Vendor Name: GRYPHON CONSTRUCTION INC
Agency Name: State University Construction Fund
Department/Facility Name: State University Construction Fund
Contract Number: D006658
Current Contract Amount: $10,200,461.00
Spending to Date: $10,054,312.00
Contract Type: Construction - Miscellaneous
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $9,652,179.00 |
07/07/2021 | 11/29/2023 | Renovate Vander Clute Hall for student union at SUNY Maritime College | 07/20/2021 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $0.00 |
12/26/2023 | Update contract term | 08/05/2021 |
Amendment | $5,010.00 |
Change order #3 provide different lighting fixtures | 06/02/2022 | |
Amendment | $3,084.00 |
Change order #4 provide drywall ceiling cover to accommodate light fixtures | 07/08/2022 | |
Amendment | $114,337.00 |
Change order #1 #2 & #5 temporary power for transformer replacement | 07/12/2022 | |
Amendment | $41,460.00 |
Change order #6 is to provide floor repairs and carpet, and re-route electrical conduit | 01/19/2023 | |
Amendment | $57,689.00 |
Change orders 7 and 8 are for various changes | 03/07/2023 | |
Amendment | $3,159.00 |
Change order #9 is to add a toggle switch and smoke detector | 03/13/2023 | |
Amendment | $28,133.00 |
Change order #10 is to provide condensate pumps and modify existing chase at door | 04/05/2023 | |
Amendment | $79,907.00 |
Change orders 11 and 12 are for plumbing modifications and relocate water piping | 04/14/2023 | |
Amendment | $12,856.00 |
Change order #13 for double check sprinkler valve installation and piping reconfiguration | 04/27/2023 | |
Amendment | $11,821.00 |
Change order #14 for removal of cabinet heater | 05/16/2023 | |
Amendment | $7,705.00 |
Change order #15 for unit heater work | 05/19/2023 | |
Amendment | $71,474.00 |
Change order 16 for various changes | 07/11/2023 | |
Amendment | $5,545.00 |
Change order 17 to change function of two storage rooms to conference room and office | 07/20/2023 | |
Amendment | $78,092.00 |
Change order 18 and 19 are for various changes | 08/18/2023 | |
Amendment | $29,914.00 |
Change order 20 for exhaust duct pathway modification | 09/18/2023 | |
Amendment | ($1,904.00) |
Change order 21 and 22 is for various changes | 12/28/2023 |