Vendor Name: BOTHAR CONSTRUCTION LLC
Agency Name: Transportation, Department of
Department/Facility Name: Department of Transportation
Contract Number: D263590
Current Contract Amount: $6,046,568.02
Spending to Date: $6,046,568.02
Contract Type: Construction - Highway
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $5,793,682.54 |
05/09/2018 | 12/01/2019 | Replace 7 Culverts Broome Chenango Delaware Sullivan Counties | 05/09/2018 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $24,860.00 |
CO#1 Addtional 19mm Binder Course Asphalt | 03/14/2019 | |
Amendment | $7,901.48 |
CO#2 Site A Emergency Work to Repair Hole Over Culvert | 03/26/2019 | |
Amendment | $4,928.43 |
CO#6 New Item for Site C Utility Pole Relocation | 04/29/2019 | |
Amendment | $44,982.00 |
CO#5 Tree Removal | 05/16/2019 | |
Amendment | $2,976.48 |
CO#7 Temp rumble strips | 12/11/2019 | |
Amendment | $0.00 |
11/01/2020 | CO#9 NCTE | 02/04/2020 |
Amendment | $81,607.20 |
CO#10 New Item for Rock Sockets for Soldier Piles & Lagging Wall | 03/04/2020 | |
Amendment | $0.00 |
11/20/2020 | CO#14 no cost time extension | 10/29/2020 |
Amendment | $36,454.58 |
CO#13 Site E Accelerated Work | 11/20/2020 | |
Amendment | $445,440.55 |
Change order #17 new trench and culvert items | 03/12/2021 | |
Amendment | $87,036.60 |
CO #19 additional stream work | 06/14/2021 | |
Amendment | $70,337.42 |
Change order #12 new emergency repair | 06/29/2021 | |
Amendment | $185,325.01 |
CO#18 New items steel sheeting & guide rail | 07/19/2021 | |
Amendment | ($755,740.27) |
CO #20 decrease items | 02/18/2022 | |
Amendment | $16,776.00 |
CO#21 Item increases | 03/21/2022 |