Vendor Name: HUDSON VALLEY ELECTRICAL CONSTRUCTION & MAINTENANCE INC
Agency Name: General Services, Office of
Department/Facility Name: Office of General Services - Design & Construction
Contract Number: D42535E
Current Contract Amount: $11,031,488.00
Spending to Date: $10,840,805.00
Contract Type: Construction - Building
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $9,998,111.00 |
04/16/2013 | 04/16/2015 | ELECTRICAL SYSTEM INFRASTRUCTURE UPGRADES ELECTRICAL WORK GREENHAVEN CORRECTIONAL FACILITY | 04/16/2013 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $55,000.00 |
06/15/2015 | CO#1 67476 TE&Temp storage of generators/switchgr, prov unloading/reload Elec Upgrd Greenhaven CF | 08/01/2014 |
Amendment | $36,075.00 |
CO#2 - Resubmission, open cut excavate, Rt 216, electrical system upgrades, Greenhaven CF | 10/15/2014 | |
Amendment | $112,758.00 |
07/15/2015 | CO#4, control 67829 - Add work and TE, electrical system upgrades, Greenhaven CF. | 12/31/2014 |
Amendment | $32,496.00 |
CO#5, control 68296. Added mods, electrical infrastructure upgrades, electrical work, Greenhaven CF | 03/16/2015 | |
Amendment | $5,938.00 |
07/30/2015 | CO#7, control 68839. Add service switch, electrical syst upgrades, Greenhaven CF (E) | 06/03/2015 |
Amendment | $0.00 |
10/28/2015 | CO#16, control 69170. NCTE, electrical system upgrades, Greenhaven CF (E) | 07/21/2015 |
Amendment | $7,287.00 |
11/27/2015 | 69039 PROV 3/4" RMC FROM GEN 1 & 2 Green Haven CF | 07/30/2015 |
Amendment | $47,543.00 |
12/07/2015 | 69059 Bldg 1 main dist panel provide MDP and all materials required Green Haven CF | 07/30/2015 |
Amendment | $17,218.00 |
12/17/2015 | 69057 ON UTILITY SERVICE POLE, PROV Green Haven CF | 07/30/2015 |
Amendment | $45,421.00 |
01/16/2016 | 68990 Provide lighting modifications Green Haven CF | 07/30/2015 |
Amendment | $28,441.00 |
68296A Reimburse contractor add't NYSEG costs A Green Haven CF seq 12 | 08/05/2015 | |
Amendment | $55,791.00 |
02/15/2016 | 69060 from remote radiators to generator engine and 30 day time ext Green Haven CF | 08/19/2015 |
Amendment | $102,068.00 |
05/15/2016 | Control# 68845 AB & EF recreation yards changes and time extension, Green Haven CF | 09/15/2015 |
Amendment | $10,452.00 |
06/14/2016 | 68988 Provide work and materials electrial work Bldg 13 Time extension | 09/16/2015 |
Amendment | $62,773.00 |
07/14/2016 | CO 18 69056 on all towers reinstalled conduits on the inside of secure perimeter. Greenhaven cf | 11/19/2015 |
Amendment | $24,302.00 |
08/13/2016 | 42535E Greenhaven CF Bldg 13 Existing panel boards were mis labeled, 30 day extension | 12/22/2015 |
Amendment | $46,330.00 |
08/13/2016 | 69415 Upgrade electrical panel | 01/20/2016 |
Amendment | $17,804.00 |
08/13/2016 | CO 22 69414 Provide Electric Upgrade-0022 | 01/28/2016 |
Amendment | $15,419.00 |
08/28/2016 | 69413 Time Extension and provide all modifications to add alternator Green Haven CF | 02/03/2016 |
Amendment | $6,529.00 |
08/28/2016 | CO#69578 Electrical System Infrastructure Upgrades Green Haven CF Dutchess Co | 02/11/2016 |
Amendment | $98,987.00 |
08/28/2016 | CO#18 69416 Electrical System Infrastructure Upgrades Green Haven CF, Dutchess Co | 03/01/2016 |
Amendment | $0.00 |
01/29/2017 | CO 25 70648 No cost time extension Green Haven CF | 10/07/2016 |
Amendment | $139,334.00 |
09/01/2017 | CO 26 70754 addt'l power feed from Powerhouse Bldg 24 to addt'l bldgs Greenhaven CF | 04/27/2017 |
Amendment | $17,126.00 |
09/01/2017 | CO 27 #71375 one day onsite training newly installed switch gear Green Haven CF | 07/06/2017 |
Amendment | $3,194.00 |
CO 28 #71592 remove nonhazardous/used transformer oil 2 decommissioned transformers Green Haven CF | 08/29/2017 | |
Amendment | $0.00 |
03/31/2018 | CO 33 #71806 Time extension Provide Electric Upgrade for feeders etc ,Greenhaven CF | 10/26/2017 |
Amendment | $7,682.00 |
CO #30 71375A electric upgrade for feeders, transformers, switchgear, sitewide Green Haven | 11/01/2017 | |
Amendment | $2,475.00 |
CO# 29 71717 Electric Upgrade for feeders, transformers and switchgear,Green Haven CF | 11/07/2017 | |
Amendment | $26,587.00 |
C0#32 71826 Provide Electric Upgrade for feeders, transformers/switchgear, GreenHaven CF | 11/10/2017 | |
Amendment | $8,347.00 |
CO#35 71833 Provide Electric Upgrade for feeders, transformers/switchgear Green Haven CF | 01/30/2018 |