Vendor Name: POWER LINE CONSTRUCTORS INC
Agency Name: Transportation, Department of
Department/Facility Name: Department of Transportation
Contract Number: D263557
Current Contract Amount: $1,543,619.44
Spending to Date: $1,543,619.44
Contract Type: Construction - Highway
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $1,311,825.40 |
10/10/2017 | 12/31/2018 | Traffic Improvements at 6 Sites at Various Locations Madison & Oneida Counties | 10/10/2017 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $40,158.35 |
CO#3 New FAW Traffic Signal Items | 12/12/2018 | |
Amendment | $6,726.65 |
CO#5 New/Inc/Decrease Items | 01/02/2019 | |
Amendment | $0.00 |
05/31/2019 | CO#7 NCTE | 01/11/2019 |
Amendment | $22,115.46 |
CO# 9 Item Increases | 02/08/2019 | |
Amendment | $4,112.82 |
CO#10 Connect New Controller Relocate Opticom Cable Change TLO Sign Patch Potholes | 04/05/2019 | |
Amendment | $24,749.96 |
CO# 11 Item increases for Field Office & Other Items & New Item Light Meter Cabinet | 04/19/2019 | |
Amendment | $0.00 |
06/30/2019 | CO#12 NCTE | 06/12/2019 |
Amendment | ($3,283.82) |
CO#13 Item increases and decreases. | 07/10/2019 | |
Amendment | $90,922.88 |
CO#15 Additional Survey Work Replace Guide Railings Install Delineators Raise Drainage Structure | 08/06/2019 | |
Amendment | $8,930.54 |
CO#14 Traffic Systems Improvement Project 15 | 08/20/2019 | |
Amendment | $37,361.20 |
CO#16 Item increases and decreases | 11/01/2019 |