Vendor Name: REALE CONSTRUCTION CO INC
Agency Name: General Services, Office of
Department/Facility Name: Office of General Services - Design & Construction
Contract Number: DEE852G
Current Contract Amount: $750,000.00
Spending to Date: $624,190.18
Contract Type: Construction - Building
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $300,000.00 |
07/25/2022 | 11/22/2022 | Repair wastewater treatment plant failed filters Bldg 3 Altona CF Clinton County | 08/18/2022 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $150,000.00 |
04/30/2023 | CO#1 78177 increase & extension due to field conditions | 12/23/2022 |
Amendment | $300,000.00 |
06/30/2023 | CO #2 TE & Replace piping and pumps for filters 3 and 4 | 03/17/2023 |
Amendment | $0.00 |
11/30/2023 | CO #2 79012 No cost time extension | 08/04/2023 |
Amendment | $0.00 |
03/31/2024 | CO#3 79515 No cost time extension | 12/28/2023 |
Amendment | $0.00 |
04/16/2024 | CO#4 80207 No cost time extension | 07/18/2024 |