Department/Facility | Contract Number | Current Contract Amount | Spending to Date | Contract Start Date | Contract End Date | Contract Description | Contract Type | Original Contract Approved/Filed Date |
---|---|---|---|---|---|---|---|---|
State University Construction Fund | T006061 |
$24,345,184.00
|
$24,345,184.00 |
03/27/2014 | 03/17/2018 | CHANGE ORDER 10 FOR CONTRACT T | Contracts Not Subject to OSC Pre-Audit | 04/08/2014 |
State University Construction Fund | T005981 |
$17,228,042.00
|
$17,223,042.00 |
07/23/2012 | 12/15/2014 | CHANGE ORDER 39 FOR CONTRACT T | Contracts Not Subject to OSC Pre-Audit | 07/26/2012 |
State University Construction Fund | T006174 |
$8,223,955.00
|
$8,223,955.00 |
10/08/2015 | 08/08/2018 | SUCF 11348 Renovate Sibley Ha | Contracts Not Subject to OSC Pre-Audit | 11/23/2015 |
State University Construction Fund | T006332 |
$4,627,041.00
|
$4,627,041.00 |
06/12/2017 | 12/31/2020 | SUCF12X371 Construct New Chil | Contracts Not Subject to OSC Pre-Audit | 06/13/2017 |
State University Construction Fund | T006133 |
$0.01
|
$0.00 |
04/08/2015 | 10/16/2016 | SUCF 23207 Replace Windows & | Contracts Not Subject to OSC Pre-Audit | 12/21/2015 |
State University Construction Fund | T006174 |
$0.01
|
$0.00 |
10/08/2015 | 08/08/2018 | SUCF 11348 Renovate Sibley Ha | Contracts Not Subject to OSC Pre-Audit | 12/21/2015 |
New York State Canal Corporation | D213949 |
$191,078.99
|
$0.00 |
08/23/2010 | 01/08/2012 | RETAINING WALL REPLACEMENT OLD CHAMPLAIN CANAL WATERFORD, NEW YORK | Construction - Miscellaneous | 08/23/2010 |
Office of Parks Recreation & Historic Preservation | D005243 |
$3,471,900.00
|
$92,951.04 |
11/02/2017 | 05/31/2018 | Concession Building Replacement & Site Improvements Southwick Beach State Park Jefferson Co GC | Construction - Building | 11/02/2017 |