Vendor Name: MURNANE BUILDING CONTRACTORS
Agency Name: State University Construction Fund
Department/Facility Name: State University Construction Fund
Contract Number: D006821
Current Contract Amount: $27,279,964.00
Spending to Date: $6,392,576.00
Contract Type: Construction - Building
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $27,186,000.00 |
05/19/2023 | 09/05/2026 | Renovate C wing at Cornish Van Hoesen Hall at SUNY Cortland | 06/02/2023 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $0.00 |
09/24/2026 | Term adjustment based on notice to proceed | 06/09/2023 |
Amendment | $6,916.00 |
Change order 1 and 2 for various changes | 10/20/2023 | |
Amendment | $12,246.00 |
Change order 3 to replace mechanical room walls | 11/30/2023 | |
Amendment | ($24,978.00) |
Change order four is to delete infrastructure associated with LED displays and cinema seating | 05/17/2024 | |
Amendment | $99,780.00 |
Change orders five and six to provide additional framing and gypsum wall board and other changes | 05/31/2024 |