Department/Facility | Contract Number | Current Contract Amount | Spending to Date | Contract Start Date | Contract End Date | Contract Description | Contract Type | Original Contract Approved/Filed Date |
---|---|---|---|---|---|---|---|---|
Office of General Services - Design & Construction | DED204V |
$300,000.00
|
$38,889.00 |
04/26/2016 | 08/24/2016 | REPAIR TRANSFORMER, SAGAMORE CPC | Construction - Building | 06/08/2016 |
Office of Parks Recreation & Historic Preservation | D005332 |
$401,727.00
|
$392,227.00 |
09/12/2018 | 12/15/2020 | Carousel Bldg Electrical Service Upgrade Hempstead Lake State Park Nassau County | Construction - Building | 09/12/2018 |
Office of General Services - Design & Construction | DEC087E |
$150,000.00
|
$1,184.00 |
10/31/2012 | 02/28/2013 | PROVIDE TEMPORARY ELECTRICAL POWER MELVILLE ESTATES LONG ISLAND DDSO | Construction - Building | 12/04/2012 |
Office of General Services - Design & Construction | DEB895V |
$272,171.00
|
$271,207.00 |
04/26/2012 | 07/30/2013 | REPLACE FIRE DAMAGED SWITCHGEAR B BUILDING 132 PILGRIM PC | Construction - Building | 06/19/2012 |
Office of General Services - Design & Construction | DED181E |
$100,000.00
|
$42,007.00 |
03/18/2016 | 11/02/2016 | Provide 30kw Rental Generator DOT Reg.10 Maint. Office Garden City Nassau Co. Emergency Electr. Work | Construction - Building | 06/08/2016 |
Office of General Services - Design & Construction | DEB273V |
$300,000.00
|
$287,361.00 |
07/22/2010 | 05/29/2011 | PROVIDE TEMPORARY GENERATORS & REPAIR CONDUITS ROBERT MOSES SP | Construction - Building | 11/17/2010 |
Office of General Services - Design & Construction | DED262V |
$300,000.00
|
$20,652.00 |
07/22/2016 | 11/19/2016 | Investigate & Restore Primary Electric, Toll Plaza Sunken Meadow State Park | Construction - Building | 08/25/2016 |
Office of General Services - Design & Construction | DEB247V |
$300,000.00
|
$271,675.00 |
06/28/2010 | 05/29/2011 | RESTORE FAILED ELECTRICAL POWER ROBERT MOSES SP | Construction - Building | 10/29/2010 |
Office of General Services - Design & Construction | D46089E |
$1,551,044.00
|
$1,538,861.00 |
08/24/2021 | 03/11/2024 | Replace emergency generator and transfer switches Bldg 20 26 72 101 702 Pilgrim PC Suffolk County | Construction - Building | 08/24/2021 |
Office of General Services - Design & Construction | D43950E |
$26,200.00
|
$24,516.10 |
03/19/2010 | 03/29/2011 | DEMOLISH SALT DOME & LOADER BARN DOT REGION 10, MELVILLE | Construction - Building | 10/07/2010 |
Office of General Services - Design & Construction | D43980E |
$43,250.00
|
$39,750.00 |
07/02/2010 | 07/28/2011 | PROVIDE SALT STORAGE BLDG MAINT SUBHEADQUARTERS DOT REGION 10, HAUPPAUGE | Construction - Building | 07/02/2010 |
Office of General Services - Design & Construction | D43225E |
$1,287,898.00
|
$1,257,908.00 |
08/28/2008 | 03/29/2013 | PROVIDE SMOKE ALARM, SMOKE DETECTION & EMERGENCY VOICE EVACUATION SYSTEM @ SUFFOLK SOB | Construction - Building | 02/08/2012 |
Office of General Services - Design & Construction | DEB653V |
$100,000.00
|
$25,794.00 |
09/01/2011 | 12/30/2011 | RESTORE FAILED ELECTRICAL SERVICE HECKSCHER SP | Construction - Building | 09/16/2011 |
Office of General Services - Design & Construction | DEB655V |
$300,000.00
|
$95,350.00 |
09/01/2011 | 01/31/2012 | REPAIR FAULTS IN POWER DISTRIBUTION SYSTEMS SUNY OLD WESTBURY | Construction - Building | 03/02/2012 |
Office of General Services - Design & Construction | DEC133V |
$300,000.00
|
$238,220.00 |
11/23/2012 | 06/30/2013 | INVESTIGATE & RESTORE POWER WEST SIDE ROBERT MOSES SP | Construction - Building | 12/13/2012 |
State University Construction Fund | T005527 |
$240,261.00
|
$240,261.00 |
06/02/2009 | 05/07/2011 | REHAB MECHANICAL SYSTEMS - LIFE SCIENCE BUILDING SUCF 13B68 SUNY STONY BROOK | Contracts Not Subject to OSC Pre-Audit | 05/04/2011 |
Office of Parks Recreation & Historic Preservation | D006014 |
$453,128.00
|
$322,084.97 |
11/23/2022 | 07/05/2024 | Bayard Cutting Arboretum State Park parking lot and visitor center Suffolk County | Construction - Building | 11/23/2022 |
Office of General Services - Design & Construction | DEB864V |
$300,000.00
|
$45,147.00 |
02/27/2012 | 06/26/2012 | RESTORE FAILED ELECTRICAL POWER FEEDER AND RELATED EQUIPMENT PILGRIM PC | Construction - Building | 06/20/2012 |