Vendor Name: STREETER ASSOCIATES INC
Agency Name: General Services, Office of
Department/Facility Name: Office of General Services - Design & Construction
Contract Number: D45964H
Current Contract Amount: $2,537,586.00
Spending to Date: $2,537,585.00
Contract Type: Construction - Building
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $2,497,500.00 |
05/14/2021 | 11/11/2022 | Replace fuel oil tanks & modify boiler controls Elmira CF Chemung County | 05/14/2021 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | ($120,867.00) |
CO#1 76366 Credit for temporary fuel tanks | 10/06/2021 | |
Amendment | $0.00 |
11/24/2022 | CO#2 77534 No cost time extension | 08/22/2022 |
Amendment | $0.00 |
12/31/2022 | CO 3 77586 No cost time extension | 08/23/2022 |
Amendment | $47,743.00 |
CO#4 77496 Add 4 isolation valves | 09/22/2022 | |
Amendment | $0.00 |
11/16/2023 | CO#5 77832 No cost time extension | 10/03/2022 |
Amendment | $14,677.00 |
CO 6 78097 Drain fuel lines and add insulation valves | 12/09/2022 | |
Amendment | $6,120.00 |
CO#7 78589 Delay claim | 06/20/2023 | |
Amendment | $92,413.00 |
CO#8 77832A Delay claim for May 14 2021 to October 13 2023 | 02/20/2024 |