Vendor Name: LANCASTER DEVELOPMENT & TULLY CONSTRUCTION CO LLC
Agency Name: Transportation, Department of
Department/Facility Name: Department of Transportation
Contract Number: D262955
Current Contract Amount: $146,152,438.65
Spending to Date: $146,152,438.65
Contract Type: Construction - Highway
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $152,036,459.98 |
05/12/2016 | 12/31/2020 | I-81 & NY 17 Interchange Reconstruction, Broome Co, Region 9 | 05/12/2016 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | ($835.00) |
12/31/2020 | CO 2 Slide Rail System VECP Region 9 | 08/17/2016 |
Amendment | $280,449.91 |
12/31/2020 | CO 1 1 81/NY 17 Interchange Reconst Phase 2. new items, increase in items Region 9 | 09/28/2016 |
Amendment | $125,650.80 |
12/31/2020 | CO# 003, FAW, I-81 & NY 17 Interchange Reconstruction, Broome Co, Region 9 | 11/08/2016 |
Amendment | $57,836.11 |
12/31/2020 | CO 5 Interchange reconst Phase 11 1 81/NY17 | 12/22/2016 |
Amendment | $387,151.02 |
12/31/2020 | CO#6 FA Est Scale Facility work @ NSRC - NY 17 & I-81 Interchange Reconstruction Broome County | 01/10/2017 |
Amendment | $604,398.42 |
12/31/2020 | CO 7 Interchange reconst Phase 11 additional work/ increase in items Region 9 | 03/29/2017 |
Amendment | $406,876.11 |
12/31/2020 | CO#8 Under Bridge Lighting/Widening Shoulder NY 17 & I-81 Interchange Reconstruction Broome County | 05/23/2017 |
Amendment | $256,781.76 |
12/31/2020 | CO#10 VECP Add'l Approach at Pier New Items I-81 & NY 17 Interchange Reconstruction Broome County | 07/28/2017 |
Amendment | $297,758.72 |
CO#13 I-81 & NY 17 Interchange Reconstruction Broome County | 09/08/2017 | |
Amendment | ($20,678.13) |
CO 11 1 81/NY 17 Interchange Reconst Phase 11 VECP Design Region 9 | 09/15/2017 | |
Amendment | $219,573.98 |
CO 15 I 81/NY 17 Interchange reconstruction Phase 11 Region 9 | 11/24/2017 | |
Amendment | $155,446.75 |
CO#19-Add VECP Item-I-81 & NY 17 Interchange Reconstruction, Broome County, Region 9 | 02/15/2018 | |
Amendment | ($253.49) |
CO#21 Inc/Decrease Items, I-81 & NY 17 Interchange Reconstruction, Broome County Region 9 | 03/05/2018 | |
Amendment | $208,022.95 |
CO#18-Decs/New-I-81&NY17 Interch Recon Ph2(Concr Pave Br Repl ITS Meas Noise/Ret Wall)BroomeCounty | 05/04/2018 | |
Amendment | $485,703.75 |
CO#22 New Items Additional Work | 09/27/2018 | |
Amendment | $719,027.58 |
CO#24 NY 17 Interchange Reconstruction Broome County Region 9 | 01/07/2019 | |
Amendment | $116,528.13 |
CO#26 New Items NY 17 Interchange Reconstruction Broome County Region 9 | 03/12/2019 | |
Amendment | ($47,824.58) |
CO#28 Add New Items & Item Increases & Decreases | 07/08/2019 | |
Amendment | $208,351.12 |
CO#31 New Items Drainage Lighting Traffic Control | 08/06/2019 | |
Amendment | ($99,900.69) |
CO#33 New Items Interchange Reconstruction | 09/20/2019 | |
Amendment | $317,209.07 |
CO#35 New Increased & Decreased Items Interchange Reconstruction | 10/30/2019 | |
Amendment | $86,671.35 |
CO#38 New Increased & Decreased Items | 02/24/2020 | |
Amendment | $24,314.66 |
CO#40 - New items. | 03/10/2020 | |
Amendment | ($9,985,716.52) |
CO#41 Clean up CO | 05/18/2020 | |
Amendment | ($686,565.11) |
CO#44 Clean up Change Order | 11/30/2020 |