Vendor Name: MANNING SQUIRES HENNIG CO INC
Agency Name: State University Construction Fund
Department/Facility Name: State University Construction Fund
Contract Number: D006740
Current Contract Amount: $42,065,355.00
Spending to Date: $22,685,566.00
Contract Type: Construction - Building
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $41,111,000.00 |
05/17/2022 | 02/15/2026 | Renovation of Foster Hall at SUNY Buffalo | 06/03/2022 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $0.00 |
03/08/2026 | Term correction | 06/08/2022 |
Amendment | $74,339.00 |
Change order for demo and disposal of lab furniture and casework at SUNY Buffalo | 11/01/2022 | |
Amendment | $63,420.00 |
Change orders# 2-3 revision to the clock outlets and repair pedestrian tunnel | 03/03/2023 | |
Amendment | $0.00 |
03/16/2026 | Change order #4 to extend the contract term | 03/20/2023 |
Amendment | $213,991.00 |
Change order #5 is to provide new structural steel and masonry repairs | 04/28/2023 | |
Amendment | $79,367.00 |
Change order #6 is to provide structural repairs at attic | 05/23/2023 | |
Amendment | $406,993.00 |
Change orders #7 and #8 install new structural steel support basement windows and insulation | 06/01/2023 | |
Amendment | $82,313.00 |
Change order #9 provide structural repairs at attic | 06/02/2023 | |
Amendment | $6,319.00 |
Change order 10 is for 6 added data drops to wireless access points and revisions to hose bibs | 06/30/2023 | |
Amendment | $247,464.00 |
Change order 11 is for demolition of terrazzo flooring at floors 1-3 | 07/26/2023 | |
Amendment | $86,971.00 |
Change order 12 to abate the existing pipe insulation | 08/10/2023 | |
Amendment | $17,126.00 |
Change order 13 provide structural repairs at attic | 09/05/2023 | |
Amendment | ($47,491.00) |
Change order 15 for feeder deletion | 10/05/2023 | |
Amendment | $173,875.00 |
Change order 14 is for additional asbestos abatement | 10/20/2023 | |
Amendment | $57,509.00 |
Change order 16 for additional asbestos abatement in subbasement | 12/05/2023 | |
Amendment | ($7,841.00) |
Change order 17 to delete the stainless steel drip flashing at the header of the windows | 12/29/2023 | |
Amendment | ($500,000.00) |
Reduce the contract field order allowance from $1,711,000 to $1,211,000 | 02/13/2024 |