Department/Facility | Contract Number | Current Contract Amount | Spending to Date | Contract Start Date | Contract End Date | Contract Description | Contract Type | Original Contract Approved/Filed Date |
---|---|---|---|---|---|---|---|---|
Office of General Services - Design & Construction | DEE393C |
$300,000.00
|
$103,873.50 |
07/20/2020 | 01/16/2021 | Correct Flood Damage Bldg 51 Buffalo Psychiatric Center Erie County | Construction - Building | 09/24/2020 |
Office of General Services - Design & Construction | DED581C |
$27,386.00
|
$27,386.00 |
08/22/2017 | 12/20/2017 | Provide Ballast for Tents NYS Fairgrounds Onondaga County | Construction - Building | 12/20/2017 |
Office of General Services - Design & Construction | D45544C |
$325,156.00
|
$325,151.00 |
03/17/2017 | 10/26/2017 | PROVIDE IMPROVEMENTS TO INDIAN VILLAGE, NYS FAIRGROUNDS ONONDAGA COUNTY | Construction - Building | 03/17/2017 |
Office of General Services - Design & Construction | DEE049C |
$300,000.00
|
$84,174.00 |
02/25/2019 | 06/25/2019 | Repair Roof Officers Quarters 1 Fort Ontario SHS Oswego County | Construction - Building | 04/23/2019 |
Office of General Services - Design & Construction | DED685C |
$600,000.00
|
$496,659.00 |
12/22/2017 | 12/22/2018 | Repair/Replace Walls & Floors & Provide SS Combo Units Wende CF Erie County | Construction - Building | 01/29/2018 |
Office of General Services - Design & Construction | D44288C |
$6,067,969.00
|
$6,067,901.00 |
07/08/2013 | 10/03/2017 | Repair Underground Steam Tunnels @ Willard Drug Treatment Center | Construction - Building | 07/08/2013 |
Office of General Services - Design & Construction | D43650C |
$5,602,855.00
|
$5,516,580.48 |
03/28/2011 | 11/14/2014 | REPLACE WINDOWS A&B BLOCK BUILDING 5 AUBURN CF | Construction - Building | 03/28/2011 |
Office of General Services - Design & Construction | D44364C |
$487,486.00
|
$486,668.67 |
03/08/2013 | 10/14/2014 | PROVIDE SECURITY IMPROVEMENTS, Construction- MacCormick SC, Tompkins County | Construction - Building | 03/08/2013 |
Office of General Services - Design & Construction | DEE031C |
$300,000.00
|
$117,780.00 |
02/01/2019 | 06/01/2019 | Repair Sprinkler System & Restore Int Finishes Western NY DDSO Geneva Cattaraugus County | Construction - Building | 03/14/2019 |
Office of General Services - Design & Construction | DEB294C |
$150,000.00
|
$40,345.00 |
08/10/2010 | 06/27/2011 | REPAIR/REPLACE COLLAPSED WINDOW WELLS BLDG 16 GROVELAND CF | Construction - Building | 12/01/2010 |
Office of General Services - Design & Construction | DEE537C |
$300,000.00
|
$732.57 |
02/22/2021 | 08/21/2021 | Repair water fire and smoke damage Building 35 Buffalo PC | Construction - Building | 04/28/2021 |
Office of General Services - Design & Construction | DEE857C |
$300,000.00
|
$41,310.41 |
08/10/2022 | 12/08/2022 | Restore fire damage Buffalo Armory Erie County | Construction - Building | 08/24/2022 |
Office of General Services - Design & Construction | DEE742C |
$200,000.00
|
$43,875.83 |
12/29/2021 | 06/27/2022 | Repair roof Western NY DDSO Hostel 10438 Erie County Region 7 | Construction - Building | 01/20/2022 |
Office of General Services - Design & Construction | D45410C |
$1,392,861.00
|
$1,382,754.00 |
08/10/2017 | 03/31/2019 | Provide Classrooms & Cell Alterations Bldg 29 Lakeview CF Chautauqua County (GC) | Construction - Building | 08/10/2017 |
Office of General Services - Design & Construction | DEC003C |
$200,000.00
|
$55,804.00 |
08/10/2012 | 12/08/2012 | REPAIR DETERIORATED OBSERVATION CELLS WENDE CF | Construction - Building | 09/17/2012 |
Office of General Services - Design & Construction | DEB867C |
$75,000.00
|
$18,741.00 |
03/07/2012 | 07/05/2012 | INVESTIGATE & REPAIR SAGGING CEILING & ABATE ASBESTOS AT OFPC FIRE ACADEMY | Construction - Building | 06/15/2012 |
