Vendor Name: CONDOR FIRE SPRINKLER LLC
Agency Name: General Services, Office of
Department/Facility Name: Office of General Services - Design & Construction
Contract Number: D45147C
Current Contract Amount: $1,554,213.00
Spending to Date: $1,547,742.00
Contract Type: Construction - Building
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $1,332,300.00 |
02/21/2020 | 11/20/2020 | Provide Water Storage & Fire Suppression Upgrades Dutchess County | 02/21/2020 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $28,415.00 |
CO#2 74978 additional conduit installation and excavation | 10/14/2020 | |
Amendment | $6,052.00 |
CO#1 74977 Modify building height | 10/28/2020 | |
Amendment | $97,544.00 |
CO#3 75025 Groundwater & constructability concerns | 11/12/2020 | |
Amendment | $0.00 |
02/16/2021 | Change order #4 75390 no cost time extension | 12/16/2020 |
Amendment | $0.00 |
06/14/2021 | Change order #5 75025A no cost time extension | 01/04/2021 |
Amendment | $20,000.00 |
Change order #6 75399 cold weather concrete & excavation | 01/20/2021 | |
Amendment | ($4.00) |
CO #7 75399A credit for cold weather concrete & excavation | 06/09/2021 | |
Amendment | $0.00 |
08/28/2021 | CO#11 76218 no cost time extension | 08/26/2021 |
Amendment | $62,790.00 |
Change order #8 75025B additional equipment costs | 09/15/2021 | |
Amendment | $7,116.00 |
Change order #10 76258 delay claim & release | 09/20/2021 |