Vendor Name: OLYMPIC ELECTRIC OF THE HUDSON VALLEY LLC
Agency Name: General Services, Office of
Department/Facility Name: Office of General Services - Design & Construction
Contract Number: D44797E
Current Contract Amount: $352,024.00
Spending to Date: $345,354.00
Contract Type: Construction - Building
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $313,900.00 |
05/16/2018 | 08/12/2021 | Shower Rehabilitation Cell Blocks A & B Sullivan CF Fallsburg Sullivan County (E) | 05/16/2018 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $5,470.00 |
CO #1 73113 - Conduit and wire repair. | 02/06/2019 | |
Amendment | $3,428.00 |
CO#2 Repair existing conduit and wire impacted during drilling | 09/13/2019 | |
Amendment | $2,413.00 |
CO#3 74381 - Repair lighting circuits. | 02/18/2020 | |
Amendment | $5,000.00 |
Change Order #4 74738 Stop work order due to COVID 19 demobilization costs | 05/29/2020 | |
Amendment | $0.00 |
12/02/2021 | CO #5 75334 no cost time extension | 12/08/2020 |
Amendment | $0.00 |
05/14/2022 | CO#6 76191 No cost time extension | 09/14/2021 |
Amendment | $10,000.00 |
CO#7 76417 Increase funds labor & materials | 10/14/2021 | |
Amendment | ($3,571.00) |
CO#8 76417A reconcillation of CO#7 | 11/17/2021 | |
Amendment | $18,977.00 |
CO# 10 Increase funds for temporary & permanent circuit repairs | 11/26/2021 | |
Amendment | ($3,593.00) |
Change order #9 74738A amend cost for CO#4 | 12/17/2021 | |
Amendment | $0.00 |
09/15/2022 | CO 11 77380 No cost time extension | 07/22/2022 |