Expressway Bronx County | 08/16/2017 |