Vendor Name: D A COLLINS CONSTRUCTION CO INC
Agency Name: Transportation, Department of
Department/Facility Name: Department of Transportation
Contract Number: D263014
Current Contract Amount: $21,312,536.61
Spending to Date: $21,312,536.61
Contract Type: Construction - Highway
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $22,385,329.91 |
01/12/2016 | 11/30/2018 | Rehab South Mall Arterial Bridges, I-787 to Empire State Plaza & Over Eagle St, Albany County | 01/12/2016 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $73,157.42 |
11/30/2018 | CO#1 TrngReq Rehab South Mall Arterial Bridges I-787 to Empire State Plaza & Over Eagle St Albany Co | 06/09/2016 |
Amendment | $2,085.30 |
11/30/2018 | CO# 5 FA Stage 1 Traffic Pattern Chg Rehab S Mall Arterial Brid's I-787 to Emp State Plz Albany Co. | 04/13/2017 |
Amendment | $1,524.74 |
11/30/2018 | CO #6, New item, rehab S. Mall arterial bridges, I-787 to E. State Plaza & over Eagle St, Alb County | 04/25/2017 |
Amendment | $3,690.04 |
11/30/2018 | CO 7 Built to Lead Signs Rehab of the 1 787 bridges to Empire State Plaza Region 1 | 05/25/2017 |
Amendment | $593.41 |
11/30/2018 | CO#9 New Item Rehab South Mall Arterial Bdgs I-787 to Empire St Plaza&Eagle St | 07/07/2017 |
Amendment | ($4,751.90) |
11/30/2018 | CO#11 Relocate Impact Attenuator Rehab South Mall Arterial Bridges I-787 to Empire St Plaza | 08/01/2017 |
Amendment | $157,117.67 |
CO#15 Painting Piers 16 & 17 Rehab South Mall Arterial Bridges I-787 Albany County | 11/07/2017 | |
Amendment | $265,000.00 |
CO#14 Rehab South Mall Arterial Bridges, I-787 to Empire State Plaza & Over Eagle St, Albany County | 03/12/2018 | |
Amendment | ($16,755.89) |
CO#10 New/Inc/Dec Items, Rehab South Mall Arterial Bridges, Emp. St. Plaza/Eagle St., Albany County | 04/13/2018 | |
Amendment | ($2,694.58) |
CO#21 Eagle Street Lighting | 05/09/2018 | |
Amendment | ($33,456.56) |
CO#27 Decrease Item Rehab South Mall Arterial Bridges I-787 to ESP & Eagle St. Albany County | 08/13/2018 | |
Amendment | $119,049.93 |
CO#24 New Concrete Item | 08/22/2018 | |
Amendment | $20,586.84 |
CO# 25 Preformed Thermoplastic Pavement Symbols Item 687.01970025 Design Issue | 08/30/2018 | |
Amendment | ($53.88) |
CO#28 Renegotiated Price for Major Item 582.06 | 09/11/2018 | |
Amendment | $18,845.60 |
CO#31 CCTV Investigation Rehab of I-787 Bridges to Empire State Plaza | 11/27/2018 | |
Amendment | $13,070.71 |
CO 2 New items | 12/20/2018 | |
Amendment | ($7,767.31) |
CO#35 FAW Median Drainage & Swale | 03/21/2019 | |
Amendment | ($294.72) |
CO#36 New Items Bridge Rehab 787 to Empire State Plaza | 04/09/2019 | |
Amendment | ($312.85) |
CO#37 Pier 6 & 8 Grider Web Repairs Cold Joint Abutment Repair Barriers | 04/26/2019 | |
Amendment | ($7,956.45) |
CO#38 Additional Steel Repair New Stiffeners Patch Repairs | 07/09/2019 | |
Amendment | ($32,823.81) |
CO#40 WZTC & Premium Time Additional Payment | 10/03/2019 | |
Amendment | ($1,640,647.01) |
CO#41 Cleanup | 11/14/2019 |