Department/Facility | Contract Number | Current Contract Amount | Spending to Date | Contract Start Date | Contract End Date | Contract Description | Contract Type | Original Contract Approved/Filed Date |
---|---|---|---|---|---|---|---|---|
Office of General Services - Design & Construction | D45497P |
$500,000.00
|
$128,786.00 |
01/27/2017 | 01/27/2020 | Job Order Contracting (JOC) Area 7 (P) | Construction - Building | 01/27/2017 |
Office of General Services - Design & Construction | D44216H |
$1,000,000.00
|
$451,804.00 |
08/31/2011 | 08/30/2014 | JOB ORDER CONTRACTING - AREA 6 | Construction - Building | 08/31/2011 |
Office of General Services - Design & Construction | D44216P |
$500,000.00
|
$0.00 |
08/31/2011 | 08/30/2014 | JOB ORDER CONTRACING - AREA 6 | Construction - Building | 08/31/2011 |
Office of General Services - Design & Construction | D44217H |
$750,000.00
|
$78,048.00 |
08/31/2011 | 08/30/2014 | JOB ORDER CONTRACTING - AREA 7 VARIOUS DAC FACILITIES | Construction - Building | 08/31/2011 |
Office of General Services - Design & Construction | D44217P |
$1,000,000.00
|
$357,812.00 |
08/31/2011 | 08/30/2014 | JOB ORDER CONTRACTING - AREA 7 | Construction - Building | 08/31/2011 |
Office of General Services - Design & Construction | DED763H |
$300,000.00
|
$178,479.00 |
03/01/2018 | 08/28/2018 | Repair / Replace Steel Pipe Stanchions Bldg 85 Groveland CF Livingston County | Construction - Building | 04/12/2018 |
Office of General Services - Design & Construction | DEB498H |
$75,000.00
|
$32,084.00 |
03/03/2011 | 07/01/2011 | REPAIR LEAKING UG HOT WATER RETURN LINE OGDENSBURG CF | Construction - Building | 04/22/2011 |
Office of General Services - Design & Construction | DEB511G |
$75,000.00
|
$30,893.00 |
03/15/2011 | 07/13/2011 | REPAIR BROKEN GREASE TRAP DRAIN & TANK STANDPIPE ACADEMY OF FIRE SCIENCE | Construction - Building | 04/26/2011 |
Office of General Services - Design & Construction | D44885P |
$1,000,000.00
|
$414,938.80 |
05/05/2014 | 02/10/2017 | JOB ORDER CONTRACTING (JOC)- AREA 5 Plumbing | Construction - Building | 05/05/2014 |
Office of General Services - Design & Construction | D45080H |
$60,400.00
|
$60,067.00 |
05/09/2016 | 08/09/2018 | PROVIDE SECURITY PERIMETER & STORAGE BLDG, INDUSTRY SECURE CENTER, MONROE CO | Construction - Building | 05/09/2016 |
Office of General Services - Design & Construction | DEB251H |
$300,000.00
|
$91,994.00 |
07/08/2010 | 11/05/2010 | REPAIR LEAKING UNDERGROUND HOT WATER LOOP MARCY CF | Construction - Building | 08/05/2010 |
Office of General Services - Design & Construction | DEB887G |
$150,000.00
|
$123,747.00 |
03/26/2012 | 07/24/2012 | INVESTIGATE/REPAIR WATER LINE LEAK BUILDING #44 WILLARD DRUG TREATMENT CENTER | Construction - Building | 05/08/2012 |
Office of General Services - Design & Construction | D44593H |
$101,971.00
|
$99,846.00 |
02/19/2014 | 08/15/2015 | REHAB DOT TRAFFIC SIGNAL SHOP HVAC NORTH SYRACUSE NY | Construction - Building | 02/19/2014 |
Office of General Services - Design & Construction | D46165P |
$500,000.00
|
$227,355.00 |
02/28/2020 | 09/07/2023 | Job Order Contracting Plumbing Area 5 | Construction - Building | 02/28/2020 |
Office of General Services - Design & Construction | D44985H |
$2,936,117.00
|
$2,931,819.00 |
10/20/2016 | 02/28/2019 | Provide Summer Boiler, Power House, Bldg 28 H Trade, Elmira CF Chemung County 2 Trades | Construction - Building | 10/20/2016 |
Office of General Services - Design & Construction | DEC940H |
$200,000.00
|
$110,141.00 |
05/22/2015 | 05/31/2016 | Restore Failed Chiller, Building 301, St. Lawrence PC | Construction - Building | 06/22/2015 |
Office of General Services - Design & Construction | D43105H |
$41,084.00
