Vendor Name: COLD SPRING CONSTRUCTION CO
Agency Name: Transportation, Department of
Department/Facility Name: Department of Transportation
Contract Number: D263387
Current Contract Amount: $51,949,094.34
Spending to Date: $51,949,094.34
Contract Type: Construction - Building
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $50,592,146.53 |
06/08/2017 | 12/31/2019 | Interchange Improvement on I-390, I-490 & Lyell Avenue Monroe County | 06/08/2017 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $408,215.00 |
CO#1 New/Inc Item Interchange Imprvmnt. on 390 & 490, Lyell Ave. Monroe County | 10/26/2017 | |
Amendment | $25,709.22 |
CO#3 New Items Interchange Improvement on I-390, I-490 & Lyell Avenue Monroe County | 11/09/2017 | |
Amendment | $24,060.00 |
CO#4 New/Decrease Items, Interchange Improvement I-390 & I-490 & Lyell Avenue, Monroe County | 11/20/2017 | |
Amendment | $25,905.60 |
CO#9 Bearings Interchange Improvement on I-390 I-490 & Lyell Avenue Monroe County | 01/11/2018 | |
Amendment | ($80.85) |
CO#12 Interchange Improvement on I-390 I-490 & Lyell Avenue Monroe County | 04/13/2018 | |
Amendment | $826.39 |
CO#15 New Items, Full depth welded end replacement & end diaphragm replacement | 06/01/2018 | |
Amendment | $0.05 |
CO#19 New Item 950.11 & Decrease 211 | 06/15/2018 | |
Amendment | ($13,680.82) |
CO#16, Item incr/decr. | 06/25/2018 | |
Amendment | $112,297.26 |
CO#21 New Items for Contaminated Soil | 07/10/2018 | |
Amendment | ($4,534.16) |
CO#20 Reneg Item & New Items | 07/27/2018 | |
Amendment | $31,906.89 |
CO# 23 Additional Work to All Locations to Install Underdrains | 08/23/2018 | |
Amendment | $45,290.86 |
CO 22, New Item. | 09/14/2018 | |
Amendment | ($1,291,224.34) |
CO#18 New/Inc/Decrease Items | 10/01/2018 | |
Amendment | $1,128,557.76 |
CO# 25 New Items & Item Increases | 01/15/2019 | |
Amendment | $99,079.50 |
CO#26 New & Increased Items For Traffic Signal System @ Lee Rd/Lyell Ave Intersection | 02/25/2019 | |
Amendment | $1,755,351.30 |
CO#27 New Items | 03/28/2019 | |
Amendment | ($208,965.71) |
CO#28 New Items Routes 390 & 490 Phase 2 Improvements | 05/14/2019 | |
Amendment | $207,543.95 |
CO#29 Items Overrun & Underrun Removed Incentive/Disincentive Item | 06/10/2019 | |
Amendment | $10,001.75 |
CO#30 Item increases and decreases | 10/09/2019 | |
Amendment | $98,985.92 |
CO#31 New Increased & Decreased Bridge Repair Items | 02/24/2020 | |
Amendment | $0.00 |
06/19/2020 | CO#32 NCTE | 03/16/2020 |
Amendment | $193,678.31 |
CO#33 New Increased & Decreased Items Interchange Improvements | 04/09/2020 | |
Amendment | $118,510.10 |
CO#34 Claim Settlement & New Items | 06/08/2020 | |
Amendment | $592.29 |
CO#36 New items beam end repairs fiberglass conduit & guiderail repairs | 02/03/2022 | |
Amendment | ($1,411,078.46) |
CO#35 Cleanup | 06/08/2022 |