Vendor Name: MANNING SQUIRES HENNIG CO INC
Agency Name: State University Construction Fund
Department/Facility Name: State University Construction Fund
Contract Number: D006724
Current Contract Amount: $18,144,943.00
Spending to Date: $16,565,839.00
Contract Type: Construction - Building
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $17,671,000.00 |
03/25/2022 | 10/02/2024 | Renovation of Classroom Building at Buffalo State College | 03/30/2022 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $0.00 |
10/09/2024 | Term correction | 04/05/2022 |
Amendment | $122,584.00 |
Change order #1 is for additional plaster demolition | 12/07/2022 | |
Amendment | $0.00 |
10/17/2024 | Change order #2 for an eight day no cost term extension | 02/27/2023 |
Amendment | $290,554.00 |
Change order #3 is to abate asbestos containing spray-on fireproofing | 03/13/2023 | |
Amendment | ($300,000.00) |
Change order #4 is a deductive to reduce the contract field order allowance | 05/11/2023 | |
Amendment | $243,999.00 |
Additional abatement and disposal - change orders #5 and #6 | 05/25/2023 | |
Amendment | ($1,716.00) |
Change order 7 for credit of quarry tile | 08/04/2023 | |
Amendment | ($32,182.00) |
Reduction in the size of the A wing | 08/10/2023 | |
Amendment | ($27,959.00) |
Change order 9 is a credit to eliminate perimeter roof coping | 08/24/2023 | |
Amendment | ($221,000.00) |
Change order 10 is to reduce the field order allowance | 10/13/2023 | |
Amendment | $272,632.00 |
Change orders 11 and 12 are to repair existing slab edge and concrete masonry wall | 11/09/2023 | |
Amendment | $127,031.00 |
Change order 13 is for additional abatement | 01/24/2024 |