Department/Facility | Contract Number | Current Contract Amount | Spending to Date | Contract Start Date | Contract End Date | Contract Description | Contract Type | Original Contract Approved/Filed Date |
---|---|---|---|---|---|---|---|---|
Office of General Services - Design & Construction | DEE544H |
$470,000.00
|
$470,000.00 |
03/09/2021 | 03/02/2022 | Repair failed heat exchanger Bldg 1 Capital District Psychiatric Center Albany County | Construction - Building | 04/15/2021 |
Office of General Services - Design & Construction | D44075P |
$146,900.00
|
$141,769.00 |
05/01/2012 | 05/17/2014 | REHAB MECHANICAL ROOMS VARIOUS BLDGS GREENE CF | Construction - Building | 10/24/2011 |
Office of General Services - Design & Construction | DEE541H |
$300,000.00
|
$221,707.00 |
02/25/2021 | 06/25/2021 | Repair steam leaks Grandview bldg 15 Willard Drug Treatment Center Seneca County | Construction - Building | 04/29/2021 |
Office of General Services - Design & Construction | DEC482H |
$100,000.00
|
$32,839.00 |
11/06/2013 | 03/06/2014 | REPAIR REPLACE LEAKING STEAM AND RETURN LINES BUILDING 14 AUBURN CF | Construction - Building | 12/10/2013 |
Office of General Services - Design & Construction | D47140H |
$468,700.00
|
$310,871.30 |
03/27/2023 | 01/27/2025 | Roof replacement NYS Police Troop E Headquarters HVAC Ontario County | Construction - Building | 03/27/2023 |
Office of General Services - Design & Construction | DEE126H |
$150,000.00
|
$56,850.00 |
06/19/2019 | 11/16/2019 | Repair Steam Leak Between Midstate CF & Marcy CF Oneida County | Construction - Building | 09/10/2019 |
Office of General Services - Design & Construction | DEC459H |
$100,000.00
|
$67,600.00 |
10/07/2013 | 02/04/2014 | REPLACE LEAKING STEAM & CONDENSATE LINES GREATER BINGHAMTON HC BROOME COUNTY | Construction - Building | 11/01/2013 |
Office of General Services - Design & Construction | DEB912P |
$300,000.00
|
$88,167.00 |
04/30/2012 | 10/30/2012 | DECOMMISSIONING OF WATER/ PLUMBING SYSTEM DUE TO CLOSURE OF SUMMIT CF | Construction - Building | 05/22/2012 |
Office of General Services - Design & Construction | D42612H |
$945,529.00
|
$927,845.00 |
01/25/2008 | 05/19/2011 | BATHROOM & SHOWER RENOVATIONS-DORMS C-I K & L GROVELAND CF | Construction - Building | 06/25/2010 |
Office of General Services - Design & Construction | D42612P |
$778,993.00
|
$776,416.00 |
01/25/2008 | 05/19/2011 | BATHROOM & SHOWER RENOVATIONS-DORMS C-I K & L GROVELAND CF | Construction - Building | 06/25/2010 |
Office of General Services - Design & Construction | D46079H |
$709,343.00
|
$642,594.00 |
08/05/2020 | 07/16/2021 | Replace Two Roof Mounted Cooling Towers Albany County | Construction - Building | 08/05/2020 |
Office of General Services - Design & Construction | D44291H |
$712,508.00
|
$712,467.00 |
05/29/2012 | 12/31/2013 | REPLACE STEAM AND CONDENSATE RETURN LINES BETWEEN BLDG NOS. 9 (ATTICA) & 72 (WYOMING) | Construction - Building | 05/29/2012 |
Office of General Services - Design & Construction | D45602H |
$1,285,000.00
|
$1,209,864.98 |
08/24/2017 | 10/13/2018 | Replace Condensate Piping Harriman State Office Building Campus Albany County | Construction - Building | 08/24/2017 |
Office of General Services - Design & Construction | DED666H |
$120,000.00
|
$21,790.00 |
12/07/2017 | 04/06/2018 | Repair Steam/Condensate Line Bldg 58 Hudson CF Columbia County | Construction - Building | 12/29/2017 |
Office of General Services - Design & Construction | DED882H |
$150,000.00
|
$4,029.00 |
08/09/2018 | 12/07/2018 | Restore Air Conditioning Bldg 5 Hutchings PC Oswego County | Construction - Building | 10/04/2018 |
Office of General Services - Design & Construction | DEB515H |
$200,000.00
|
$15,296.00 |
