Vendor Name: S & O CONSTRUCTION SERVICES INC
Agency Name: General Services, Office of
Department/Facility Name: Office of General Services - Design & Construction
Contract Number: D42646H
Current Contract Amount: $2,809,131.00
Spending to Date: $2,798,767.00
Contract Type: Construction - Building
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $2,144,857.00 |
12/07/2015 | 11/06/2018 | Rehabilitation Kitchen & Mess Hall, HVAC, Building 21, Fishkill CF, Dutchess County | 12/08/2015 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | ($36,455.00) |
11/06/2018 | CO#2, ctrl 70316 Rehabilitation Kitchen & Mess Hall, HVAC, Building 21, Fishkill CF, Dutchess Count | 09/30/2016 |
Amendment | $313,089.00 |
11/06/2018 | Rehabilitate Kitchen/ mess hall Bldg 21 Fishkill CF | 03/21/2017 |
Amendment | $0.00 |
01/15/2019 | CO 4 71164 No cost time extension 70 days Rehab kitchen mess hall Bldg 21 Fishkill CF | 04/18/2017 |
Amendment | $4,692.00 |
CO 5 Rehabilitate Kitchen and Mess Hall, Bldg 21 Fishkill CF | 12/07/2017 | |
Amendment | $0.00 |
06/03/2019 | CO#6 71742 Time extension Rehabilitate Kitchen/Mess Hall Bldg 21 Fishkill CF | 12/28/2017 |
Amendment | $17,472.00 |
CO#7 72053 Rehabilitate Kitchen and-Kitchen/Mess Hall Bldg 21 Fishkill CF | 02/07/2018 | |
Amendment | $10,574.00 |
CO#8 72425 cut n cap addl radiators mezzanine fl area | 06/05/2018 | |
Amendment | $0.00 |
01/21/2020 | CO #10 73173 NCTE | 01/24/2019 |
Amendment | $309,968.00 |
CO#9 72497 Steam & Heating Pipe Work | 03/06/2019 | |
Amendment | $24,531.00 |
CO# 11 73908 Provide control wiring, clean steam generator bypass | 10/22/2019 | |
Amendment | $0.00 |
07/02/2020 | CO#12 74248 NCTE | 02/27/2020 |
Amendment | $0.00 |
07/19/2021 | Change order #13 75618 no cost time extension | 03/19/2021 |
Amendment | $0.00 |
01/12/2022 | Change order #14 75258 no cost time extension | 04/21/2021 |
Amendment | $20,403.00 |
CO #15 76394 increase for fittings piping & hangers | 10/15/2021 | |
Amendment | $0.00 |
03/10/2022 | CO#16 76798 no cost time extension | 01/28/2022 |
Amendment | $0.00 |
10/14/2022 | CO#17 77672 No cost time extension | 10/03/2022 |