Vendor Name: SCHENECTADY HARDWARE & ELEC CO INC
Agency Name: General Services, Office of
Department/Facility Name: Office of General Services - Design & Construction
Contract Number: D44808E
Current Contract Amount: $5,756,273.00
Spending to Date: $5,747,181.00
Contract Type: Construction - Building
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $4,606,400.00 |
02/27/2014 | 05/23/2015 | Renovate Building 5 @ Harriman State Office Campus, Albany | 02/27/2014 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $56,636.00 |
C.O. #1 Modification to Temporary Power service | 06/26/2014 | |
Amendment | $4,617.00 |
CO#2, Control#67763 - Switchgear Houskeeping Pad, Renovate Bldg 5 @ Harriman State Office Campus | 08/25/2014 | |
Amendment | $75,310.00 |
08/21/2015 | CO# 3 67945 Provide Electrical risers State OB Campus Renovate Bld 5 | 10/24/2014 |
Amendment | ($1,735.00) |
CO# 6 67947 Modify FA Programming & Credit Motor Disconnects Harriman SO Bld 5 | 10/20/2014 | |
Amendment | $34,032.00 |
CO# 5 68025 Loss of wire salvage State OB Campus Renovate Bld 5 | 11/03/2014 | |
Amendment | $190,738.00 |
Control#68039, CO#8 - Increase for Premium Time to Maintain Project Schedule | 12/18/2014 | |
Amendment | $96,560.00 |
Control#67891 - Lighting Modifications (2nd resubmittal), Renovate Bldg 5 at Harriman Campus | 12/30/2014 | |
Amendment | ($6,330.00) |
Control#68297, CO#10- Credit upper canopy fixtures & duct smoke detectors, Renovate Bldg 5, Harriman | 12/26/2014 | |
Amendment | $415,089.00 |
Control#68417, CO#11 - Conduit to Replace Use of Walker Duct, Renovate Bldg 5 @ Harriman Campus | 02/03/2015 | |
Amendment | $175,190.00 |
Control#68541 CO#12 - Add'l power/data&relocate Renovate Bldg 5 @ Harriman State Office Campus | 03/13/2015 | |
Amendment | $16,476.00 |
08/26/2015 | Control#68616 CO#13 - Revise 3rd Fl power/data Renovate Bldg 5 @ Harriman State Office Campus | 03/13/2015 |
Amendment | $58,295.00 |
Control#68643 CO#14 - Modify lighting Renovate Bldg 5 @ Harriman State Office Campus | 03/13/2015 | |
Amendment | $0.00 |
09/10/2015 | Control#68541A - NCTE Renovate Bldg 5 @ Harriman State Office Campus | 03/13/2015 |
Amendment | $915.00 |
Control#68676 CO#15 Receptacles - Renovate Bldg 5 @ Harriman State Office Campus | 03/24/2015 | |
Amendment | $0.00 |
09/20/2015 | CO#68765 NCTE Renovate Bldg 5 @ Harriman State Office Campus Albany | 04/16/2015 |
Amendment | $3,873.00 |
Control#68659, CO#18-Add 3rd floor power/data, Renovate Bldg 5 @ Harriman State Office Campus Albany | 04/20/2015 | |
Amendment | $5,834.00 |
Control#68772, CO#24 - Riser Panel Removal, Renovate Bldg 5 @ Harriman State Office Campus Albany | 04/20/2015 | |
Amendment | $4,895.00 |
Control#68683,CO#19-Elevator Sump Pit Electrical-Renovate Bldg 5@Harriman State Office Campus Albany | 04/20/2015 | |
Amendment | $4,592.00 |
Control#68684, CO#22 - Penthouse Exit Signs, Renovate Bldg 5 @ Harriman State Campus | 04/20/2015 | |
Amendment | $2,491.00 |
Control#68700, CO#20 - Vestibule G01 Electrical Devices, Renovate Bldg 5, Harriman State Campus | 04/20/2015 | |
Amendment | $2,707.00 |
Control#68780, CO#21 - Ground Floor Fire Alarm Revisions, Renovate Bldg 5 @ Harriman State Campus | 04/20/2015 | |
Amendment | $870.00 |
Control#68735, CO#23 - Provide Power for DDC Controls for AHU 4, Renovate Bldg 5 @ Harriman Campus | 04/20/2015 | |
Amendment | $498.00 |
Control#68804,CO#25-Add'l elevator pump circuit,Renovate Bldg 5@Harriman State Office Campus Albany | 04/20/2015 | |
Amendment | $2,443.00 |
Control#68696,CO#26-Elevator heat detectors, Renovate Bldg 5@Harriman State Office Campus Albany | 04/22/2015 | |
Amendment | $4,007.00 |
Control#68834 CO#28-Ground flr enclave lighting, Renovate Bldg 5@Harriman State Office Campus Albany | 04/28/2015 | |
Amendment | $6,365.00 |
Control#68833,CO#27-Modify site lighting ctrls, Renovate Bldg 5@Harriman State Office Campus Albany | 04/29/2015 | |
Amendment | $3,247.00 |
Control#68835,CO#30 - Bldg Mgr Suite power feed, Renovate Bldg 5@Harriman State Office Campus Albany | 05/06/2015 | |
Amendment | ($316.00) |
Control#68699, CO#30-Lighting modify Penthouse, Renovate Bldg 5@Harriman State Office Campus Albany | 05/11/2015 | |
Amendment | $993.00 |
Control#68855, CO #32 - Relocate exit signs, Renovate Bldg 5 @ Harriman State Office Campus Albany | 05/08/2015 | |
Amendment | ($14,749.00) |
Control#68783, CO #31 - Visit Mgmt System, Renovate Bldg 5 @ Harriman State Office Campus Albany | 05/14/2015 |