Vendor Name: VERDE ELECTRIC CORP
Agency Name: General Services, Office of
Department/Facility Name: Office of General Services - Design & Construction
Contract Number: DM3041E
Current Contract Amount: $1,252,411.00
Spending to Date: $1,248,576.00
Contract Type: Construction - Building
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $1,135,100.00 |
03/20/2014 | 11/25/2016 | RESTORE ELECTRICAL SYSTEMS SING SING CF | 03/20/2014 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $8,376.00 |
68137 removal of exsisting buried concrete slab at electric vault Sing SingSeq 1 | 02/11/2015 | |
Amendment | $51,590.00 |
68190 concrete encased ductbank from HVS to transformer, Restore Failed Electrical @ Sing Sing | 05/29/2015 | |
Amendment | ($3,432.00) |
68774 Removal installation sump pump in electrical vault Sing Sing Westchester Co seq 3 | 06/17/2015 | |
Amendment | $41,732.00 |
12/13/2016 | Revision of MDP 13 main circuit Super Storm Sandy Filed 112 Exempt | 06/26/2015 |
Amendment | $4,182.00 |
12/13/2016 | 69554 Add'l chain link fence and 8' wide swing gates Hurricane Sandy Sing Sing CF filed 112 Exem | 01/06/2016 |
Amendment | $14,863.00 |
12/13/2016 | 69553 Key interlock Vista Switchgrear Sing Sing CF | 02/12/2016 |