|
$36,784.00 |
02/28/2011 | 02/27/2012 | PROVIDE CCTV SYSTEMS, DRAFT PROCESSING & SHU ELMIRA CF | Construction - Building | 02/28/2011 |
Office of General Services - Design & Construction | DEC641G |
$200,000.00
|
$48,556.00 |
05/14/2014 | 09/11/2014 | INVESTIGATE & REPAIR SINK HOLE MAIN YARD AUBURN CF CAYUGA COUNTY | Construction - Building | 06/19/2014 |
Office of General Services - Design & Construction | DED941H |
$300,000.00
|
$89,027.00 |
10/15/2018 | 02/12/2019 | Investigate & Repair Leaks in 8 Inch Hot Water Heating Line Southport CF Chemung County | Construction - Building | 11/06/2018 |
Office of General Services - Design & Construction | DQ1682H |
$254,100.00
|
$245,812.00 |
07/03/2017 | 04/24/2018 | Repair Dampers, Buildings 1&2&4-6&10-12&14-17, Hutchings PC Syracuse Onondaga County | Construction - Building | 07/03/2017 |
Office of General Services - Design & Construction | DEE764G |
$175,000.00
|
$134,364.50 |
02/01/2022 | 09/09/2022 | Repair water main break Hughes State Office Bldg Syracuse Onondaga County | Construction - Building | 03/08/2022 |
Office of General Services - Design & Construction | DEB111H |
$300,000.00
|
$51,544.00 |
02/18/2010 | 02/26/2011 | REPAIR BROKEN VENTILATION SYSTEM ATTICA CF | Construction - Building | 08/20/2010 |
Office of General Services - Design & Construction | DEB209G |
$100,000.00
|
$83,750.00 |
05/06/2010 | 02/16/2011 | REPAIR BLOCKED SANITARY LINE BLDG 9 MID STATE CF | Construction - Building | 09/10/2010 |
Office of General Services - Design & Construction | DEB222P |
$200,000.00
|
$64,051.00 |
06/08/2010 | 03/29/2011 | INVESTIGATE/TEST/REPAIR LEAKING FUEL PIPING MID STATE CF | Construction - Building | 10/07/2010 |
Office of General Services - Design & Construction | D45826H |
$750,000.00
|
$0.00 |
05/17/2018 | 05/17/2021 | Job Order Contracting - Area 6 | Construction - Highway | 05/17/2018 |
Office of General Services - Design & Construction | DEB975H |
$300,000.00
|
$46,044.00 |
07/02/2012 | 10/30/2012 | CORRECT STEAM LINE JOINT FAILURES IN BLDG #75 @ GREATER BINGHAMTON HC | Construction - Building | 08/09/2012 |
Office of General Services - Design & Construction | DEB327P |
$300,000.00
|
$24,943.00 |
09/22/2010 | 01/20/2011 | RESTORE COLLAPSED STEAM TUNNEL BLDG 13 GREATER BINGHAMTON HEALTH CENTER | Construction - Building | 10/19/2010 |
Office of General Services - Design & Construction | D44215P |
$1,000,000.00
|
$523,223.00 |
08/30/2011 | 06/30/2015 | JOB ORDER CONTRACTING - AREA 5 | Construction - Building | 08/30/2011 |
Office of General Services - Design & Construction | DEB761H |
$300,000.00
|
$39,724.00 |
11/07/2011 | 03/06/2012 | DECOMMISSION HEATING SYSTEM FOR FACILITY CLOSURE CAMP GEORGETOWN | Construction - Building | 12/05/2011 |
Office of General Services - Design & Construction | DEB762P |
$300,000.00
|
$84,533.00 |
11/07/2011 | 03/06/2012 | DECOMMISSION WATER SYSTEM FOR FACILITY CLOSURE CAMP GEORGETOWN | Construction - Building | 12/08/2011 |
Office of General Services - Design & Construction | DEC560H |
$75,000.00
|
$27,797.00 |
02/13/2014 | 06/13/2014 | REPLACE COLLAPSED AIR DUCT MOHAWK VALLEY PC | Construction - Building | 03/21/2014 |
Office of General Services - Design & Construction | DEC931H |
$308,250.00
|
$308,250.00 |
05/18/2015 | 12/04/2015 | REPAIR LEAKING CONDENSATE RETURN LINE, GREATER BINGHAMTON HC | Construction - Building | 06/18/2015 |
Office of General Services - Design & Construction | D45295P |
$57,972.00
|
$56,581.00 |
01/29/2019 | 04/08/2021 | Upgrade Wastewater Treatment Plant Finger Lakes RC Tompkins County | Construction - Building | 01/29/2019 |
Office of General Services - Design & Construction | DED527G |
$200,000.00
|
$81,548.00 |
