Vendor Name: ALL-CON CONTRACTING CORP
Agency Name: State University of New York
Department/Facility Name: College of Technology at Farmingdale
Contract Number: D010062
Current Contract Amount: $7,945,133.00
Spending to Date: $7,071,363.70
Contract Type: Construction - Building
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $7,555,000.00 |
12/01/2021 | 03/30/2024 | Rehabilitation of Knapp Hall (First Floor) at SUNY Farmingdale | 11/22/2021 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $159,618.00 |
04/29/2024 | Change Orders #1-4 & 7 for plumbing repairs and other various modifications | 08/19/2022 |
Amendment | $80,780.00 |
Change order #5,6,8,9,10 - various changes | 09/02/2022 | |
Amendment | $11,959.00 |
Change order #11 is to clean, prime and paint the wood in the University Club | 11/21/2022 | |
Amendment | $23,850.00 |
Change orders 13, 14, 17,19, 20, 21 are for various changes | 05/22/2023 | |
Amendment | $0.00 |
07/31/2024 | Change order #22 is a three month time extension | 06/20/2023 |
Amendment | $7,795.00 |
Change order 23 for additional work | 06/29/2023 | |
Amendment | $7,464.00 |
Change orders 15, 25, 26 and 27 for various changes | 08/03/2023 | |
Amendment | $37,882.00 |
Change orders 24, 29, 30, 31 and 32 for various changes | 09/13/2023 | |
Amendment | $28,639.00 |
Change orders 18 and 28 for various changes | 10/10/2023 | |
Amendment | $6,250.00 |
Change order 33 cup, cap and relocate four pipes in the south wing | 11/10/2023 | |
Amendment | $25,896.00 |
Change orders 38,40,41,42,44,45 and 46 for various additional work | 04/17/2024 |