Vendor Name: LO SARDO GEN CONTRS INC
Agency Name: General Services, Office of
Department/Facility Name: Office of General Services - Design & Construction
Contract Number: D43350C
Current Contract Amount: $8,185,498.00
Spending to Date: $8,173,494.00
Contract Type: Construction - Building
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $6,960,000.00 |
06/26/2013 | 07/13/2014 | REHABILITATE FACADE - CONSTRUCTION | 06/26/2013 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $319.00 |
CO#1 Ctl #67338 Rehab Facade AC Powell State OB NY, NY Limestone Soffit Panels Overhanging Plaza Lvl | 06/20/2014 | |
Amendment | ($5,347.00) |
04/13/2015 | CO#2 Ctl#67523 TE Realign Items-Rehab Facade AC Powell SOB Limestone Soffit Panels Overhng Plz Lvl | 08/20/2014 |
Amendment | $411.00 |
CO#3 Ctl#67696-Corrective Action-Rehab Facade AC Powell SOB Limestone Soffit Panels Overhng Plz Lvl | 10/17/2014 | |
Amendment | $20,319.00 |
08/01/2015 | CO#7 Ctl#68608-Stone Repair&ExtCED-Rehab Facade AC Powell SOB Limestone Soffit Panel Overhng Plz Lvl | 03/24/2015 |
Amendment | $27,494.00 |
08/31/2015 | CO#6 Ctl#68074-Floor Drains&ExtCED-Rehab Facade AC Powell SOB Limestone Soffit Panel Overhng Plz Lvl | 03/24/2015 |
Amendment | $8,643.00 |
CO#8 Ctl#68615-Clean Soffit&Panels-Rehab Facade AC Powell SOB Limestone Soffit Panel Overhng Plz Lvl | 05/12/2015 | |
Amendment | $12,821.00 |
CO#9 Ctl#68631-Supercolumn C Repair-Rehab Facade ACPowell SOB Limestone Soffit Panel Overhng Plz Lvl | 05/15/2015 | |
Amendment | $210,268.00 |
10/10/2015 | CO10 Ctl 68672-Wall Part.Rep.&Remove-Rehab Facade ACPowell SOB Soffit Panel Overhng Plz Lvl | 06/11/2015 |
Amendment | $10,903.00 |
CO11Ctl69075-Granite@SupercolumnE&F-Rehab Facade ACPowell SOB Limestone Soffit Panel Overhng Plz Lvl | 07/16/2015 | |
Amendment | $26,918.00 |
CO12Ctl69074-Addl Restor. N&W Facade-Rehab Facade ACPowell SOB Limestone Soffit Panel Ovrhng Plz Lvl | 07/30/2015 | |
Amendment | $55,766.00 |
11/09/2015 | CO#13 Ctl#69055-Window Filed Testing-Rehab Facade ACPowell SOB Limestone Soffit Panel Ovrhng Plz Lvl | 09/10/2015 |
Amendment | $0.00 |
03/31/2016 | CO#15 Ctl#69677-5 Month NCTE-Rehab Facade AC Powell SOB Limestone Soffit Panel Overhang Plaza Level | 12/22/2015 |
Amendment | $289,959.00 |
03/31/2016 | CO#14Ctl#69329-Int.Window Caulk-Rehab Facade AC Powell SOB Limestone Soffit Panel Overhang Plaza Lvl | 12/30/2015 |
Amendment | $19,486.00 |
03/31/2016 | CO#16Ctl#69619-Addl Dutchman Repair-Rehab Facade AC Powell SOB Limestone Soffit Overhang Plaza Level | 02/10/2016 |
Amendment | $0.00 |
06/30/2016 | CO#19-Ctl#70180-Three Month NCTE-Rehab Facade AC Powell SOB Limestone Soffit Overhang Plaza Level | 05/26/2016 |
Amendment | $227,226.00 |
06/30/2016 | CO# 69875, SPALL AND CRACK REPAIR, REHABILITATE FACADE - CONSTRUCTION | 06/09/2016 |
Amendment | $37,144.00 |
06/30/2016 | CO#18-Ctl#69964-Repair Windows&Roof-Rehab Facade AC Powell SOB Limestone Soffit Overhang Plaza Level | 06/22/2016 |
Amendment | $283,168.00 |
06/30/2016 | CO# 70865, Delay Claim, Rehab Facade AC Powell State Office Building | 03/16/2017 |