Department/Facility | Contract Number | Current Contract Amount | Spending to Date | Contract Start Date | Contract End Date | Contract Description | Contract Type | Original Contract Approved/Filed Date |
---|---|---|---|---|---|---|---|---|
Office of General Services - Design & Construction | D46137P |
$300,419.00
|
$286,523.00 |
08/14/2020 | 09/16/2022 | New classrooms & office space Bldg 118 Bedford Hills CF Westchester County | Construction - Building | 08/14/2020 |
Office of General Services - Design & Construction | D46131P |
$852,416.00
|
$842,874.00 |
08/14/2020 | 06/01/2023 | Provide classrooms & office space Bldg 100 Residential Rehab Unit Fishkill CF Dutchess County | Construction - Building | 08/14/2020 |
Office of General Services - Design & Construction | DEE340H |
$300,000.00
|
$67,243.00 |
05/01/2020 | 08/29/2020 | Repair powerhouse boiler leak Sing Sing CF 354 Hunter St Ossining Westchester County | Construction - Building | 08/19/2020 |
Office of General Services - Design & Construction | D46133H |
$2,210,950.00
|
$1,955,423.63 |
08/24/2020 | 12/14/2023 | New classrooms & office spaces Bldg 45 Greene Correctional Facility Greene County | Construction - Building | 08/24/2020 |
Office of General Services - Design & Construction | D46046H |
$2,034,013.00
|
$1,834,358.94 |
09/02/2020 | 06/30/2024 | Provide HVAC Interior Renovations Bldg 503 Camp Smith Training Site Westchester County | Construction - Building | 09/02/2020 |
Office of General Services - Design & Construction | D44992H |
$302,950.00
|
$240,578.47 |
09/03/2020 | 04/17/2024 | Replace High Voltage Switchgear & Generator Ottisville CF Ottisville Orange County | Construction - Building | 09/03/2020 |
Office of General Services - Design & Construction | DEE388H |
$200,000.00
|
$89,089.00 |
07/16/2020 | 01/13/2021 | Repair A/C S-Block Control Room Visit Room Greene CF Greene County | Construction - Building | 10/28/2020 |
Office of General Services - Design & Construction | DEE455H |
$100,000.00
|
$40,088.00 |
10/22/2020 | 08/19/2021 | Repair ISO ventilation fan Green Haven CF | Construction - Building | 12/16/2020 |
Office of General Services - Design & Construction | DEE468H |
$300,000.00
|
$199,064.00 |
11/05/2020 | 12/30/2021 | Repair heat exchanger and piping Building 66 Sullivan CF Sullivan county | Construction - Building | 01/06/2021 |
Office of General Services - Design & Construction | D45659H |
$561,308.00
|
$553,674.64 |
01/21/2021 | 11/17/2023 | Replace windows stairways & upgrade HVAC Bldg 819 Rockland PC Hudson River Campus Dutchess County | Construction - Building | 01/21/2021 |
Office of General Services - Design & Construction | DEE482H |
$300,000.00
|
$203,912.00 |
11/30/2020 | 01/19/2023 | Restore heat, Bldg 5 - HVAC, Sing Sing CF | Construction - Building | 01/22/2021 |
Office of General Services - Design & Construction | DM3098H |
$2,479,931.00
|
$1,496,271.08 |
01/22/2021 | 02/04/2025 | Heating system repairs Bldg 12 Vocational School Green Haven Correctional Facility Dutchess County | Construction - Building | 01/22/2021 |
Office of General Services - Design & Construction | DM3077H |
$49,058.00
|
$47,158.00 |
02/16/2021 | 06/12/2023 | Rehabilitate elevator Fishkill CF Building #21-1 Dutchess County | Construction - Building | 02/16/2021 |
Office of General Services - Design & Construction | D45847H |
$743,260.00
|
$187,577.00 |
02/22/2021 | 08/01/2023 | Provide recording room and facility wide CCTV/Audio and alarm system Downstate CF Dutchess County | Construction - Building | 02/22/2021 |
Office of General Services - Design & Construction | D44086P |
$74,619.00
|
$69,301.00 |
02/25/2021 | 02/02/2023 | Replace wastewater treatment plant Highland Residential Center Ulster County | Construction - Building | 02/25/2021 |
Office of General Services - Design & Construction | D46024H |
$818,318.00
|
$734,975.26 |
02/26/2021 | 07/29/2024 | Replace air handling unit Building 44 Cook Chill Production Center Orangeburg Rockland County | Construction - Building | 02/26/2021 |
