Department/Facility | Contract Number | Current Contract Amount | Spending to Date | Contract Start Date | Contract End Date | Contract Description | Contract Type | Original Contract Approved/Filed Date |
---|---|---|---|---|---|---|---|---|
Office of Parks Recreation & Historic Preservation | D005517 |
$109,200.00
|
$104,900.00 |
04/23/2019 | 06/12/2020 | Electric Upgrades South Entrance & Campground Water System Watkins Glen State Park Schuyler County | Construction - Building | 04/23/2019 |
Office of General Services - Design & Construction | D45895E |
$122,230.00
|
$109,730.00 |
06/03/2019 | 01/30/2020 | Provide Salt Storage Buildings NYSDOT Region 9 Various Locations | Construction - Building | 06/03/2019 |
SUNY at Binghamton | T300496 |
$249,000.00
|
$84,059.71 |
05/01/2019 | 04/30/2020 | MEDIUM VOLTAGE ELECTRICAL SERV | Contracts Not Subject to OSC Pre-Audit | 08/01/2019 |
SUNY at Binghamton | T300505 |
$33,900.00
|
$33,900.00 |
09/02/2019 | 11/01/2019 | BSC LACROSSE FIELD SCOREBOARD | Contracts Not Subject to OSC Pre-Audit | 08/22/2019 |
SUNY at Binghamton | T300507 |
$57,950.00
|
$57,950.00 |
10/17/2019 | 10/15/2020 | ITS DATA CONDUIT EXTENSION SIT | Contracts Not Subject to OSC Pre-Audit | 10/08/2019 |
College at Oneonta | T990493 |
$107,216.00
|
$107,216.00 |
10/03/2019 | 07/01/2020 | PROJECT #091053 (M09567) REPL | Contracts Not Subject to OSC Pre-Audit | 10/09/2019 |
SUNY at Binghamton | T300511 |
$1,026,042.00
|
$1,026,042.00 |
10/17/2019 | 03/01/2021 | CLEVELAND HALL RENOVATIONS - E | Contracts Not Subject to OSC Pre-Audit | 10/15/2019 |
SUNY at Binghamton | T300528 |
$171,364.00
|
$171,364.00 |
04/13/2020 | 08/03/2020 | ENDICOTT HALL FIRE ALARM REPLA | Contracts Not Subject to OSC Pre-Audit | 04/07/2020 |
SUNY at Binghamton | T300540 |
$249,000.00
|
$96,456.36 |
05/01/2020 | 04/30/2022 | MEDIUM VOLTAGE SERVICE CONTRAC | Contracts Not Subject to OSC Pre-Audit | 04/24/2020 |
SUNY at Binghamton | T300537 |
$190,331.00
|
$190,331.00 |
05/18/2020 | 08/03/2020 | BROOME HALL FIRE ALARM REPLACE | Contracts Not Subject to OSC Pre-Audit | 05/07/2020 |
Office of General Services - Design & Construction | D47018E |
$57,000.00
|
$51,900.00 |
03/17/2021 | 12/16/2021 | Provide salt storage buildings Region 9 Waverly & Berkshire various locations Tioga County | Construction - Building | 03/17/2021 |
College at Oneonta | D990521 |
$284,900.00
|
$284,900.00 |
05/04/2021 | 12/31/2021 | Maintenance and operations center emergency generator upgrade | Construction - Miscellaneous | 05/04/2021 |
College at Oneonta | T990528 |
$112,749.00
|
$112,748.99 |
05/31/2021 | 10/09/2021 | 091056 UPGRADE EMERGENCY GENER | Contracts Not Subject to OSC Pre-Audit | 06/04/2021 |
College at Cortland | T000824 |
$218,315.07
|
$218,315.07 |
02/01/2022 | 08/05/2023 | RANDALL HALL BATHROOMS RENOVAT | Contracts Not Subject to OSC Pre-Audit | 02/18/2022 |
SUNY at Binghamton | T300577 |
$249,000.00
|
$66,609.87 |
05/01/2022 | 04/30/2024 | MEDIUM VOLTAGE ELECTRICAL SERV | Contracts Not Subject to OSC Pre-Audit | 06/13/2022 |
SUNY at Binghamton | D200030 |
$1,579,900.00
|
$1,498,530.00 |
08/26/2022 | 02/01/2024 | Electrical contract for the Old Rafuse dorm renovation | Construction - Building | 08/12/2022 |
College at Oneonta | D990572 |
$258,500.00
|
$231,562.50 |
02/16/2023 | 04/12/2024 | Generator interconnects at the SUNY Oneonta freshman dormitory | Construction - Miscellaneous | 02/16/2023 |
SUNY at Binghamton | D200054 |
$374,495.00
|
$209,802.75 |
06/08/2023 | 09/30/2024 | Mandela room and old union hall lighting upgrades at SUNY Binghamton | Construction - Building | 06/08/2023 |
State University Construction Fund | D006855 |
$2,405,000.00
|
$0.00 |
09/25/2023 | 02/11/2027 | Upgrade of electrical distribution at SUNY Binghamton | Construction - Miscellaneous | 09/19/2023 |
SUNY at Binghamton | D200067 |
$439,949.00
|
$250,670.80 |
01/22/2024 | 08/04/2024 | Renovation for speech and language pathology at Gannett, SUNY Binghamton, electrical | Construction - Miscellaneous | 01/22/2024 |