Vendor Name: CONCRETE APPLIED TECHNOLOGIES CORP
Agency Name: State University Construction Fund
Department/Facility Name: State University Construction Fund
Contract Number: D006744
Current Contract Amount: $26,985,399.00
Spending to Date: $23,120,751.00
Contract Type: Construction - Miscellaneous
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $25,789,000.00 |
05/24/2022 | 12/29/2025 | Campus-wide loop road and utility improvements at SUNY College of Technology at Alfred, Allegany Co | 06/03/2022 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $0.00 |
01/13/2026 | Term correction | 06/09/2022 |
Amendment | $134,568.00 |
Change order one is to relocate some of the existing water line | 11/02/2023 | |
Amendment | $95,559.00 |
Change order number two for improved drainage | 11/20/2023 | |
Amendment | $24,336.00 |
Change order number three for additional retaining wall | 05/30/2024 | |
Amendment | $15,708.00 |
Change order four to provide precast concrete gravity wall | 06/07/2024 | |
Amendment | $178,453.00 |
Change orders five, six, seven and eight for utilities work | 07/18/2024 | |
Amendment | $40,929.00 |
Change orders nine and ten for various changes | 08/09/2024 | |
Amendment | $67,903.00 |
Change order 11 for water line connection fittings and piping to existing bypass | 08/22/2024 | |
Amendment | $12,827.00 |
Change order 12 is to install drains at electric and communications vaults and daylight pipes | 09/06/2024 | |
Amendment | $88,732.00 |
Change orders 13 and 14 are for various changes | 09/23/2024 | |
Amendment | $429,359.00 |
Change order 15 for water routing modifications | 10/10/2024 | |
Amendment | $108,025.00 |
Change order 16 to reroute sidewalk and tree removal | 10/24/2024 |