07/07/2017 | 11/04/2017 | Investigate/Repair Leaking Water Main Elmira CF Near Bldg 13 Chemung County | Construction - Building | 07/24/2017 |
Office of General Services - Design & Construction | D43473H |
$84,600.00
|
$82,167.00 |
07/18/2011 | 01/31/2014 | REPAIR ELEVATORS, BLDGS 1, 44,127, 131 & 136 WILLARD DRUG TREATMENT CENTER | Construction - Building | 07/18/2011 |
Office of General Services - Design & Construction | D43474H |
$1,819,051.00
|
$1,811,400.00 |
02/25/2010 | 07/31/2013 | REHAB HEATING SYSTEM BLDG 117 WILLARD CF | Construction - Building | 02/25/2010 |
Office of General Services - Design & Construction | DED610P |
$300,000.00
|
$184,925.00 |
10/12/2017 | 04/10/2018 | Replace domestic hot water tank, C Block Bldg. 152, Groveland CF Livingston County | Construction - Building | 11/10/2017 |
Office of General Services - Design & Construction | D46130H |
$664,000.00
|
$638,403.00 |
04/27/2020 | 08/31/2022 | Provide Classrooms & Office Space Bldg 38 Residential Rehab Unit Cayuga CF Cayuga County | Construction - Building | 04/27/2020 |
Office of General Services - Design & Construction | D46130P |
$294,110.00
|
$270,217.00 |
04/27/2020 | 08/31/2022 | Provide Classrooms & Office Space Bldg 38 Residential Rehab Unit Cayuga CF Cayuga County | Construction - Building | 04/27/2020 |
Office of General Services - Design & Construction | DEB721G |
$300,000.00
|
$107,864.00 |
10/12/2011 | 04/09/2012 | REPAIR LEAKING UNDERGROUND WATER MAIN GROVELAND CF | Construction - Building | 11/17/2011 |
Office of General Services - Design & Construction | DEB725H |
$110,436.00
|
$110,355.00 |
10/14/2011 | 10/27/2012 | REPAIR/REPLACE FAILING PIPE STANCHIONS WILLARD DRUG TREATMENT CENTER | Construction - Building | 02/29/2012 |
Office of General Services - Design & Construction | D45827H |
$750,000.00
|
$251,236.00 |
05/15/2018 | 05/15/2021 | Job Order Contracting Area 7 Service Contract (H) | Construction - Highway | 05/15/2018 |
Office of General Services - Design & Construction | D47116H |
$750,000.00
|
$304,595.34 |
09/07/2021 | 09/07/2024 | Job Order Contract Area 6 Jefferson Lewis & St Lawrence Counties | Construction - Building | 09/07/2021 |
Office of General Services - Design & Construction | D47365P |
$500,000.00
|
$0.00 |
02/14/2023 | 02/14/2025 | Job Order Contract plumbing work Area 5 multiple counties | Construction - Building | 02/14/2023 |
Office of General Services - Design & Construction | D47367P |
$500,000.00
|
$0.00 |
02/24/2023 | 02/24/2025 | Job Order Contract JOC plumbing work Area 7 multiple counties | Construction - Building | 02/24/2023 |
Office of General Services - Design & Construction | DEC620G |
$300,000.00
|
$167,446.00 |
04/25/2014 | 10/22/2014 | REPAIR BROKEN WATER MAIN GROVELAND CF LIVINGSTON CO | Construction - Building | 05/21/2014 |
Office of General Services - Design & Construction | DEC299H |
$75,000.00
|
$16,754.00 |
04/11/2013 | 08/09/2013 | REPAIR REPLACE FAILED BUILDING CONTROL SYSTEM PRINT SHOP ELMIRA CORRECTIONAL FACILITY | Construction - Building | 05/28/2013 |
Office of General Services - Design & Construction | DEE903G |
$300,000.00
|
$124,037.34 |
11/14/2022 | 04/28/2023 | Repair leaking heat line Bldgs 144 145 146 Mohawk CF Oneida County | Construction - Building | 03/06/2023 |
Office of General Services - Design & Construction | DEB703G |
$100,000.00
|
$41,539.00 |
09/26/2011 | 01/24/2012 | REPAIR/REPLACE FAILED STORM DRAIN BLDG 50 MOHAWK CF | Construction - Building | 11/17/2011 |
Office of General Services - Design & Construction | D45679H |
$2,749,200.00
|
$2,567,246.00 |
11/15/2017 | 07/10/2019 | Provide Building Upgrades Industry Secure Center Monroe County H | Construction - Building | 11/15/2017 |