Vendor Name: TIOGA CONSTRUCTION COMPANY INC
Agency Name: Transportation, Department of
Department/Facility Name: Department of Transportation
Contract Number: D264291
Current Contract Amount: $18,176,507.91
Spending to Date: $18,176,507.91
Contract Type: Construction - Highway
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $16,498,071.40 |
10/22/2020 | 02/02/2022 | Bridge replacement project Rte 34B over Salmon Creek Town of Lansing Tompkins County | 10/22/2020 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $23,982.15 |
Change order #4 new utilities and bridge structure items | 06/24/2021 | |
Amendment | $30,237.20 |
CO#5 Item increases decreases and new items. | 07/19/2021 | |
Amendment | $983,871.66 |
CO # 6 Additional steel and pins | 09/17/2021 | |
Amendment | $0.00 |
07/31/2022 | CO#9 No cost time extension | 11/26/2021 |
Amendment | $7,423.44 |
CO #12 Additional rebar and shear studs | 03/03/2022 | |
Amendment | $893,647.76 |
CO#13 Addition of new items for steel erection | 05/25/2022 | |
Amendment | $996.45 |
CO #17 Superstructure reinforcement | 09/06/2022 | |
Amendment | $166,819.07 |
CO#19 Cost escalations due to project delay | 10/12/2022 | |
Amendment | ($428,541.22) |
CO#18 Item decreases. | 11/01/2023 |