Office of General Services - Design & Construction | DM3116P |
$23,796.00
|
$22,696.00 |
03/26/2021 | 04/20/2022 | Replace Roof Downstate Correctional Facility Dutchess County | Construction - Building | 03/26/2021 |
Office of General Services - Design & Construction | DM3116H |
$42,025.00
|
$39,225.00 |
03/26/2021 | 07/11/2022 | Replace Roof Downstate Correctional Facility Dutchess County | Construction - Building | 03/26/2021 |
Office of General Services - Design & Construction | D46022H |
$258,129.00
|
$251,807.00 |
03/29/2021 | 03/28/2024 | Rehabilitate Freezer Space RS-7 & RS-8 Building 144 Cook Chill Production Center Rockland County | Construction - Building | 03/29/2021 |
Office of General Services - Design & Construction | DQ1803H |
$101,866.00
|
$25,588.19 |
05/19/2021 | 10/19/2023 | Rehabilitate tank containment infrastructure Woodbourne CF Sullivan County | Construction - Building | 05/19/2021 |
Office of General Services - Design & Construction | DEE559H |
$300,000.00
|
$81,624.54 |
04/16/2021 | 04/27/2024 | Repair Freezers in Kitchen Sing Sing CF Westchester County | Construction - Building | 05/28/2021 |
Office of General Services - Design & Construction | D45857P |
$258,070.00
|
$170,893.26 |
05/28/2021 | 12/04/2024 | Rehabilitate wastewater treatment plant Eastern CF Ulster County | Construction - Building | 05/28/2021 |
Office of General Services - Design & Construction | DM3125H |
$615,037.00
|
$485,673.29 |
07/15/2021 | 06/04/2024 | Replace gym roof bldg 45 Woodbourne CF Sullivan County | Construction - Building | 07/15/2021 |
Office of General Services - Design & Construction | D45557P |
$245,974.00
|
$222,331.73 |
08/16/2021 | 06/17/2024 | Provide laundry & day room bldg 505 Camp Smith Training Site Cortlandt Manor Westchester County | Construction - Building | 08/16/2021 |
Office of General Services - Design & Construction | D45557H |
$520,446.00
|
$457,318.88 |
08/16/2021 | 07/01/2024 | Provide laundry & day room bldg 505 Camp Smith Training Site Cortlandt Manor Westchester County | Construction - Building | 08/16/2021 |
Office of General Services - Design & Construction | D47105H |
$600,414.00
|
$565,244.53 |
08/25/2021 | 08/01/2024 | Rehabilitate 2nd floor admin area Peekskill Armory Peekskill Westchester County | Construction - Building | 08/25/2021 |
Office of General Services - Design & Construction | D47105P |
$167,968.00
|
$154,976.38 |
08/25/2021 | 06/30/2024 | Rehabilitate 2nd floor admin area Peekskill Armory Peekskill Westchester County | Construction - Building | 08/25/2021 |
Office of General Services - Design & Construction | DM3130H |
$277,077.00
|
$271,062.00 |
09/14/2021 | 06/08/2023 | Repair replace valves pipes & appurtenances HVAC work Bldgs 2 & 9 Greenhaven CF Dutchess County | Construction - Building | 09/14/2021 |
Office of General Services - Design & Construction | D45813P |
$55,254.00
|
$49,924.25 |
11/22/2021 | 12/14/2023 | Provide sleep lab bldg 35 Nathan Kline Research Institute Orangeburg Rockland County | Construction - Building | 11/22/2021 |
Office of General Services - Design & Construction | D45813H |
$127,249.00
|
$107,654.17 |
11/22/2021 | 12/14/2023 | Provide sleep lab bldg 35 Nathan Kline Research Institute Orangeburg Rockland County | Construction - Building | 11/22/2021 |
Office of General Services - Design & Construction | DM3087H |
$117,392.00
|
$9,102.13 |
11/22/2021 | 03/10/2025 | Replace freight elevator bldg 12 Wallkill CF Ulster County | Construction - Building | 11/22/2021 |
Office of General Services - Design & Construction | DEE696H |
$150,000.00
|
$26,076.94 |
10/29/2021 | 02/26/2022 | Repair and replace steam pipe lines Coxsackie CF Greene County | Construction - Building | 01/13/2022 |
Office of General Services - Design & Construction | DEE731H |
$150,000.00
|
$81,612.96 |
12/14/2021 | 03/01/2024 | Repair steam/cond leak Building B14 Sing Sing CF Westchester County Region 3 | Construction - Building | 01/14/2022 |