03/19/2011 | 07/17/2011 | RESTORE FAILED HEAT/HOT WATER S BLOCK BLDG 28 GOUVERNEUR CF | Construction - Building | 05/10/2011 |
Office of General Services - Design & Construction | DEC838H |
$200,000.00
|
$29,240.00 |
01/29/2015 | 05/29/2015 | Emergency - Repair Piping & Valves on Heat Exchanger Building 28 Elmira CF | Construction - Building | 02/18/2015 |
Office of General Services - Design & Construction | DEB911H |
$300,000.00
|
$91,756.00 |
04/30/2012 | 08/28/2012 | DECOMMISSION HEATING SYSTEM HVAC AT SUMMIT CF | Construction - Building | 05/22/2012 |
Office of General Services - Design & Construction | DEC795P |
$300,000.00
|
$16,129.00 |
11/24/2014 | 03/24/2015 | REPAIR HOT WATER HEATER BLDG 136 WILLARD DRUG TREATMENT CENTER SENECA COUNTY | Construction - Building | 12/15/2014 |
Office of General Services - Design & Construction | D42910P |
$782,047.00
|
$782,047.00 |
05/06/2008 | 11/01/2010 | REHABILITATE PARKING GARAGE BINGHAMTON GOVERNMENT CENTER | Construction - Building | 06/21/2010 |
Office of General Services - Design & Construction | DEC813H |
$300,000.00
|
$32,106.00 |
12/10/2014 | 06/02/2015 | REPAIR / REPLACE 500 GALLON HOT WATER TANK @ BLDG 5, FIVE POINT CF, SENECA CO | Construction - Building | 01/09/2015 |
Office of General Services - Design & Construction | DEC613H |
$200,000.00
|
$18,386.00 |
04/08/2014 | 08/06/2014 | REPAIR LEAKING UNDERGROUND HEATING LINE SOUTHPORT CF | Construction - Building | 05/16/2014 |
Office of General Services - Design & Construction | DEE059P |
$75,000.00
|
$14,343.00 |
03/13/2019 | 08/10/2019 | Investigate Repair Replace Grease Trap Drain Mercy CF Oneida County | Construction - Building | 05/15/2019 |
Office of General Services - Design & Construction | DEE540H |
$75,000.00
|
$2,556.91 |
02/26/2021 | 06/26/2021 | Repair hot water riser lines CORE 4 Empire State Plaza Swan Bldg Albany County | Construction - Building | 04/28/2021 |
Office of General Services - Design & Construction | DEE316P |
$200,000.00
|
$52,914.00 |
03/31/2020 | 07/29/2020 | Repair Replace Grease Traps Building 16 Rooms 1-43 Elmira CF Chemung County | Construction - Building | 06/11/2020 |
Office of General Services - Design & Construction | DEE753H |
$200,000.00
|
$3,630.10 |
01/18/2022 | 05/18/2022 | Repair leaking reheat pipe State OB Campus Albany County | Construction - Building | 02/24/2022 |
Office of General Services - Design & Construction | DED142P |
$100,000.00
|
$18,271.00 |
02/05/2016 | 06/04/2016 | Replace Domestic Hot Water Boiler, Building 8, Hale Creek CF | Construction - Building | 03/10/2016 |
Office of General Services - Design & Construction | DEB734H |
$100,000.00
|
$34,358.00 |
10/21/2011 | 02/18/2012 | REPAIR HOT WATER TANK BLDG 75 KITCHEN GREATER BINGHAMTON HC | Construction - Building | 11/28/2011 |
Office of General Services - Design & Construction | DQ1747H |
$775,786.00
|
$767,519.00 |
09/11/2018 | 12/11/2019 | Replace HVAC Equipment Convert Bldg to Natural Gas Albany County H | Construction - Building | 09/11/2018 |
Office of General Services - Design & Construction | D44672H |
$409,366.00
|
$408,803.00 |
04/16/2014 | 07/01/2016 | HVAC WORK PROVIDE STEAM TO HOT WATER CONVERTER FIVE POINTS CF SENECA CO | Construction - Building | 04/16/2014 |
Office of General Services - Design & Construction | D47405H |
$2,087,000.00
|
$130,180.23 |
10/11/2023 | 12/24/2024 | Replace steam & condensate direct bury piping at State Office Building Campus in Albany County | Construction - Building | 10/11/2023 |
Office of General Services - Design & Construction | D45968H |
$2,654,000.00
|
$1,841,887.82 |
12/19/2022 | 01/25/2025 | Replace Pumps Heat Exchangers & Domestic Water Chiller at GNARESP Corning Tower Albany County | Construction - Building | 12/19/2022 |