Office of General Services - Design & Construction | D44288E |
$546,346.00
|
$546,338.00 |
07/08/2013 | 07/05/2017 | Repair Underground Steam Tunnels @ Willard Drug Treatment Center | Construction - Building | 07/08/2013 |
Office of General Services - Design & Construction | D45373C |
$436,078.00
|
$429,188.00 |
10/20/2017 | 06/11/2019 | Provide concrete paver court yard and sidewalks, Henderson-Smith SOB, Steuben County | Construction - Building | 10/20/2017 |
Office of General Services - Design & Construction | DEB478C |
$125,000.00
|
$9,782.00 |
02/07/2011 | 08/06/2011 | RESTORE ICE DAMAGED ROOFS & INTERIORS BUFFALO PC | Construction - Building | 03/24/2011 |
Office of General Services - Design & Construction | D41549C |
$3,685,874.00
|
$3,679,985.00 |
07/27/2007 | 08/30/2010 | PROVIDE ENTRY AND GUARD TOWER BUILDINGS AND PERIMETER SECURITY FENCE MODIFICATIONS - ALBION CF | Construction - Building | 03/04/2010 |
Office of General Services - Design & Construction | D41704C |
$2,895,146.00
|
$2,884,133.00 |
12/09/2010 | 12/27/2012 | CONSTRUCT FIRING RANGE FISHKILL CF | Construction - Building | 01/12/2012 |
Office of General Services - Design & Construction | DQ1402C |
$474,479.00
|
$429,306.00 |
03/17/2011 | 03/20/2012 | UPGRADE SHU, BUILDING 17 ATTICA CF | Construction - Building | 12/19/2011 |
Office of General Services - Design & Construction | D44822C |
$3,319,934.00
|
$3,282,622.00 |
01/30/2018 | 09/29/2020 | Provide Maintenance Subheadquarters Cattaraugus County, Region 5 (GC) | Construction - Building | 01/30/2018 |
Office of General Services - Design & Construction | DED623C |
$600,000.00
|
$412,425.00 |
10/30/2017 | 07/28/2018 | Remediate Hazardous Materials Buildings 79 Industry Campus Monroe County | Construction - Building | 12/01/2017 |
Office of General Services - Design & Construction | DEC049C |
$175,000.00
|
$20,993.00 |
10/03/2012 | 01/31/2013 | REPAIR DETERIORATED STEAM TUNNEL WALLS BETWEEN BUILDINGS 3 AND 7 AUBURN CF | Construction - Building | 11/08/2012 |
Office of General Services - Design & Construction | DEB605C |
$300,000.00
|
$31,440.00 |
08/10/2011 | 02/06/2012 | REPAIR LEAKING ROOF & INTERIOR FINISHES BLDG 17 ATTICA CF | Construction - Building | 09/06/2011 |
Office of General Services - Design & Construction | DEB607C |
$100,000.00
|
$59,431.00 |
08/10/2011 | 01/10/2012 | DEMOLISH & REMOVE COLLAPSING STORAGE BARN BLDG 25 ROCHESTER PC | Construction - Building | 02/10/2012 |
Office of General Services - Design & Construction | DEE705C |
$200,000.00
|
$59,835.02 |
11/09/2021 | 03/09/2022 | Repair damaged wall & provide bollards 5430 South Bay Road North Syracuse Onondaga County | Construction - Building | 12/13/2021 |
Office of General Services - Design & Construction | DEE333C |
$400,000.00
|
$314,724.00 |
04/17/2020 | 01/06/2021 | Repair wind damage masonry & roof Buffalo Armory Buffalo Erie County | Construction - Building | 08/27/2020 |
Office of General Services - Design & Construction | DQ1661C |
$460,367.00
|
$447,437.00 |
04/27/2016 | 09/06/2017 | Replace Domestic Hot Water Tanks & EPDM Roofing, General Construction, Building 9, Attica CF | Construction - Building | 04/27/2016 |
Office of General Services - Design & Construction | DEE082C |
$175,000.00
|
$49,279.00 |
04/22/2019 | 08/20/2019 | Repair Maintenance Facility Region 6 Penn Yan Yates County | Construction - Building | 07/12/2019 |
Office of General Services - Design & Construction | D43473E |
$278,000.00
|
$250,299.00 |
07/18/2011 | 12/19/2014 | REPAIR ELEVATORS, BLDGS 1, 44,127, 131 & 136 WILLARD DRUG TREATMENT CENTER | Construction - Building | 07/18/2011 |
Office of General Services - Design & Construction | D42378C |
$2,111,018.00
|
$2,096,711.00 |
06/05/2017 | 08/03/2021 | Upgrade Electric Distribution System Willard Drug Treatment Center Seneca County | Construction - Building | 06/05/2017 |
