Vendor Name: LANE CONSTRUCTION CORPORATION
Agency Name: Transportation, Department of
Department/Facility Name: Department of Transportation
Contract Number: D262025
Current Contract Amount: $28,741,874.29
Spending to Date: $28,741,874.29
Contract Type: Construction - Highway
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $29,002,653.26 |
06/22/2012 | 07/15/2013 | Accelerated Bridge Rehab of I87 over the Mohawk River, Colonie & Halfmoon | 06/22/2012 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $12,109.45 |
CO#6 - Increase for Bearing Pad Epoxy and Drainage Inlet Extensions | 04/08/2013 | |
Amendment | $37,170.00 |
CO#8-Tow Truck Service-Accelerate Bridge Rehab of I-87 over the Mohawk River, Colonie & Halfmoon | 04/18/2013 | |
Amendment | $15,049.21 |
CO # 15-Traffic loop installation-Accelerate Bridge Rehab, I87 over Mohawk River, Colonie & Halfmoon | 08/23/2013 | |
Amendment | $34,561.21 |
CO#7-Survery&WZTCforAdd'l Lane-Accelerated Bridge Rehab I-87 over Mohawk River,Colonie&Halfmoon | 09/06/2013 | |
Amendment | $8,794.08 |
CO # 17 -Traffic Control-No U-Turn-Accelerated Bridge Rehab I-87 over Mohawk River,Colonie&Halfmoon | 09/13/2013 | |
Amendment | $9,767.51 |
CO # 18 - Tube Joint Repair - Accelerated Bridge Rehab I-87 over Mohawk River, Colonie & Halfmoon | 10/03/2013 | |
Amendment | $4,362.00 |
CO # 10 - Box Beam Guide Rails - Accelerated Bridge Rehab I-87 over Mohawk River, Colonie & Halfmoon | 10/18/2013 | |
Amendment | $16,370.86 |
CO #14 - Beam Seat Notching- Accelerated Bridge Rehab I-87 over Mohawk River, Colonie & Halfmoon | 10/31/2013 | |
Amendment | ($1,870,000.00) |
CO #33 - Removal of Lane Rental-Accelerated Bridge Rehab I-87 over Mohawk River, Colonie & Halfmoon | 12/04/2013 | |
Amendment | $218,197.31 |
CO # 12 - New Trans Plate - Accelerated Bridge Rehab I-87 over Mohawk River, Colonie & Halfmoon | 12/17/2013 | |
Amendment | $23,403.29 |
CO# 16- N (SB) Crossover - Accelerated Bridge Rehab of I87 over the Mohawk River, Colonie & Halfmoon | 01/07/2014 | |
Amendment | $6,543.35 |
CO#19 Scupper Downspout Accelerated Bridge Rehab of I87 Over the Mohawk River Colonie & Halfmoon | 01/17/2014 | |
Amendment | $12,732.60 |
CO#20 Armorless joints material change - Accelerated Bridge Rehab of I87 Over Mohawk River | 02/04/2014 | |
Amendment | $6,291.00 |
CO#23 Striping Accelerated Bridge Rehab of I-87 over the Mohawk River Colonie & Halfmoon | 02/11/2014 | |
Amendment | $7,595.99 |
CO#24 Traffic control Accelerated Bridge Rehab of I-87 over the Mohawk River Colonie & Halfmoon | 02/19/2014 | |
Amendment | $20,583.72 |
CO#26 Cold weather concrete Accelerated Bridge Rehab of I-87 over the Mohawk River Colonie&Halfmoon | 02/27/2014 | |
Amendment | $20,031.64 |
CO#27 Barrier transition Accelerated Bridge Rehab of I87 over the Mohawk River Colonie & Halfmoon | 03/12/2014 | |
Amendment | $1,128,579.08 |
CO#25 Add'l Weekend Phase 1 Accelerated Bridge Rehab of I87 Over Mohawk River Colonie & Halfmoon | 04/18/2014 | |
Amendment | $31,804.18 |
CO#11 Contingency Detour Signs Accelerated Bridge Rehab of I87 Over Mohawk River Colonie & Halfmoon | 05/13/2014 | |
Amendment | $30,083.19 |
CO#21 - Transition Joint Detail, Accelerated Bridge Rehab I-87 Over Mohawk River Colonie & Halfmoon | 05/23/2014 | |
Amendment | $8,840.29 |
CO#28 Approach Slab Retrofit - Accelerated Bridge Rehab I-87 Over Mohawk River Colonie & Halfmoon | 05/30/2014 | |
Amendment | $222,414.10 |
CO#36 New Transition Plate (Subcontractor Costs) - Accelerated Bridge Rehab I-87 Over Mohawk River | 06/18/2014 | |
Amendment | $729,820.81 |
CO#29 Zipper barrier Accelerated Bridge Rehab I-87 Over Mohawk River Halfmoon/Colonie | 07/10/2014 | |
Amendment | $9,822.00 |
CO#32 Bridge Rehab I-87 Over Mohawk River Halfmoon/Colonie Saratoga/Albany Co | 07/18/2014 | |
Amendment | ($23,388.79) |
CO#35 Bridge Rehab I-87 Over Mohawk River Halfmoon/Colonie Saratoga/Albany Co | 05/28/2015 | |
Amendment | $0.00 |
11/24/2014 | CO#37 NCTE Resubmittal Bridge Rehab I-87 Over Mohawk River Halfmoon/Colonie Saratoga/Albany Co | 06/01/2015 |
Amendment | ($13,874.05) |
CO#39 Bridge Rehab I-87 Over Mohawk River Halfmoon/Colonie Saratoga/Albany Co | 07/23/2015 | |
Amendment | ($965,693.14) |
CO 30 CLEAN UP Bridge ove Mohawk River, Colonie, Halfmoon Region 1 | 08/21/2015 | |
Amendment | ($2,749.86) |
CO#40 Liquidated damages Bridge Rehab I-87 Over Mohawk River Halfmoon/Colonie Saratoga/Albany Co | 09/11/2015 | |
Amendment | $0.00 |
11/24/2014 | FINAL, Accelerated Bridge Rehab of I87 over the Mohawk River, Colonie & Halfmoon | 08/01/2016 |