Office of General Services - Design & Construction | D46050H |
$7,665,799.00
|
$7,600,908.00 |
03/28/2022 | 01/29/2024 | Replace Hot Water Lines from Albion CF to Orleans CF Orleans County | Construction - Building | 03/28/2022 |
Office of General Services - Design & Construction | DEE169H |
$850,000.00
|
$489,839.00 |
08/27/2019 | 05/12/2020 | Provide Ventilation at Maintenance HQ at Region 9 Oneonta Otsego County | Construction - Building | 10/11/2019 |
Office of General Services - Design & Construction | D43381H |
$3,039,269.00
|
$3,012,941.88 |
03/06/2009 | 08/26/2011 | UPGRADE HEATING SYSTEMS BLDG 1 & 31 MID-STATE CF | Construction - Building | 06/29/2011 |
Office of General Services - Design & Construction | DEE618H |
$200,000.00
|
$8,108.62 |
07/27/2021 | 11/24/2021 | Repair leaking condensing unit & rooftop damage bldg 16 Elmira CF Chemung county | Construction - Building | 08/26/2021 |
Office of General Services - Design & Construction | D43908P |
$680,601.00
|
$679,441.00 |
09/25/2009 | 04/15/2012 | RENOVATE CENTENNIAL HALL PHASE III PLUMBING CENTENNIAL HALL | Construction - Building | 09/25/2009 |
Office of General Services - Design & Construction | D43618H |
$422,668.00
|
$422,658.00 |
01/05/2010 | 07/04/2011 | PRV POWER & AIR CONDITIONING UPGRADES-DATA CENTER DEC HEADQUARTERS | Construction - Building | 02/23/2011 |
Office of General Services - Design & Construction | D43134H |
$1,835,525.00
|
$1,832,678.00 |
02/10/2010 | 09/25/2014 | PROGRAM BUILDING ADDITION BUILDING 115 ALBION CF | Construction - Building | 02/10/2010 |
Office of General Services - Design & Construction | D44104H |
$444,000.00
|
$423,692.00 |
08/11/2011 | 12/23/2012 | PROVIDE SHOWER RENOVATIONS, VARIOUS DORMS LIVINGSTON CF | Construction - Building | 08/11/2011 |
Office of General Services - Design & Construction | DEE136H |
$421,593.00
|
$356,014.00 |
08/16/2019 | 08/31/2021 | Repair Coolers 2 4 5 & 9 Coxsackie CF Greene County | Construction - Building | 09/25/2019 |
Office of General Services - Design & Construction | DEF136H |
$300,000.00
|
$9,906.52 |
01/17/2024 | 07/15/2024 | Repair boiler at Albion Correctional Facility in Orleans County | Construction - Building | 02/29/2024 |
Office of General Services - Design & Construction | D43042H |
$498,000.00
|
$492,735.00 |
10/29/2009 | 06/03/2012 | PROVIDE FIRST RESPONDER TRAINING FACILITY ONEIDA COUNTY FACILITY | Construction - Building | 10/29/2009 |
Office of General Services - Design & Construction | D43042P |
$37,000.00
|
$35,403.00 |
10/29/2009 | 06/03/2012 | PROVIDE FIRST RESPONDER TRAINING FACILITY ONEIDA COUNTY FACILITY | Construction - Building | 10/29/2009 |
Office of General Services - Design & Construction | DEB962H |
$300,000.00
|
$86,730.00 |
06/19/2012 | 10/23/2013 | REPLACE MEDICAL CENTER CHILLER LIVINGSTON CF | Construction - Building | 08/24/2012 |
College at Cortland | T000479 |
$63,120.00
|
$63,107.82 |
06/01/2015 | 06/30/2016 | CHILLER SERVICE | Contracts Not Subject to OSC Pre-Audit | 07/31/2015 |
College at Cortland | T000544 |
$60,544.00
|
$58,389.00 |
09/01/2010 | 06/30/2016 | ICE ARENA CHILLER MAINTENANCE CONTRACT | Contracts Not Subject to OSC Pre-Audit | 09/28/2010 |
College of Ceramics at Alfred University | T167438 |
$356,200.00
|
$356,171.46 |
07/16/2012 | 11/16/2012 | REPLACEMENT OF HARDER HALL AIR | Contracts Not Subject to OSC Pre-Audit | 07/12/2012 |
SUNY - Upstate Medical University | T504632 |
$31,680.00
|
$31,680.00 |
07/01/2018 | 06/30/2021 | PREVENTIVE MAINTENANCE SERVICE | Contracts Not Subject to OSC Pre-Audit | 07/31/2018 |
SUNY - Upstate Medical University | T505579 |
$108,592.00
|
$95,197.00 |
03/01/2021 | 02/28/2024 | BUILDING TU4 MECHANICAL MAINTE | Contracts Not Subject to OSC Pre-Audit | 04/07/2021 |