Vendor Name: MURNANE BUILDING CONTRACTORS
Agency Name: State University of New York
Department/Facility Name: SUNY - Upstate Medical University
Contract Number: D550311
Current Contract Amount: $2,809,821.51
Spending to Date: $2,809,821.51
Contract Type: Construction - Building
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $2,070,000.00 |
06/25/2021 | 12/22/2021 | University Hospital south wing façade and brick repair | 06/25/2021 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $0.00 |
01/21/2022 | Change order #1 for additional sheathing replacement and expansion joint installation | 04/05/2022 |
Amendment | $44,920.00 |
STS correction for previously approved change order #1 | 04/08/2022 | |
Amendment | $642,949.51 |
06/01/2022 | Change order #2 for window replacement and hazardous waste abatement | 04/26/2022 |
Amendment | $46,585.00 |
08/15/2022 | Change order #3- 75 day extension and increase in material cost | 07/26/2022 |
Amendment | $5,367.00 |
Change order #4 is for additional bond costs | 04/28/2023 |