Vendor Name: STREETER ASSOCIATES INC
Agency Name: General Services, Office of
Department/Facility Name: Office of General Services - Design & Construction
Contract Number: D46130C
Current Contract Amount: $2,773,626.00
Spending to Date: $2,369,269.20
Contract Type: Construction - Building
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $2,383,000.00 |
04/27/2020 | 10/26/2021 | Provide Classrooms & Office Space Bldg 38 Residential Rehab Unit Cayuga CF Cayuga County | 04/27/2020 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | ($1,400.00) |
Change order #1 75413 materials/method substitution temporary door frame and hardware | 01/08/2021 | |
Amendment | ($2,800.00) |
CO#2 75483 Materials Methods Substitution | 01/15/2021 | |
Amendment | ($19,618.00) |
CO#3 75574 relocate field office near the QWL bldg | 04/23/2021 | |
Amendment | $0.00 |
04/04/2022 | Change order #5 control #75892 no cost time extension | 06/11/2021 |
Amendment | ($1,020.00) |
CO#4 75944 Change key cylinders to meet facility requirements for keying | 06/23/2021 | |
Amendment | ($936.00) |
CO# 6 76237 Credit for paint not required | 09/03/2021 | |
Amendment | $7,000.00 |
03/21/2022 | CO# 7 76431 Acceleration of project work to decrease time by 14 days & premium time differential | 11/10/2021 |
Amendment | ($10,670.00) |
CO#9 76796 Credit for scope reduction | 01/19/2022 | |
Amendment | ($21,803.00) |
CO#8 76754 Credit for existing substrate & self leveling material not compatible with floor system | 02/15/2022 | |
Amendment | $0.00 |
05/19/2022 | Change order #10 no cost time extension | 03/28/2022 |
Amendment | $0.00 |
08/31/2022 | CO#11 77546 No cost time extension | 07/22/2022 |
Amendment | $22,386.00 |
01/23/2023 | CO#13 77943 classroom window security glazing & time extension | 01/13/2023 |
Amendment | $0.00 |
03/31/2023 | CO#14 78316 No Cost time extension | 03/27/2023 |
Amendment | $26,528.00 |
CO#15 78837 Delay Claim | 07/13/2023 | |
Amendment | $0.00 |
12/15/2023 | CO #16 79223 No cost time extension | 10/03/2023 |
Amendment | $392,959.00 |
06/01/2024 | CO#17 79040 Steel doors & time extension | 02/08/2024 |