Department/Facility | Contract Number | Current Contract Amount | Spending to Date | Contract Start Date | Contract End Date | Contract Description | Contract Type | Original Contract Approved/Filed Date |
---|---|---|---|---|---|---|---|---|
New York State Thruway Authority | CT17067 |
$425,000.00
|
$0.00 |
09/27/2017 | 08/31/2020 | READY-MIX CONCRETE | Commodity - Road Materials | 09/27/2017 |
New York State Thruway Authority | CT19065 |
$50,000.00
|
$0.00 |
11/13/2019 | 09/30/2020 | Ready-Mix Concrete | Commodity - Miscellaneous | 11/13/2019 |
New York State Thruway Authority | CT20104 |
$231,250.00
|
$0.00 |
06/10/2021 | 09/30/2025 | Ready-mix concrete | Commodity - Road Materials | 06/10/2021 |
New York State Thruway Authority | D213860 |
$5,973,887.71
|
$0.00 |
05/13/2010 | 06/30/2011 | IR MILL & INLAY W/ SAFETY IMPROVEMENTS MP 313.75-MP 320.7 SYRACUSE DIVISION | Construction - Highway | 12/29/2010 |
New York State Thruway Authority | D213917 |
$8,833,701.20
|
$0.00 |
05/13/2010 | 06/17/2011 | LR MILL & INLAY AND MISC WORK MP180.0-MP 197.9 MONTGOMERY COUNTY | Construction - Highway | 12/29/2010 |
New York State Thruway Authority | D214247 |
$7,637,727.95
|
$0.00 |
02/10/2014 | 06/15/2015 | MILL & INLAY SAFETY IMPROVEMENTS & MISCELLANEOUS WORK SYRACUSE DIVISION | Construction - Highway | 02/10/2014 |
New York State Thruway Authority | D214458 |
$8,368,761.27
|
$0.00 |
06/09/2016 | 12/02/2016 | 1R Mill and Inlay, Drainage/Safety Improvements, Herkimer and Oneida Counties | Construction - Highway | 06/09/2016 |
New York State Thruway Authority | D214551 |
$18,382,554.45
|
$0.00 |
03/17/2017 | 10/31/2018 | Pave.Rehab.&Safety Improve.MP233-5 to 252-2&Drainage Improve.MP 205-05(WB)Onieda&Montgomery Counties | Construction - Highway | 03/17/2017 |
New York State Thruway Authority | D214586 |
$3,238,980.59
|
$0.00 |
11/02/2017 | 10/31/2018 | 1R safety Improve and misc work. MP240.9 to MP252.2, Oneida and Madison Counties. | Construction - Highway | 11/02/2017 |
New York State Thruway Authority | D214685 |
$5,629,408.29
|
$0.00 |
08/08/2018 | 08/16/2019 | Highway Resurfacing Mill & Inlay I-90 from MP 304 to MP 313 Cayuga & Seneca Counties TAS 18-30 | Construction - Highway | 08/08/2018 |
New York State Thruway Authority | D214924 |
$4,598,975.95
|
$0.00 |
07/27/2023 | 11/30/2023 | Pavement repairs & resurfacing at various locations in Montgomery County | Construction - Highway | 07/27/2023 |
Department of Transportation | D261059 |
$2,279,760.92
|
$2,279,760.92 |
05/01/2009 | 12/18/2009 | ASPHALT CONCRETE RESURFACING ROUTES 5A & 69 TOWN OF WHITESTOWN, ONEIDA COUNTY | Construction - Highway | 12/09/2009 |
Department of Transportation | D261221 |
$1,561,133.50
|
$1,561,133.50 |
09/21/2009 | 07/31/2010 | RESURFACING ON ROUTES 5S & 28 HERKIMER, MOHAWK & RUSSIA, HERKIMER COUNTY | Construction - Highway | 09/21/2009 |
Department of Transportation | D261228 |
$5,286,328.51
|
$5,286,328.51 |
09/16/2009 | 11/30/2010 | RESURFACING ROUTES 12, 13, 26, 46, 49 & 69 MADISON & ONEIDA COUNTIES | Construction - Highway | 12/08/2010 |
Department of Transportation | D261229 |
$3,807,721.39
|
$3,807,721.39 |
09/22/2009 | 09/10/2010 | RESURFACING AT VARIOUS LOCATIONS, ONEIDA CO. | Construction - Highway | 08/25/2010 |
Department of Transportation | D261605 |
$675,346.66
|
$675,346.66 |
03/07/2011 | 11/30/2011 | MILL AND RESURFACE 2.4 MILES RTE 14 SODUS POINT, WAYNE COUNTY | Construction - Highway | 03/07/2011 |
Department of Transportation | D261716 |
$478,400.14
|
$478,400.14 |
06/09/2011 | 11/30/2011 | PREVENTIVE & CORRECTIVE MAINTENANCE ROUTE 350 WAYNE COUNTY | Construction - Highway | 06/09/2011 |