Office of General Services - Design & Construction | DEB602C |
$150,000.00
|
$129,660.00 |
08/04/2011 | 06/27/2012 | REPAIR HOLES IN CELL & SHOWER WALLS BLDG 5 AUBURN CF | Construction - Building | 02/10/2012 |
Office of General Services - Design & Construction | D44733C |
$720,656.00
|
$720,038.00 |
05/23/2016 | 09/23/2017 | PROVIDE EXPANSION, ANNEX BLDG. DOT REGION 6, COOPERS PLAINS | Construction - Building | 05/24/2016 |
Office of General Services - Design & Construction | D43120E |
$2,743,647.00
|
$2,742,334.00 |
09/03/2010 | 01/31/2014 | REPLACE ELECTRICAL & LIGHTING SYSTEMS ELMIRA CF | Construction - Building | 09/03/2010 |
Office of General Services - Design & Construction | DEA930C |
$300,000.00
|
$208,826.00 |
09/01/2009 | 08/28/2010 | REPAIR FALLING BRICKWORK ON PARAPETS BUFFALO ARMORY | Construction - Building | 01/11/2010 |
Office of General Services - Design & Construction | DQ1784C |
$338,400.00
|
$331,576.00 |
02/01/2021 | 09/06/2022 | Replace sanitary line Wyoming CF Wyoming & Genesee Counties | Construction - Building | 02/01/2021 |
Office of General Services - Design & Construction | DEC499C |
$200,000.00
|
$199,720.00 |
11/22/2013 | 12/12/2014 | REPAIR & STABILIZE FALLING MASONRY FRONT ENTRANCE BUFFALO ARMORY | Construction - Building | 12/27/2013 |
Office of General Services - Design & Construction | DEE737C |
$1,250,000.00
|
$1,158,728.22 |
12/20/2021 | 03/09/2023 | Repair boiler explosion damage building 1 Willard Drug Treatment Center Seneca County Region 6 | Construction - Building | 01/28/2022 |
Office of General Services - Design & Construction | DQ1814C |
$199,500.00
|
$193,208.00 |
05/20/2022 | 01/03/2024 | Provide generator Building 72 Collins CF Erie County | Construction - Building | 05/20/2022 |
Office of General Services - Design & Construction | D45763C |
$14,523,758.00
|
$14,221,284.40 |
06/14/2018 | 04/15/2022 | Rehab Bldgs 85 89 140 200 & Entry Bldg 457 Groveland CF Livingston County (C) | Construction - Building | 06/14/2018 |
Office of General Services - Design & Construction | DQ1826E |
$261,000.00
|
$155,165.00 |
11/18/2022 | 08/14/2024 | Provide Facility Closure Willard Drug Treatment Center Seneca County | Construction - Building | 11/18/2022 |
Office of General Services - Design & Construction | DQ1826C |
$2,427,000.00
|
$1,567,953.00 |
11/18/2022 | 08/14/2024 | Provide Facility Closure Willard Drug Treatment Center Seneca County | Construction - Building | 11/18/2022 |
Office of General Services - Design & Construction | DEB932C |
$200,000.00
|
$24,158.00 |
05/24/2012 | 09/21/2012 | REPLACE SPRINKLER HEAD/RENOVATE WATER DAMAGED ROOMS IN BUILDING 4 BUFFALO PC | Construction - Building | 07/10/2012 |
Office of General Services - Design & Construction | DED459C |
$200,000.00
|
$101,357.00 |
04/10/2017 | 08/08/2017 | REPLACE WATER DAMAGED FINISHES & MOLD REMEDIATION, ELMIRA PC, CHEMUNG COUNTY | Construction - Building | 04/26/2017 |
Office of General Services - Design & Construction | DEE602C |
$300,000.00
|
$31,994.90 |
07/13/2021 | 11/10/2021 | Repair damaged support column Dairy Bldg NYS Fairgrounds | Construction - Building | 08/03/2021 |
Office of General Services - Design & Construction | D44254C |
$1,782,993.00
|
$1,782,971.00 |
04/08/2013 | 10/31/2014 | PROVIDE SECURITY WINDOWS ADMINISTRATION BLDG 24 AND BLDG 7 ALBION CF | Construction - Building | 04/08/2013 |
Office of General Services - Design & Construction | DQ1271C |
$257,750.00
|
$254,777.00 |
09/27/2010 | 05/08/2013 | REHAB LOCKER ROOMS, BLDG. 1 ADMIN BASEMENT AUBURN CF | Construction - Building | 09/13/2011 |
Office of General Services - Design & Construction | DQ1343C |
$156,000.00
|
$152,272.00 |
07/09/2010 | 09/10/2011 | BATHROOM RENOVATIONS - MT MCGREGOR CF | Construction - Building | 07/09/2010 |