Office of General Services - Design & Construction | D45552H |
$989,480.00
|
$630,662.50 |
01/18/2022 | 03/25/2024 | Provide Sub-Headquarters Building in East Fishkill Dutchess County | Construction - Building | 01/18/2022 |
Office of General Services - Design & Construction | D45552P |
$831,990.00
|
$449,220.31 |
01/18/2022 | 03/25/2024 | Provide Sub-Headquarters Building in East Fishkill Dutchess County | Construction - Building | 01/18/2022 |
Office of General Services - Design & Construction | D45401P |
$285,843.00
|
$27,586.26 |
02/25/2022 | 10/12/2025 | Rehabilitate Towers 12 - 18 Sing Sing Correctional Facility Ossining Westchester County | Construction - Building | 02/25/2022 |
Office of General Services - Design & Construction | D45401H |
$130,000.00
|
$18,209.12 |
02/25/2022 | 10/12/2025 | Rehabilitate Towers 12 - 18 Sing Sing Correctional Facility Ossining Westchester County | Construction - Building | 02/25/2022 |
Office of General Services - Design & Construction | D46230H |
$222,105.00
|
$47,791.50 |
02/25/2022 | 05/05/2025 | Provide CCTV & Audio monitoring system facility wide Sullivan CF Sullivan County | Construction - Building | 02/25/2022 |
Office of General Services - Design & Construction | D45837H |
$1,770,797.00
|
$647,528.73 |
03/28/2022 | 05/06/2025 | Wastewater treatment plant improvements at Bedford Hills Correctional Facility in Westchester County | Construction - Building | 03/28/2022 |
Office of General Services - Design & Construction | D45837P |
$284,887.00
|
$159,062.10 |
03/28/2022 | 04/29/2025 | Wastewater treatment plant improvements at Bedford Hills Correctional Facility in Westchester County | Construction - Building | 03/28/2022 |
Office of General Services - Design & Construction | DM3097P |
$301,195.00
|
$173,360.68 |
03/29/2022 | 11/18/2024 | Rehabilitate Kitchen Floor Building 3 Green Haven CF Dutchess County | Construction - Building | 03/29/2022 |
Office of General Services - Design & Construction | DM3097H |
$162,248.00
|
$7,907.89 |
03/29/2022 | 01/19/2025 | Rehabilitate Kitchen Floor Building 3 Green Haven CF Dutchess County | Construction - Building | 03/29/2022 |
Office of Parks Recreation & Historic Preservation | D005903 |
$114,730.00
|
$111,630.53 |
04/14/2022 | 06/30/2023 | Renovations to Endekill Cottage Mills-Norrie State Park Dutchess County | Construction - Building | 04/14/2022 |
Office of Parks Recreation & Historic Preservation | D005902 |
$66,256.00
|
$65,646.00 |
04/14/2022 | 06/30/2023 | Renovations to Endekill Cottage Mills-Norrie State Park Dutchess County | Construction - Building | 04/14/2022 |
Office of General Services - Design & Construction | DM3126H |
$285,809.00
|
$142,003.90 |
04/19/2022 | 11/26/2024 | Repair leaking sanitary line Building 81 Taconic CF Westchester County | Construction - Building | 04/19/2022 |
Office of General Services - Design & Construction | DEE763H |
$200,000.00
|
$49,180.38 |
01/28/2022 | 09/29/2022 | Repair failing heat station building 13 Fishkill CF Dutchess County | Construction - Building | 05/03/2022 |
Office of General Services - Design & Construction | DEE838H |
$300,000.00
|
$138,228.84 |
06/15/2022 | 06/04/2024 | Repair failed hot water exchanger & valves Sing Sing CF Westchester County | Construction - Building | 07/13/2022 |
Office of General Services - Design & Construction | D46227H |
$270,842.00
|
$270,730.00 |
08/08/2022 | 05/09/2024 | Rehabilitate office & building entrance DMNA Headquarters HVAC Albany County | Construction - Building | 08/08/2022 |
Office of General Services - Design & Construction | D46166H |
$1,551,700.00
|
$1,172,777.58 |
08/12/2022 | 04/10/2024 | Replace boilers and accessories Yonkers Armory Yonkers New York | Construction - Building | 08/12/2022 |
Office of General Services - Design & Construction | D44991H |
$1,430,912.00
|
$0.00 |
08/12/2022 | 03/19/2025 | Provide generator building Shawangunk CF Ulster County | Construction - Building | 08/12/2022 |