Department of Transportation | D261737 |
$834,932.57
|
$834,932.57 |
07/13/2011 | 11/30/2011 | ASPHALT CONCRETE MILL & RESURFACE RT19 & 20A WARSAW, WYOMING COUNTY | Construction - Highway | 07/13/2011 |
Department of Transportation | D261738 |
$1,930,437.91
|
$1,930,437.91 |
08/12/2011 | 11/30/2011 | RESURFACE ASPHAULT CONCRETE ROUTE 20A LIVINGSTON & WYOMING COUNTIES | Construction - Highway | 08/12/2011 |
Department of Transportation | D261740 |
$1,933,236.31
|
$1,933,236.31 |
07/13/2011 | 12/03/2011 | REPAIR & RESURFACE ROUTES 245 & 364 YATES COUNTY | Construction - Highway | 11/25/2011 |
Department of Transportation | D261761 |
$993,582.20
|
$993,582.20 |
07/13/2011 | 06/30/2012 | ROADSIDE SAFETY GUIDERAIL CONTRACT WESTMORELAND WHITESTOWN ROME, ONEIDA COUNTY | Construction - Highway | 12/23/2011 |
Department of Transportation | D261927 |
$7,788,399.91
|
$7,788,399.91 |
03/09/2012 | 11/30/2012 | MILL & REPAVE IINTERSTATE 81 JEFFERSON COUNTY | Construction - Highway | 03/09/2012 |
Department of Transportation | D262071 |
$7,053,546.66
|
$7,053,546.66 |
06/22/2012 | 12/31/2012 | MULTI SITE PAVEMENT REHABILITATION HERKIMER ONEIDA & OSWEGO COUNTIES | Construction - Highway | 06/22/2012 |
Department of Transportation | D262075 |
$6,319,006.13
|
$6,319,006.13 |
09/27/2012 | 12/31/2013 | 10.9 MILES OF ASPHALT CONCRETE MILLING & RESURFACING CRACK & FULL DEPTH PAVEMENT REPAIRS ON I-505 | Construction - Highway | 09/27/2012 |
Department of Transportation | D262283 |
$1,167,172.55
|
$1,167,172.55 |
05/08/2013 | 12/02/2013 | MILL AND RESURFACE 6.5 MILES ROUTE 15A SPRINGWATER AND CANADICE TOWNSHIPS | Construction - Highway | 05/08/2013 |
Department of Transportation | D262597 |
$2,288,545.28
|
$2,288,545.28 |
06/18/2014 | 11/14/2014 | ASPHALT CONCRETE RESURFACING ROUTE 444 TOWNS OF VICTOR & EAST BLOOMFIELD ONTARIO COUNTY | Construction - Highway | 06/18/2014 |
Department of Transportation | D262598 |
$1,919,992.36
|
$1,919,992.36 |
06/10/2014 | 01/02/2015 | ASPHALT CONCRETE RESURFACING ROUTE 408 TOWNS OF NUNDA & MOUNT MORRIS LIVINGSTON COUNTY | Construction - Highway | 06/10/2014 |
Department of Transportation | D262849 |
$704,378.13
|
$704,378.13 |
04/24/2015 | 11/30/2015 | Realignment of Vertical Profile of Approximately 0.35 Mile of Route 20, Herkimer County | Construction - Highway | 04/24/2015 |
Department of Transportation | D262851 |
$2,023,816.24
|
$2,023,816.24 |
03/10/2015 | 12/31/2015 | ASPHALT CONCRETE RESURFACING RT 5, US RT 20, AND RT 414, VILLAGE & TOWN OF WATERLOO, SENECA FALLS | Construction - Highway | 03/10/2015 |
Department of Transportation | D262883 |
$5,190,587.42
|
$5,190,587.42 |
04/30/2015 | 12/31/2015 | Asphalt Concrete Resurfacing, Route 28, Old Forge to Eagle Bay, Town of Webb, Herkimer County | Construction - Highway | 04/30/2015 |
Department of Transportation | D263077 |
$3,255,857.62
|
$3,255,857.62 |
01/13/2016 | 06/30/2016 | Milling & Resurfacing Route 54A, Town of Pulteney, Steuben County | Construction - Highway | 01/13/2016 |
Department of Transportation | D263158 |
$4,152,584.43
|
$4,152,584.43 |
05/04/2016 | 11/30/2016 | 12.4 Mi.Asphalt Concrete Resurfacing Rte63 Towns of Groveland,Geneseo&York-Livingston County,Reg. 4 | Construction - Highway | 05/04/2016 |
Department of Transportation | D263179 |
$888,672.39
|
$888,672.39 |
06/14/2016 | 08/31/2016 | Milling and Asphalt Concrete Resurfacing Route 5A in the Town of New Hartford Oneida County Region 2 | Construction - Highway | 06/14/2016 |
Department of Transportation | D263257 |
$3,647,808.11
|
$3,647,808.11 |
