Vendor Name: BEN CICCONE INC
Agency Name: Transportation, Department of
Department/Facility Name: Department of Transportation
Contract Number: D264593
Current Contract Amount: $13,160,020.65
Spending to Date: $12,680,289.17
Contract Type: Construction - Highway
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $8,482,616.20 |
02/14/2022 | 11/23/2022 | Ramp reconstruction I-287 Eastbound to Saw Mill River Parkway Northbound Weschester County | 02/14/2022 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $325,201.20 |
CO#4 Excess material excavation and offsite disposal | 09/08/2022 | |
Amendment | $0.00 |
06/23/2023 | CO #6 No cost time extension | 12/06/2022 |
Amendment | $1,640,200.00 |
CO#10 Micropile installation | 05/31/2023 | |
Amendment | $328,745.23 |
CO#9 Item increases | 06/22/2023 | |
Amendment | $0.00 |
12/02/2023 | CO#12 No cost time extension | 07/06/2023 |
Amendment | $482,800.95 |
CO#11 New items | 09/13/2023 | |
Amendment | $484,533.75 |
CO#13 3 new item increases for shoring & prep for east wall redesign & additional drainage | 10/19/2023 | |
Amendment | $256,262.85 |
CO #14 Item increases for concrete structure & footing | 12/07/2023 | |
Amendment | $0.00 |
01/31/2024 | CO# 16 No cost time extension | 12/20/2023 |
Amendment | $0.00 |
05/31/2024 | CO #18 No cost time extension | 03/22/2024 |