12/14/2016 | 11/30/2017 | 11.3 Miles of Asphalt Concrete Paving on NY Rte 5 & US Rte 20 Twns of Hopewell & Seneca Ontario Co | Construction - Highway | 12/14/2016 |
Department of Transportation | D263268 |
$3,230,668.72
|
$3,230,668.72 |
11/25/2016 | 11/15/2017 | Asphalt Concrete Resurface&Sign Replace&Guide Rail I-490 Leroy Bergin Chili Riga Reg4 Genesee County | Construction - Highway | 11/25/2016 |
Department of Transportation | D263269 |
$967,403.04
|
$967,403.04 |
11/14/2016 | 09/30/2017 | Cold in-place Recycling and Maintenance Paving, Wayne County, Region 4 | Construction - Highway | 11/14/2016 |
Department of Transportation | D263468 |
$1,638,330.06
|
$1,638,330.06 |
06/16/2017 | 01/31/2018 | Preventive Maintenance Pavemt Rt.5 Madison Co.-Sconondoa St Oneida Castle Sherill & Vernon Oneida Co | Construction - Highway | 06/16/2017 |
Department of Transportation | D263537 |
$5,015,913.35
|
$5,015,913.35 |
09/15/2017 | 09/28/2018 | Rts 5, 49,840 preventative maintenance, Rome/Utica, Oneida County | Construction - Building | 09/15/2017 |
Department of Transportation | D263580 |
$1,275,654.47
|
$1,275,654.47 |
01/11/2018 | 06/14/2019 | Pedestrian & Safety Imprvmnts. US Rte. 20, Nelson, Madison County | Construction - Highway | 01/11/2018 |
Department of Transportation | D263678 |
$421,431.44
|
$421,431.44 |
05/21/2018 | 11/30/2018 | Pavement Resurface NY 12 Village of Sherburne Chenango County | Construction - Highway | 05/21/2018 |
Department of Transportation | D263684 |
$4,877,242.00
|
$4,877,242.00 |
05/07/2018 | 08/31/2019 | Paving Along Rtes 8 & 12 with Guide Rail, Drainage, Bridge Work, etc., T/O Deerfield Oneida County | Construction - Highway | 05/07/2018 |
Department of Transportation | D263702 |
$4,284,058.56
|
$4,284,058.56 |
10/24/2018 | 08/14/2020 | Safety Widening Project Route 5 W of Chamberline Dr to E of Sunview Dr SH 5080 Onondaga County | Construction - Highway | 10/24/2018 |
Department of Transportation | D263806 |
$2,981,862.14
|
$2,981,862.14 |
12/24/2018 | 11/30/2019 | Asphalt Concrete Reconstruction 0.7 Miles Fulton County | Construction - Highway | 12/24/2018 |
Department of Transportation | D263874 |
$533,528.60
|
$533,528.60 |
04/12/2019 | 11/29/2019 | Empire State Trail Improvement Project Herkimer County | Construction - Highway | 04/12/2019 |
Department of Transportation | D263939 |
$4,813,666.71
|
$4,813,666.71 |
07/18/2019 | 06/06/2020 | Rehab Pavement Rte 5S Towns of Little Falls & Danube Herkimer County | Construction - Highway | 07/18/2019 |
Department of Transportation | D264001 |
$9,641,951.79
|
$9,641,951.79 |
09/05/2019 | 06/30/2021 | Intersection Reconfiguration Asphalt Concrete Milling Resurfacing & Sign Maintenance Oneida County | Construction - Highway | 09/05/2019 |
Department of Transportation | D264135 |
$2,471,218.53
|
$2,471,218.53 |
03/27/2020 | 06/15/2021 | Milling & Resurfacing State Rte 5 Oneida and Canastota Madison County | Construction - Highway | 03/27/2020 |
Department of Transportation | D264204 |
$2,845,188.13
|
$2,845,188.13 |
07/17/2020 | 07/31/2021 | 3.4 Miles Asphalt Rehabilitation & Safety Improvements Route 5 Herkimer & Little Falls Herkimer Co | Construction - Highway | 07/17/2020 |
Department of Transportation | D264238 |
$2,404,530.42
|
$2,404,530.42 |
06/17/2020 | 12/31/2020 | Asphalt Milling & Resurfacing Route 104 Williamson Sodus & Ontario Wayne County | Construction - Highway | 06/17/2020 |
Department of Transportation | D264356 |
$5,767,453.08
|
$5,767,453.08 |
04/23/2021 | 01/31/2022 | Guiderail replacement MBC pavement resurface Marcellus Onondaga Skaneateles Onondaga County Region 3 | Construction - Highway | 04/23/2021 |